The regular meeting of the Board of Directors of the Truckee Donner Public Utility District
was called to order at 6:00 PM in the TDPUD Board room by President Hemig.
ROLL CALL: Directors Joe Aguera, Jeff Bender, Ron Hemig, and John Hillstrom were
present. Director Pat Sutton was absent.
PLEDGE OF ALLEGIANCE
Steve Gross led the Board and public in the Pledge of Allegiance.
EMPLOYEES PRESENT: Nancy Waters, Kathy Neus, Steven Poncelet, Joe Horvath,
Jim Wilson, Mary Chapman, Jim Wilson, Neil Kaufman, Michael Holley and Barbara Cahill
CONSULTANTS PRESENT: Steve Gross
OTHERS PRESENT: Juanita Schneider, Dan Warren, Ryan Holland and Judy Holland
CHANGES TO THE AGENDA
General Manager Holley asked to pull all the Closed Session Item No.'s 17, 18 and 19.
Mr. Holley asked the Board to move the action item dealing with the Net Metering revision
after the public hearing.
President Hemig announced that the Board will not convene for the first meeting in January
2010
PUBLIC INPUT
Dan Warren said a Glenshire homeowner remarked that the PUD should rebate people for
old strings of Christmas lights they are no longer going to use.
DIRECTOR UPDATE
Director Hemig said he is going to attend the JPA Municipal Utility Financing Authority
meeting on December 9th in Susanville with UAMPS and Lassen MUD.
PUBLIC HEARING: ORDINANCE AND RESOLUTION TO CHANGE NET METERING OF
CUSTOMER OWNED SOLAR AND WIND POWER PRODUCTION SYSTEMS
President Hemig opened the public hearing and asked for public input.
1 Minutes: December 2, 2009
Ryan Holland stated he is concerned about moving the evaluation month to March and its
affect on the losing two months of the banked generation.
President Hemig asked staff to clarify the change with Mr. Holland. There were no additional
public comments. The public hearing was closed.
ACTION ITEM
CONSIDERATION OF ADOPTING AN ORDINANCE TO AMEND SCHEDULE NM, NET
METERING AND RESOLUTION TO AMEND DISTRICT CODE, TITLE 7.64.020.3 (B) This
item relates directly to the District's Net Metering Agreement for the evaluation and
reconciliation month.
Director Bender moved, and Director Aguera seconded, that the Board adopt an Ordinance
revising Schedule NM, Net Metering and rescind Ordinance No. 2008-06; and approve a
resolution amending the Net Metering chapter in Title 7, Electric Service
ROLL CALL: Director Sutton, absent; All other Directors aye, by voice vote. SO MOVED
CONSENT ITEM
CONSIDERATION OF 2010-2011 LABOR AGREEMENTS
A. TDPUD EMPLOYEES REPRESENTED BY IBEW 1245
B. TDPUD UNREPRESENTED EMPLOYEES
Director Hillstrom moved, and Director Bender seconded, that the Board approve the consent
calendar.
ROLL CALL: Director Sutton, absent; All other Directors aye, by voice vote. SO MOVED
SPECIAL BUSINESS
ELECTION OF OFFICERS OF THE BOARD This item involves election of the President
and vice President of the Board for the next twelve months.
The Board by acclamation and consensus appointed Jeff Bender as President of the Board.
Director Sutton was absent. All other Directors, aye. SO MOVED
The Board by acclamation and consensus appointed John Hillstrom as vice President of the
Board. Director Sutton was absent. All other Directors, aye. SO MOVED
ACTION ITEMS
CONSIDERATION OF A RESOLUTION ACCEPTING FINAL COMPLETION OF THE
COVERED PARKING- CARPORT STRUCTURE #3 PROJECT This item involves the
closeout of the TDPUD Covered Parking-Carport Structure #3 project and recording of
the Notice of Completion.
Director Hillstrom moved, and Director Aguera seconded, that the Board adopt a resolution ac-
cepting the Covered Parking Project as complete and authorize filing of the Notice of Completion
ROLL CALL: Director Sutton, absent; All other Directors aye, by voice vote. SO MOVED
2 Minutes: December 2, 2009
. . CONSIDERATION OF THE AWARD OF A CONSTRUCTION CONTRACT FOR THE
DONNER LAKE TRANSMISSION LINE POLE REPLACEMENT PROJECT This item
concerns the possible award of a construction bid for the Donner Lake Transmission
Line Pole Replacement Project.
Director Hemig moved, and Director Aguera seconded, that the Board award the Donner Lake
Transmission Line Pole Replacement Project contract to PAR Electrical Contractors in the amount of
$67,950 including a 10% change order allowance of $6,800 for a total not-to-exceed amount of
$74,750.
ROLL CALL: Director Sutton, absent; All other Directors aye, by voice vote. SO MOVED
CONSIDERATION OF A FINAL COMPLETION AND A CLOSEOUT CHANGE ORDER FOR
THE DISTRICT PIPELINE REPLACEMENT PROJECT — 2009- CONTRACT A This item
involves the closeout of 2009 Water Pipeline Replacement Project A with Hunt
Construction and recording the Notice of Completion.
Director Hillstrom moved, and Director Hemig seconded, that the Board authorize Contract
Change Order No. 4 to the District Pipeline Replacement — 2009 — Contract A project in a deductive
amount of $45,321.11; and adopt a resolution accepting the District Pipeline Replacement — 2009 —
Contract A project as complete and authorize the filing of the Notice of Completion.
ROLL CALL: Director Sutton, absent; All other Directors aye, by voice vote. SO MOVED
CONSIDERATION OF A FINAL COMPLETION AND A CLOSEOUT CHANGE ORDER FOR
THE DISTRICT PIPELINE REPLACEMENT PROJECT — 2009- CONTRACT B This item
involves the closeout of 2009 Water Pipeline Replacement Project B with Hunt
Construction and recording the Notice of Completion.
Director Hillstrom moved, and Director Hemig seconded, that the Board authorize Contract
Change Order No. 9 to the District Pipeline Replacement — 2009 — Contract B project in a deductive
amount of $310,722.20; and adopt a resolution accepting the District Pipeline Replacement — 2009 —
Contract B project as complete and authorize the filing of the Notice of Completion.
ROLL CALL: Director Sutton, absent; All other Directors aye, by voice vote. SO MOVED
APPROVAL OF CEQA INITIAL STUDY FOR 2010 PIPELINE REPLACEMENT PROJECT
This item involves a CEQA Review of the District Pipeline Replacement— 2010 Project.
Director Hemig moved, and Director Aguera seconded, that the Board authorize staff to file the
proposed negative declaration and environmental initial study with the Office of the Nevada County
Clerk; authorize staff to file the proposed negative declaration and environmental study with
responsible and interested agencies and with the State Clearinghouse; and set a public hearing date
of December 16, 2009
ROLL CALL: Director Sutton, absent; All other Directors aye, by voice vote. SO MOVED
3 Minutes: December 2, 2009
WORKSHOP
REVIEW OF THE 2009 CONSERVATION PROGRAMS AND REBATES This item is a
review of the 2009 conservation Programs and Rebates
Steven Poncelet gave a presentation:
• FY09 Conservation Programs
o Existing energy programs
o Added new energy conservation programs
o New water conservation program
• Staff working to optimize and develop programs
• Planned FY09 Conservation Programs:
Energy Programs Water Programs
1. Million CFL 1. Green Partners
2. Residential Rebates 2. TDPUD Water Wise Demonstration Garden
3. Commercial Rebates 3. Web-Based Water Wise Garden Resource
4. Refrigerator Recycling 4. Smart Water Controllers
5. Business Green Partners 5. Water-Efficient Toilets
6. Green Schools Program
7. Green Builders
8. Low/Moderate Income Assistance Program
9. LED Holiday Light Exchange
10. Green Challenge
11. "Keep Your Cool" Commercial Refrigeration
12. LED/CFL MR-16 Business Lighting Pilot
13. Commercial LED Exit Sign Retrofit
14. Residential Green Partners
15. Home & Business Electronics Education
16. Portable/Take Home Energy Metering
• Additional FY09 program
o Energy Savings Program (ESP)
o Customer Leak Repair Rebates
o TDPUD Building Energy Efficiency
• Other Public Information & Conservation Department activities
o Public Information
o Legislative & Regulatory (L&R)
o Website
• Conservation Department is on schedule and working to optimize & develop programs
0 7 new energy programs
0 4 new water programs
o Existing programs doing well
o Strong community presence
o Program development will pay off fully in FY10+
o Projecting a small budget surplus, -5% under budget
• Existing energy programs YTD results (through Oct. 09)
o Appliance Rebates: 480 (350 goal)
o Million CFL: 40,000 lights (50,000 goal)
o Business Green Partners: 110 customers (200 goal)
4 Minutes: December 2, 2009
o Commercial Lighting Rebates: $17K ($40K goal)
o LED Holiday Light Exchange: tbd (500 customer goal)
o Over 2-dozen community events and presentations
• New energy programs YTD results (through Oct. 09)
o Residential Green Partners: 200 customers (200 goal)
• Over 2,000 lights
o LED MR-16 Business Lighting Pilot: 14 customers (12 goal)
o Keep Your Cool: $30K/22 customers ($30K goal)
• Extra $20K by end of year
o TDPUD Building Energy Efficiency: Study by Dec. 15, 2009
o Energy Saving Program (ESP): Over 30 customers first-month (200 goal mid-2010)
o Commercial LED Exit sign and Green Challenge underway
• New Water programs YTD results (through Oct. 09)
o Smart Water Controllers: $30K/11 customers ($30K budget)
• Will evaluate program results next summer
o TDPUD Water Wise Demonstration Garden: completed
• Web-based tool and informational signage to come
o Customer Leak Repair Rebate: 9 customers
• Promoted through leak repair letters
• Will grow with water meter project
• Water meter project key driver: new water rates & side-by-side billing
• Took the place of Water Efficient Toilet program
There was no public input.
Board discussion:
• Is there a sense of participation from second homeowners
• Leak rebate- are we going to advise owner
• Can see the value in interaction with customers- opportunity to build relationships and
inform about programs
• How often do leak letters go out- sending too often would get annoying- limit to 3
reminders- or use bill stuffers
• Is stimulus money going to be used to follow through with the District building energy
analysis
• Like the Glenshire idea to turn in old unused light for a rebate
• Are the appliance rebates in demand- wonder if there is much of a EMV payoff with
second homeowners
• Could we ask for a better than Energy Star efficiency to receive a rebate- go to a
higher standard
• Water heater rebate- how does a customer figure out which one to purchase
• Can regular CFL's be used with a dimmer switch
• When will the Building Energy Use Assessment by Enovity be completed and presented
to the Board as a workshop
• Is a $100 plumber rebate for the leak program enough- what was the average cost
customers paid to fix leaks
5 Minutes: December 2, 2009
CLOSED SESSION
Closed session Items were pulled from the agenda.
CLOSED SESSION PURSUANT TO GOVERNMENT CODE SECTION 54956.9,
SUBDIVISION (A), EXISTING LITIGATION: CLAIMS OF PACIFIC RIM CONSTRUCTION,
INC. AND ADVANCED ASPHALT
CONFERENCE WITH LABOR NEGOTIATOR: SECTION 54957.6 OF THE GOVERNMENT
CODE. DISTRICT REPRESENTATIVE: MICHAEL D. HOLLEY;
a. Employee representative: IBEW Local 1245
b. Unrepresented Employees
CLOSED SESSION PURSUANT TO GOVERNMENT CODE SECTION 54956.9,
SUBDIVISION (B), POTENTIAL LITIGATION, ONE CASE
RETURN TO OPEN SESSION
Report on closed session
ADJOURNMENT
There being no further business before the Board, the meeting was adjourned at 7:32 PM.
TRUCKEE BLIC UTILITY DISTRICT
Jeff B nder resi ent
Prepared by �C
Barbara Cahill, Deputy District Clerk
6 Minutes: December 2, 2009