HomeMy WebLinkAbout1996-02-13 Min - Board MEMORANDUM
Date : February 13 , 1996
From: Mike
To: Dave
Subject : Activities for January 1996
The following listing provides a brief description of the various
projects I was involved with during January. I have included a
status report in the boxes following each project .
Truckee Diner
�-* * This project is located at the corner of West River
Street and Highway 267 . The project proposes construction of a
restaurant (phase 1) and a nine unit commercial building (phase
2) . At this time only phase 1 is expected to be constructed this
year.
Recommendation for final acceptance was made.
Truckee Falls
* This project is located on Northwoods Blvd. between
White Fir Trail and Lausanne Way. The project proposes
construction of an eighteen hole golf course and associated
structures .
I met with representatives of the project as well as other
involved agencies . Work for this project is in progress.
Donner Lake Plaza
* This project is located in the Donner Gate area between
the Chevron station and the Beginning restaurant .This will be a
6200 s . f . commercial building. The U-Haul rental business will be
relocated to this location.
Recommendation for final acceptance was made.
Page 1 1996 Activities List Project List February 13, 1996
Donner Village Condos
* This project is located in Tahoe Donner on Northwoods
Blvd. This will be a 14 unit condo complex built on two parcels
that have been combined.
Recommendation for final acceptance was made.
Porter Simon Building
* This commercial building replaced the building
destroyed by the explosion downtown.
Recommendation for final acceptance was made.
89/80 Properties
* This project is located on Sha Neva Road near the
Forest Service office and the Sanders Well Site. The developers
are proposing construction of retail/commercial/mini storage
improvements .
Results of the modeling work performed by Sauers Engineering
was provided to the developers. Work for this project is in
progress .
Eagle Court
* This is a 4 unit condominium project located on
Northwoods Blvd. in Tahoe Donner.
The draft development agreement was completed and provided to
the developer. We are awaiting the developer' s comments .
Coachland Mobile Home Park Expansion
* Phase one of this project provided for the installation
of a single 6" metered service for the ultimate expansion of the
mobile home park. This consolidated single point of service
allowed for the removal of multiple smaller diameter metered
services .
Recommendation for final acceptance was made.
Porter Simon Building
* This commercial building replaced the building
destroyed by the explosion downtown.
Recommendation for final acceptance was made.
Page 2 1996 Activities List Project List February 13, 1996