HomeMy WebLinkAbout1995-06-19 Min - Board REGULAR MEETING
June 19, 1995
In accordance with District Code Section 2 08 010 the TDPUD minutes are action only minutes
All Board meetings are recorded on audio tapes which are preserved perpetually and made
available for listening to any interested par y upon their request
The regular meeting of the Board of Directors of the Truckee Donner Public Utility District was
called to order at 7:07 PM in the TDPUD Board Room by President Jones.
ROLL CALL: Directors Joe Aguera, Ron Hemig, Bob Jones, James Maass and Patricia Sutton
were present.
EMPLOYEES PRESENT.. Mary Chapman, Susan Craig, Peter Holzmeister, Dave Rully and Scott
Terrell.
CONSULTANTS PRESENT: Consulting Engineer, Keith Sauers.
OTHERS PRESENT: There were no others present in the audience.
CONSIDERATION OF PROGRESS PAY REQUESTS AND CONTRACT CHANGE ORDERS;
POSSIBLE APPROVAL
The following are Proposition 55 construction management items.
Gateway Tank Project
Construction activities for the Gateway Water Tank Project include tree removal, excavation of
the cut slope behind the tank, excavation of the tank pad, construction of the rock lined ditch
above the cut slope and construction of a fill for the tank access. Construction is approximately
12% complete in about 12% of the contract time.
Director Maass moved, and Director Aguera seconded, that the Board approve Periodic Estimate
for Partial Payment No. 1 presented by RDC, Inc. for work on the Gateway Water Tank Project
in the amount of$60,030. All Directors, aye, by voice vote.
The design of the Gateway Water Tank grading plan anticipated that bedrock would be
encountered at a depth that would allow the lower portion of the cut to be constructed at a fairly
steep slope. Bedrock was not intercepted at the expected depth, but is significantly deeper This
resulted in the entire cut slope being constructed at a more modest angle and a retaining wall is
f the site development. It was noted that this chap
now needed as part o a can be accommodated p g
by Prop 55 monies. Director Maass moved, and Director Hemig seconded, that the Board
approve Contract Change Order No. 1 in the amount of$42,300 presented by RDC, Inc. relating
to the Gateway Water Tank Project. All Directors, aye, by voice vote. SO MOVED.
Prosser Heights Tank Replacement Project
Site work is nearly complete including tank footing, underground piping and paving. Tank erection
is underway with the floor and tank shell welded in place. The project is approximately 60%
complete in about 53% of the contract time.
6119195 Page 1
. Director Aguera moved, and Director Maass seconded, that the Board approve Periodic Estimate
for Partial Payment No. 2 in the amount of $49,405.50 to RDC, Inc. for work on the Prosser
Heights Tank Replacement Project. All Directors, aye, by voice vote. SO MOVED.
1995 Well Pumps Improvement Project
The Northside Well installation is near completion and its pump is currently in production. The
Prosser Annex Well pump is installed along with the electrical equipment. Mechanical equipment
installation remains to be completed before the pump can be put into service. The project is
approximately 97% complete in about 94% of the contract time.
Director Maass moved, and Director Aguera seconded, that the Board approve Periodic Estimate
for Partial Payment No. 2 in the amount of$129,121.38 to Claybom Contracting Group, inc. for
work on the 1995 Well Pumps Improvement Project. All Directors, aye, by voice vote. SO
MOVED.
The Board considered a change order involving the installation of additional electrical components
at both the Northside Well and Prosser Annex Well sites. The need for these components is
required to meet particular conditions at the sites. The time extension will give the contractor until
June 30 to complete the project including these modifications.
Director Maass moved, and Director Aguera seconded, that the Board approve Clayborn
Contracting Group's Contract Change Order No. 3 in the amount of$1,135 and a time extension
of 22 days on the 1995 Well Pumps improvement Project. All Directors, aye, by voice vote. SO
• MOVED.
PUBLIC INPUT
There was no public input.
WORKSHOP
Gateway water storage tank issues
Peter Holzmeister discussed comments made by MAPF regarding the construction of the
Gateway tank. MAPF realizes that it missed the public comment period, but has asked the
District to paint the tank an earth-tone color. MAPF has also asked the District to prepare an
artist's rendering to show how the tank would look when complete and share the rendering with
the community. The consensus of the Board was that the General Manager choose a color for
the tank that is appropriate. The Board was not in agreement to have a rendering prepared.
Changes in the program of the Administrative Services Department
Mary Chapman discussed changes she is proposing in the Administrative Services Department
and the impact of those changes on her budget her report is attached to these minutes.
Use of electric energy in Truckee
Scott Terrell discussed the results of the end use survey conducted by NCPA. Copies of the
overheads he used are attached to these minutes. There was considerable discussion among
6119195 Page 2
the Directors and this topic will be scheduled again for a future workshop meeting.
Town's proposed ordinance relating to encroachment permits
Peter Hoizmeister discussed a proposed ordinance of the Town of Truckee that would regulate
encroachments of District water and electric facilities in the street rights-of-way. The General
Manager will meet with Town officials to discuss modifications in the ordinance to provide for
more flexibility for the placement of District facilities.
Monthly staff reports
The monthly staff reports were reviewed; copies are attached for reference.
ADJOURNMENT
The meeting was adjourned at 11:05 p.m.
TRUCK D NN R PUBLIC UTIL► ISTRICT
Robert A. Jones r Ident
Prepared by -
Susan M. raig, Deputy District Clerk 61
smc
6119195 Page 3