HomeMy WebLinkAbout1974-04-02 Min - Board APRIL 2 , 1974
The regular meeting of the Board of Directors of the Truckee-Donner
Public Utility District was called to order by the president at 7 : 30
p.m. in the conference room.
ROLL CALL: J. Craig, present; D. Anderson, present ; P. Sutton,
present; R. Anderson, present ; R. Waters , present.
EMPLOYEES PRESENT: Paulus , Kinzie , Krajewski , Silva, Grow
.--. GUESTS PRESENT: Attorney Joynt, E. A. Hamilton, A. J. Witting
MINUTES OF MARCH 19 , 1974
The president asked if there were any additions , corrections , or
omissions to the minutes of March 19 , 1974. It was moved by Director
R. Anderson and seconded by Director Sutton that the minutes be
accepted as written. All aye; motion carried.
The minutes of March 26 will be held over to the next regular meeting.
BILLS FOR BOARD' S APPROVAL
After Questioning a few of the bills , it was moved by Director Craig
and seconded by Director R. Andersonthat the bills be paid. All aye ;
motion carried.
RESOLUTION 74-02 - MEETING TIMES
This resolution states that the meetings will commence one-half-hour
earlier, at 7 : 00 p.m. The board members agreed that this change would
be unnecessary and that the Board President should attempt to keep
the meeting time no later than 11 : 00 or 11s;30 p.m.
It was decided and agreed to leave the meeting time as it is and to
voluntarily stop the meeting at 11 : 00 or 11 : 30 p.m.
At this time, Director Craig asked that 'OLD BUSINESS' be placed on
the agenda after the bills . He felt that many times management was
directed to look into pending matters and report back to the board for
discussion. The other board members thought this was a good idea.
UNION DISCUSSION
Mr. Paulus proposed staggering the work week for the line crew and
office employees over a seven-day period to eliminate electric standby.
Mr. Paulus estimated the cost for standby is $3,000 per year. A
feasible working schedule was worked out for the line crew and put on
the blackboard for review by the Board.
Mr. Paulus reported that the linemen originally thought the idea of
a seven-day week was agreeable, but later said they were uninterested.
Since it was 8 : 00 p.m. , union discussion was postponed until after the
transformer bids were opened.
TRANSFORMER BID OPENING - 8 : 00 P.M.
The five bids were opened by President Waters . Attached are the bid
results .
Westech' s bid stated that if both packages were awarded, $500 could be
deducted from the total bid amount of both packages for shipping.
According to the bid specifications , the bid award will have to
made between either Package A or B; they cannot be broken down into
specific items within the bid packages .
It was recommended by the Manager that the bids be reviewed by Hal
Heidrick and Joe Joynt prior to being awarded. The bid award was
Page 1 April 2 , 1974 gg
Transformer Bids . . . continued
postponed until the next regular meeting.
UNION DISCUSSION . . . continued
Discussion ensued regarding staggering the work week for both outside
and office employees . Directors R. and D. Anderson thought the stag-
gered work week was worth looking into by the manager. Director
Sutton wanted to know what Sierra Pacific does for standby. Roy
Waters informed her that the lineman work ten days and have four
days off. They also employ troublemen that are able to work alone . —.
President Waters wanted Mr. Paulus to check with the union to see
what their feelings were regarding a staggered week.
The Board discussed the proposals presented by the IBEW; they are :
Title 2. 2 - Conditions of Employment . The board felt this could be
added.
Title 5 - Overtime. Agreement was reached that this could be added
to the agreement.
Title 7 - Transportation. It was agreed that this could be added.
Title 9 - Vacations . Duane Anderson felt this should be left as it
presently states--18 days paid vacation after five years of employ-
ment. Director Sutton thought it could be twenty days after fifteen
years. The other board members felt it was negotiable.
Title 13 - Funerals. Duane Anderson felt we should adopt guidelines
similar to PG & E' s which specifically spell out what relative an
employee can take a funeral leave for. Director Sutton wished to
add grandparents to this list .
Title 14 - Expenses . After discussion, it was discovered that this
proposal was already outlined in the present union contract, and
did not need to be discussed for this year' s union negotiations .
However, Director Sutton asked that a limit be placed on the meal
expenditures.
Title 17 - Vacancies. The Board agreed that this change of wording
regarding vacancies could be added to the agreement. Director Craig
asked if a clause could also be added stating more than a days
notice will be given to employees that are going to be laid off.
Title 20 - Employee Benefit Program. Since the District currently
pays 850 of the insurance coverage for both the employee and depen-
dents , the Board decided not to increase this to 1000 . Regarding
the upgrading of medical coverage, Mr. Paulus said that a Blue Cross
Insurance representative was up to speak with him concerning medical
insurance. Mr. Paulus stated that after negotiations , he could get
together with our present insurance agency, California Association
of Employers , to compare their coverage with Blue Cross if the employ-
ees still desired it.
Director Craig wondered if the contract should be clarified under
Section 9 . 1 which states that a regular employee shall be entitled
to 12 days of vacation after 12 consecutive months employment.. He
read this to mean that an employee has to work six months as a pro-
bationary employee and then another 12 months as a regular employee
before receiving 12 days vacation. Mr. Paulus said that despite the
unclear wording, an employee does receive 12 vacation days after 12
months employment.
President Waters asked the Board members if they would be willing to
go with the percentage wage increase that is granted the Sierra
Pacific employees under their negotiations , which is usually the
pattern followed by previous boards . Mr. Paulus thought he had
budgeted 72 to 8 percent increase in salaries over the previous year.
President Waters and Director Craig both favored increasing the
office girl ' s salaries to Sierra Pacific' s.
Director Sutton asked for a clarification on accumulated sick leave
Page 2 April 2 , 1974
?C1.��
Union Discussion continued
for employees as amended in the employee agreement dated June 19,
1973. Mr. Paulus informed her that as of June 19 , the employee
ceased to accumulate sick leave and that the amount on the books as
of that day is the number of days he/she will take upon termination.
If an employee is ill and uses all of the days accumulated up to June
19, he is entitled to re-acannula.te the same amount of days as of the
June 19 date. The employee is still allowed to accumulate sick leave
over the June 19 amount but he will not be paid for those additional
days upon termination. The possibility of paying off all unused sick
leave was discussed.
Director Sutton Questioned the union agreement being applicable to
administrative employees . According to the first page of the union
agreement, the contract covers union employees , non-union employees ,
and administrative employees . Director Sutton did not feel there were
any provisions for salaried employees insofar as sick leave and vaca-
tion pay was concerned. Mr. Paulus informed her that there is a
resolution in 1971 which states admiriisstrative employees will be paid
for all accumulated sick leave and vacation upon retirement , discharge,
or termination. Director Sutton requested a copy of this resolution.
Mr. Paulus suggested renting shirts with either a name of the employee
or company on it for the outside crews . The shirts would cost $48
per month which is for three clean shirts a week for eight employees .
The directors felt this was a good idea and could possibly be worked
into the union negotiations. Roy Waters suggested furnishing the
employee with an I .D. card for easy identification.
Due to the length of the meeting, discussion on the union negotiations
was tabled until the next regular meeting.
PROPOSED BUDGET
Mr. Paulus passed out the proposed budget ; a copy of which is attached.
Mr. Paulus quoted figures to the board on the budget that did not
include a four percent power increase of rates . The result is
approximately $30, 000 less for operating margin. Mr. Paulus said
there is the garage or pick-up that can be eliminated from the budget
should the rates not be increased; however, he felt both should be
obtained as they are needed.
The possibility of leasing a boom truck for the summer months was
discussed. Additional information would be needed prior to such an
arrangement.
The budgeted expenditures were broken down between water and electric
departments. For many of the expenses, the water portion was 20 0 of
the overall expected expense.
The water improvements as recommended by Dan Cook were discussed.
These improvements would be p�APr from money in time deposits that
was paid by subdividers for /source and storage in subdivisions and
land sales . The directors were asked to report back to the board with
their recommendations on these improvements .
Director Sutton recommended that the district attempt to get by the
year without a four percent increase in power rates .
Director D. Anderson suggested looking into the electric standby
charge as an additional source of income should it pass the legis-
lature. He felt this income would offset many of the related operat-
ing expenses which would give the District additional monies to spend
on expenditures and afford not to raise the power rates . Since the
water standby is presently enforceable, Director Sutton suggested
enacting an ordinance stating a standby water fee will be levied.
Discussion was tabled until the next regular meeting.
MANAGER' S REPORT
Mr. Paulus confirmed with the board the calling of bids for the 2500
KVA substation transformer. They agreed these should go out.
April 2 1974 .qo
Page 3 , 1
Manager' s Report . . . continued
Mr. Paulus and Bruce Grow will be taking a weeks vacation commensing
April 8.
PG & E has informed Mr. Paulus that they are not interested in the
Mutual Assistance Agreement that Sierra Pacific proposed. An agree-
ment is being retyped as presented by Sierra Pacific for their
review which incorporated Sierra Pacific and the District. Any
changes S. P. P. Co. has can be added; then Mr. Joynt can review it
prior to the board taking any action on acceptance.
The Sierra Sun has written a letter requesting more cooperation —.
from the office insofar as releasing information that goes to the
board members is concerned. They would like to receive copies of
all material that is sent to the directors relating to board meet-
ings , etc. Mr. Paulus said this would be done in future practices .
The meeting between Mr. John Trauner, Nevada County Auditor-Con-
troller, and Tom Paulus was postponed one week.
The proposed Truckee Mobile Home Park located on South River
Street is asking that the District waive the water connection fee
for the park. They state that the only connection to be made by
the District is at the main entry point on South River Street and
not within the park itself. The district normally charges $150 per
water connection which would include mobile home spaces . The
contractor of the park would like to install their own facilities ;
the district would still be charging the $5 per month water usage
charge as is the custom in other mobile home parks . The developer
proposed using plastic piping from the main water line to the
trailer spaces. If this was - allowed, there would have to be an
agreement between the developer and the District releasing the
District from any responsibility for the plastic pipe within the
trailer park. The Board members felt that if the District is col-
lecting the $5 per month for water from the park dwellers , then
the water lines should be constructed according to District spec-
ifications . The conflict on this is that the park will be on pri-
vate property. The main water line will be on the county right-
of-way which will be constructed according to District specifications
(galvanized pipe ; from that point to the individual trailer pads ,
the water lines are not the district ' s responsibility as is the
case in all other construction. Due to Director D. Anderson's
comments on this subject, Director Sutton felt Mr. Anderson' s remarks
were in conflict of interest. Discussion on this was tabled until
the next regular meeting. Director Sutton requested that the
manager look into what procedures were followed in Aweeka' s
trailer park, Village Green, etc . , so that a comparison could be
made regarding this mobile home park.
It was moved by Director R. Anderson and seconded by Director Craig
that the meeting be adjourned. After a five minute break, the
board, management, and Attorney Joynt reconvened into executive
session to discuss the Tahoe Donner power contract.
The regular meeting was adjourned by the president at 11': 05 p.m.
TRUCKEE-DONNER PUBLIC UTILITY DISTRICT
BY:
RGY- WATERS, PRESIDENT OF THE BOARD
r
;EIRRkYN K NZ , RECO_R_D7NG SECRET4#RY
Page 4 APRIL 2 , 1974 .� i
1974 PROPOSED BUDGET
WATER
Revenue :
460 Domestic 52 ,000
461 Commercial & Industrial 293,000
419. 2 , 463. 4,5 Miscellaneous 191000
100 .9000
Expenditures :
163 Whse . Expense 120
184 Const. Clearing 100
408 Taxes - 5% 300
603-681 Oper. & Maint. 7 ,000
909-909 . 5 Advertising 75
912-913 Customer Billing 860
920 Director's Fees 1 ,200
921. 1 Office Expense 800
921. 2 Dues & Subscriptions 100
921. 3 Telephone 720
921. 4 Travel 300
921. 5 Bldg. Services 500
921.6 Utilities 300
923. 1 Legal Counsel 6 , 750
923. 2 Auditing & Accounting 21000
923. 3 Engineering 51000
924 Insurance 1 ,003
926 Retirement 621
932 Maint. of General Plant 100
950 Transportation Expense 3,696
961-971 Employee Benefits 29697
972 Salaries 16 ,088
50 .t330
Operating Margin 499670
.-1
qz
1974 PROPOSED BUDGET
Account Number Revenue-Electric 1973 1974
442-440 . 5 Domestic 392 ,694 420 ,183
442. 1-443. 5 Commercial 196, 271 210 ,010
442 . 2-445 . 5 Industrial 313, 836 335 , 805
419 . 1 , 456-459 . 5Miscellaneous 46 , 859 48 ,690
441 Non Revenue 1 ,021 840
9502681 11015 ,528
Revenue-Water
460 Domestic 501,426 52 ,000
461 Commercial-Industrial 27,9816 291,000
419 . 2 , 463. 4, 5 Miscellaneous 17 ,402 19 ,000
95 ,644 100 ,000
1046 ,325 11115 ,528
EXPENDITURES
136 Warehouse Expense 11,001 1, 200
184 Construction Clearing 702 800
408 Taxes - 5% 4,495 5 ,000
427 Interest - L.T. Debt 189044 151,500
555 Purchased Power 5052060 596 ,000
580 Operation 4,686 6 ,000
590 Maintenance-Electric 8 ,447 10 ,049
902-903. 5 Customer Billing-E 31193 31400
909-909. 5 Advertising 200 400
920 Director' s Fees 6 ,000 69000
921. 1 Office Expense 3, 895 4,000
603-681 Oper. & Maint. Water 6 , 787 7 ,000
912-913 Customer Billing-W 790 900
921.s Dues & Subscriptions 947 950
921. 3 Telephone 2 ,417 2 ,600
921. 4 Travel 874 1 ,500
921. 5 Bldg. Services 912 1 ,000
921. 6 Utilities 812 850
923. 1 Legal Counsel 12 ,069 133,500
923. 2 Audit & Accounting 6 ,030 10 ,000
923. 3 Engineering 3 ,619 10 ,000
924 Insurance 71477 7,462
926 Retirement 2 ,070 3,105
932 Maint. of Gen. Plant 951 1,9000
950 Transportation Expenses 19 ,866 229000
961-971 Employee Benefits 36 ,866 413,180
972 Salaries 171 ,269 1872180
829 ,479 9582576
216 , 846 1562952
. q2-A
1974 PROPOSED BUDGET
ELECTRIC
Revenue:
440-440 . 5 Domestic 420 ,183
442 . 1-443. 5 Commercial 2109010
442. 2-445. 5 Industrial 335 ,805
419 . 1,456-459. 5 Miscellaneous 48,690
441 Non Revenue 840
1015 ,528
Expenditures :
163 Whse. Expense 1 ,080
184 Const. Clearing 700
408 Taxes 4, 700
427 Interst - L.T. Debt 152500
555 Purchased Power 596 ,000
580 Operation 63,000
590 Maintenance 101049
902-9032902-903. 5 Customer Billing 3,440
909-909. 5 Advertising 325
920 Director' s Fees 4, 800
921 . 1 Office Expense 3, 200
921. 2 Dues & Subscriptions 850
921. 3 Telephone 19880
921. 4 Travel 1 ,200
921. 5 Bldg. Services 500
921.6 Utilities 550
923. 1 Legal Counsel 630750
923. 2 Audit & Accounting 81000
923. 3 Engineering 51000
924 Insurance 6 ,459
926 Retirement 21484
932 Maint. of General Plant 900
950 Transportation Expenses 182304
961-971 Employee Benefits 38 ,483
972 Salaries 171 ,092
9082246
Operating Margin 107 ,282
9
�. g.q
-B
1974 PROPOSED BUDGET
CAPITOL EXPENDITURE & DEBT REDUCTION
Water Improvements 70 .9500
Garage 169900
Truck 17,980
Secruity Lights 1 ,400
Wire 601,000
Transformers 50 ,9000
Meters 12 ,600
Poles 19 ,500
Sierra Pacific (D.L. ) 12 ,438
REA 19 .9000
Misc. Electric Inv. 34,134
Water Invoice 8,000
Substation Transformer 15 ,000
337 ,452
Time Deposit Water 70 ,1500
Time Deposits from Lakeworld 959000
Southside Well Reimbursement 159000
Operating Margins 1561952
337,452
. vt '2-C
BID RESULTS - OPENING 4-2-74
PACKAGE "A" 500 KVA TRANS. 225 KVA TRANS, TOTAL PRICE DELIVERY DATE
1. RTE CORPORATION $ 3,784 $ 2,457 $ 6P241R May 1, 1975
2. ALLIS-CHALMERS $ 3,977 $ 2,811 $ 6,788 44 weeks
3. WESTINGHOUSE $ no bid $ no bid $
20-24 weeks Item 1
4. STANDARD TRANS. $ 3,855 $ 3,586 $ 7,441 85 weeks Item 2
S. WESTECH $ 31704 $ 2,551 $ 61255 90 days after R.O.A.
PACKAGE "B" 300 KVA TRANS. 3-225 KVA TRANS 225 KVA TRANS.
RADIAL FEED LOOP FEED LOOP FEED TOTAL PRICE DELIVERY DATE
1. RTE CORPORATION $ 29808 $ 2,622 (Unit) $ 29898 $ 13,572 May 1, 1975
3
2. ALLIS-CHALMERS $ 2,817 $ 2,885 $ 3,260 $ 14,732 K 44 weeks '
July 15, 1974
3. WESTINGHOUSE $ 4,115 $ 3,855 $ 41275 $ 192955 or sooner
4. STANDARD TRANS. $ no bid $ no bid $ no bid $
same as package
A-if both pack-
5. WESTECH $ 3,070 $ 21703 �� $ 29914 $ 142093 age A & B are
as-C) awarded deduct
$500 from total
bid price for
both packages
STATEMENT OF GENERAL FUND
Bank Balance - 3-19- 74 429259 . 31
Time Deposits 219280 .00
Deposits 39 ,091 . 88
Approved Billings 242318.39
Atlantic Richfield 11. 27
Western Hdwe . & Tool 1 . 31
Wedco 1. 49
Tom Paulus janitorial 60 .00
George Cattan (10 . 00) (24,382 . 46)
PAYROLL
3-29-74 DT OT STANDBY GROSS NET
Silva 91. 21 143. 00 806 . 21 610 .90
Paulus 750 .00 539. 23
Lopez 69 . 86 66 . 50 668. 36 473. 79
Grow 585 . 20 454.03
Krajewski 575.00 424. 32
Straub 73. 95 537.95 392. 41
Reynolds 532 .00 419 . 57
Sharp 515.68 383. 75
Barry 354. 40 292 .63
Craig 44.64 342 . 24 262. 89
Connell 340 .08 250 . 59
Kinzie 82. 11 339. 71 262.67
Kirchner 2 . 29 246 . 29 181 . 92
Rose 87 .00 76 . 44 (51025 . 14)
364.06 209. 50 6680 . 12
Bank Balance - March 29 , 1974 732223. 59
BILLS FOR BOARD' S APPROVAL
Builder' s Service Center 56 . 98
Gordon Huber Company 85 . 18
RTE 4-50 KVA transformers 12768 . 20
Snap-on Tools 92 . 72
Sierra Sun transformer ad. 6 .00
Superior Switchboard test switches 272 . 19
Truckee-Donner Disposal 22 . 50
Sierra Pacific 62 ,360 . 90
R. Gautsche Chevron grease , etc. 14. 42
Zep Mfg. Company paint & cleaner 61.02
Truckee-Donner Glass warehouse & truck 129 . 70
Wedco angle iron for whse: 211.07
" repair test equip. 48. 43
�t
elec. Conn. 6 . 11
U.G. tools 207.94
" transformers 844. 20
" 342 . 30
clamps 227. 77
fuse links 56 .04
" connectors 1 ,218 .00
PVC moulding 601 .01
" elec. conn. 209 . 23
Cal Western Life pension 683. 14
IBM maint. agreement 25 . 51
Graybar #2 ug, cond. 12162 . 72
Calif. Assoc. of Emp. emp. ins . 534.90
Pitney Bowes mailing machine lease 33. 08
Tom Paulus Reno trip 2 .90
A. Carlisle W-2 forms 12 .04
Pacific Telephon 267. 85
Alentco flares 50 .00
Ace Hardware 84. 42
Anixter conductor 12945 . 85
Armanko Office Supply 41 . 44
Hydro-Search water study 12017 . 24
Sierra Sun ord. 74-02 73. 00
Truckee Sno Jet 4• 99
Tahoe Pyramid Ins . bid award 71162 .00
i
�/` - ,C)q
Bills for Board' s Approval . . . continued
Teichert Aggregates "good will" 5 . 74
Sierra Electronics radio repair 21.00
Walt' s Exxon 14. 45
Joe's Truckee Auto Repair 485 . 99 (822470 . 17)
Bank Balance after payment of above (91246 . 58) r--�