HomeMy WebLinkAbout11 Spring Street Pipeline Project Agenda Item # 11
Public Utility District
ACTION
To: Board of Directors
From: Neil Kaufman
Date: April 16, 2014
Subject: Consideration of Setting Contract Parameters for the Spring Street
Pipeline Rehabilitation Project
1. WHY THIS MATTER IS BEFORE THE BOARD
Board approval is required for expenditures in excess of$15,000.
2. HISTORY
The Water Department has an ongoing need to replace existing water pipelines that
fall into two basic categories.
1) Pipes that are in poor condition and require repeated repairs.
2) Pipes that are old, undersized (typically 4-inch diameter and smaller) and have
exceeded their useful life.
The Town of Truckee will be conducting a streetscape project in the Brickeltown area
of Truckee. The area of the Town's project is from 10120 Jibboom Street to the traffic
roundabout at the McIver Crossing. The existing water pipe in Spring Street between
Jibboom Street and Keiser Avenue is in poor condition and the Water Department
would like to address this problem before the final paving and parking improvements
are constructed along Spring Street.
A workshop regarding this project was held on April 2, 2014.
3. NEW INFORMATION
The bid documents for the project have been completed and the District has begun
advertising for bids. A copy of the bid documents in PDF format is included as
Attachment 1.
The Town's streetscape project is scheduled to begin construction on July 2014.
Therefore, it is necessary for the District to complete its work in June in order to avoid
conflicts between two separate contractors working in a limited area. The current
project schedule is:
• Begin Advertising for Bids -April 2014
• Bid Opening - May 2014
• Bid Award - May 2014
• Construction - June 2014
• Project Completion - June 2014
In order to perform the construction in June, it is necessary to award the contract in
early May. This time frame provides a few weeks for the contractor to submit all the
necessary contractual requirements such as bonds and insurance and to order
materials.
As discussed at the April 2 workshop, the next scheduled Board meeting on May 21
does not fit well with the need to award the project in early May. It was suggested that
the Board could consider authorizing the award of the contract up to a certain dollar
value prior to the actual bid opening. After the bid opening, if the apparent low bid
exceeds the authorized dollar value, or if some irregularity occurs, it would be
necessary for the Board to take additional action, possibly at a special meeting.
The estimated construction cost for the project is $60,000.
4. FISCAL IMPACT
The estimated cost for the project is $60,000. The planned funding source for this
project is the Water Department Capital Replacement Fund.
5. RECOMMENDATION
a) Authorize the award of the Spring Street Pipeline Rehabilitation construction contract to
the lowest responsive and responsible bidder in for an amount not to exceed $60,000.
b) Establish a 10 percent change or allowance in an amount not exceed $6,000.
c) Authorize the transfer of up $66,000 from the Water Department Capital Replacement
Fund to the Water Department General Fund.
Michael D. Holley
General Manager/Water Utility Manager
Attachment 1- partial
SECTION 00030 - NOTICE TO CONTRACTORS
Notice is hereby given that the Board of Directors of Truckee Donner Public Utility District,
Nevada County, California, herein referred to as the "DISTRICT," will receive sealed proposals
at the District office, 11570 Donner Pass Road, Truckee, California 96161 until 2:00 p.m., May
1, 2014, at which time they shall be opened and publicly read for construction of:
SPRING STREET PIPELINE REHABILITATION
The WORK of this Contract comprises the construction of the following:
• Sliplining approximately 425 feet of existing 10-inch steel pipe with 6-inch PE pipe
• One service lateral
• Two gate valves
• Connections to existing pipelines and service laterals
• Ancillary items such as fittings, locator wire, marking tape and other appurtenances
In accordance with the provisions of Section 1770, 1772 and 1773.2 of the Labor Code, the
DISTRICT has determined the general prevailing rates of wages applicable to the WORK to be
done. These rates are set forth in a schedule located at the DISTRICT office; said schedule is
available to any interested party on request. The CONTRACTOR shall post a copy at the job
site.
Each bid must conform to the requirements of the Contract Documents, all of which may be
examined at the offices of the DISTRICT: 11570 Donner Pass Road, Truckee, California,
96161. Copies of the Contract Documents may be obtained on the following basis:
Documents Payment
Complete Printed Set of Contract Documents,
Specifications and Half-Size (1 1" x 17") Drawings $35.00
Printed Set of Full-Size (22"x 34") Drawings $10.00
Complete Set of Contract Documents
Specifications and Half-Size Drawings on CD in PDF format $5.00
Payments are not refundable.
No bid will be considered unless it is made on the form provided and accompanied by Certified
Check, Cashier's Check, or Bidder's Bond for 10 percent of the amount of the bid, made
payable to the DISTRICT. The above-mentioned check or bid bond shall be given as a
guarantee that the bidder executes the Contract, if it be awarded to him, in conformity with the
Contract Documents.
Within 15 days after notification of the Award of the Contract, the successful bidder or bidders
will be required to furnish a Performance and Payment Bond in an amount equal to one hundred
percent (100%) of the Contract Price. Said bond shall be secured from a Surety Company
satisfactory to the DISTRICT.
TRUCKEE DONNER PUD NOTICE INVITING BIDS
SPRING STREET PIPELINE REHABILITATION PAGE 00030-1
The CONTRACTOR may, pursuant to and in conformity with Public Contract Code Section
22300, substitute eligible securities for any monies withheld by the DISTRICT to ensure
performance under the Contract.
The CONTRACTOR shall, at the time the bid is awarded and throughout the term of the
Contract, hold and maintain in force the following types of California Contractor's licenses: A-
General Engineering or C-34 Pipeline.
The DISTRICT reserves the right to reject any and all bids and/or waive any irregularities or
informalities in the bidding.
- END OF SECTION -
TRUCKEE DONNER PUD NOTICE INVITING BIDS
SPRING STREET PIPELINE REHABILITATION PAGE 00030-2
SPRING STREET PIPELINE REHABILITATION - BID SCHEDULE
BID UNIT
ITEM DESCRIPTION QUANTITY UNITS PRICE SUBTOTAL
1 Mobilization 1 LS
2 Perform Excavation and
Backfill at Access Pits 1 LS
3 Slipline Existing 10"Steel Pipe
with 6" PE Pipe 425 FT
4 1.5" PE Water Service Lateral
at 10184 Spring Street 10 FT
5 Connection to New 6"Valve at
Station 0+00 1 LS
6 Connection to New 8"Valve at
Station 4+29.55 1 LS
7 Rock Excavation 2 HRS
8 AC Pavement and Base
(trench restoration) 230 SF
9 Additional %"Thickness of AC
Pavement(trench restoration) 230 SF
10 All Other Work Required by the
Contract Documents 1 LS
Total Amount of Bid:
TRUCKEE DONNER PUD BID FORMS
SPRING STREET PIPELINE REHABILITATION PAGE 00300-3
SECTION 00310 - MEASUREMENT AND PAYMENT
PART 1 -- GENERAL
1.1 SCOPE
A. Payment for the various items of the Bid Schedule, as further specified herein, shall
include all compensation to be received by the CONTRACTOR for furnishing all tools,
equipment, supplies, and manufactured articles, and for all labor, operations, and
incidentals appurtenant to the items of work being described, as necessary to complete
the various items of the WORK all in accordance with the requirements of the Contract
Documents, including all appurtenances thereto, and including all costs of permits and
cost of compliance with the regulations of public agencies having jurisdiction, including
Safety and Health Requirements of the California Division of Industrial Safety and the
Occupational Safety and Health Administration of the U.S. Department of Labor (OSHA).
No separate payment will be made for any item that is not specifically set forth in the Bid
Schedule, and all costs therefor shall be included in the prices named in the Bid Schedule
for the various appurtenant items of work.
B. The CONTRACTOR shall Bid all items in the Bid Schedule. A Bid containing an
incomplete Bid Schedule shall be considered Non-Responsive and shall be rejected.
1.2 PAYMENT FOR PAVEMENT RESTORATION
A. Each Bid Schedule includes a bid item for the installation of A.C. pavement and base. The
unit price given for the installation shall be based upon "Trench Restoration" as defined in
Section 02460, Article 1.1.0 for A.C. pavement. The unit price shall include the 8-inches
of subgrade as required by the Contract Documents. For the purposes of bidding, the
CONTRACTOR shall assume a pavement thickness of four inches as indicated on
Drawing G-2, unless otherwise indicated.
B. The DISTRICT has not determined the existing pavement thickness for each street within
the project area. In some cases, the existing pavement thickness is greater than the four
inches assumed in Article 1.2.A. Therefore, for bidding purposes, each Bid Schedule
includes a bid item for the installation of an additional Y inch thickness of A.C. pavement.
C. The DISTRICT will determine the payment for pavement thickness as follows:
1. If the existing pavement thickness is 4 inches or less, the CONTRACTOR shall be
paid for pavement restoration based upon total square footage times the unit price
given in the bid item for"A.C. Pavement and Base".
2. If the existing pavement thickness is 4.5 inches, the CONTRACTOR shall be paid
for pavement restoration based upon total square footage times the unit price given
in the bid item for "A.C. Pavement and Base" plus the unit price given in the bid item
for"Additional 1/z"Thickness of A.C. Pavement".
3. If the existing pavement thickness is 5 inches, the CONTRACTOR shall be paid for
pavement restoration based upon total square footage times the unit price given in
the bid item for"A.C. Pavement and Base" plus two times the unit price given in the
bid item for"Additional '/2"Thickness of A.C. Pavement'.
TRUCKEE DONNER PUD MEASUREMENT AND PAYMENT
SPRING STREET PIPELINE REHABILITATION PAGE 00310-1
4. For a pavement thickness greater than 5 inches, the payment will be calculated in a
similar manner to Article 1.2.C.3.
1.3 PAYMENT FOR ROCK EXCAVATION
A. The DISTRICT determines the number of hours spent performing rock excavation as
follows:
1. For power-operated hammers and rock saws, the measurement includes all time
the equipment is in use on site. The time for mobilization of the equipment to the
site and time spent removing the broken up rock from the trench shall not be due
additional compensation.
2. For drilling and blasting, the measurement includes time spent drilling charge
holes, time spent filling and preparing the charges, time spent backfilling over the
charges, and time spent excavating the backfill from over the charges. The time
for mobilization of the equipment to the site and time spent removing the broken up
rock from the trench shall not be due additional compensation.
In the event that blasting results in more damage to the street than is customary, in
the opinion of the DISTRICT, due to excess use of explosives, the CONTRACTOR
shall not be due additional compensation for the time and expense incurred
repairing or replacing the damaged asphalt.
3. Any exploratory drilling for rock shall be at the expense of the CONTRACTOR.
PART 2— BID SCHEDULE
2.1 MOBILIZATION (Bid Item 1)
A. No measurement shall be made for this item. The CONTRACTOR will be compensated
for all mobilization and job set-up costs based on the lump sum price provided in the Bid
Schedule.
B. The amount entered in Bid Item 1 of the Bid Schedule for Mobilization shall not exceed
five percent of the total amount of the Bid.
2.2 PERFORM EXCAVATION AND BACKFILL AT ACCESS PITS (Bid Item No. 2)
A. No measurement shall be made for this item. The CONTRACTOR shall be compensated
for all Work performed under this item based on the lump sum price provided in the Bid
Schedule. The price given by the CONTRACTOR shall include all labor, equipment and
materials necessary to perform this Work.
2.3 SLIPLINE EXISTING 10-INCH STEEL PIPE WITH 6-INCH PE PIPE (Bid Item No. 3)
A. Measurement of water pipe installed will be the actual centerline length of new 6-inch
pipe as determined by the DISTRICT. The CONTRACTOR will be paid for furnishing
and installing water pipe based on the unit prices shown in the Bid Schedule and on the
DISTRICT'S measurement of the length of installed pipe. No separate payment shall be
made for any fittings or materials except those itemized in the Bid Schedule.
B. The prices given by the CONTRACTOR for Bid Item 3 shall include all labor, equipment
and materials necessary to provide all elements of the Project from Station 0+00 to Station
TRUCKEE DONNER PUD MEASUREMENT AND PAYMENT
SPRING STREET PIPELINE REHABILITATION PAGE 00310-2
4+25 on Drawing P-1 as required by the Contract Documents except those itemized
separately.
2.4 FURNISH AND INSTALL 1.5-INCH PE WATER SERVICE LATERAL AT 10184 SPRING
STREET (Bid Item No. 4)
A. Measurement of water service lateral installed will be the actual centerline length of new
1.5-inch pipe as determined by the DISTRICT. The CONTRACTOR will be paid for
furnishing and installing water pipe based on the unit prices shown in the Bid Schedule
and on the DISTRICT'S measurement of the length of installed pipe. No separate
payment shall be made for any fittings or materials except those itemized in the Bid
Schedule.
B. The price given by the CONTRACTOR shall include all labor, equipment and materials
necessary to provide a complete and functioning installation as required by the Contract
Documents except those itemized separately.
C. This Bid Item shall apply to installation of the 1.5" PE service lateral at 10184 Spring Street
only.
2.5 PERFORM CONNECTION TO NEW 6-INCH VALVE AT STATION 0+00 (Bid Item No. 5)
A. No measurement shall be made for this item. The CONTRACTOR shall be compensated
for all Work performed under this item based on the lump sum price provided in the Bid
Schedule. The price given by the CONTRACTOR shall include all labor, equipment and
materials necessary to perform this Work.
B. Bid Item No. 5 shall include furnishing and installing the following
1. One 6"flanged gate valve
2. One 10" x 6"flanged reducer
3. All other parts and accessories necessary for a complete and functioning installation
2.6 PERFORM CONNECTION TO NEW 8-INCH VALVE AT STATION 4+29.55
(Bid Item No. 6)
A. No measurement shall be made for this item. The CONTRACTOR shall be compensated
for all Work performed under this item based on the lump sum price provided in the Bid
Schedule. The price given by the CONTRACTOR shall include all labor, equipment and
materials necessary to perform this Work.
B. Bid Item No. 6 shall include furnishing and installing the following
1. One 8" flanged gate valve
2. One 8" 90-degree flanged elbow
3. One 8" x 6"flanged reducer
4. One 6" FL x MJ adapter
5. One 6" MJ sleeve
6. All other parts and accessories necessary for a complete and functioning installation
2.7 PERFORM ROCK EXCAVATION (Bid Item No. 7)
A. Measurement of rock excavation shall be based on measurement of the actual number
of hours spent by performing rock excavation work as determined by the DISTRICT. The
TRUCKEE DONNER PUD MEASUREMENT AND PAYMENT
SPRING STREET PIPELINE REHABILITATION PAGE 00310-3
price given by the CONTRACTOR shall include all labor, equipment, materials and
subcontractors necessary to perform this Work.
B. The CONTRACTOR shall have the option of using power-operated hammers, rock
saws, drilling and blasting or other appropriate rock excavation methods. The hourly
rate listed shall include all compensation due to the CONTRACTOR for performing rock
excavation. The CONTRACTOR SHALL NOT be entitled to any additional monies or
compensation, including stand-by time for crew members idled during the performance
of rock excavation. The CONTRACTOR shall not be due payment if its forces are
unable to perform work while waiting for subcontractors or materials to arrive on the
project site.
C. The use of expansive compounds or similar methods that have a time delay associated
with their effectiveness shall be reviewed on a case-by-case basis and the
CONTRACTOR shall not be entitled to compensation while waiting for such methods to
become effective.
D. Section 02200 — Earthwork defines the level of effort required before the DISTRICT will
consider excavation work to be rock excavation. In the event that the CONTRACTOR
chooses to utilize excavation equipment with a flywheel horsepower lower than that
given in Section 02200, the CONTRACTOR shall not be entitled to payment for rock
excavation.
2.8 FURNISH AND INSTALL A.C. PAVEMENT AND BASE (TRENCH RESTORATION)
(Bid Item No. 8)
A. Measurement of A.C. pavement shall be based on measurement of the actual square
footage of A.C. pavement installed as determined by the DISTRICT. The CONTRACTOR
shall be paid for A.C. pavement based on the unit prices shown in the Bid Schedule and
on the DISTRICT'S determination of the square footage of A.C. pavement installed. The
price given by the CONTRACTOR shall include all labor, equipment, and materials
necessary to perform this Work.
B. For Bid Item 8, the CONTRACTOR shall assume an AC pavement thickness of four
inches. Payment for additional AC to match the thickness of the existing road section shall
be in accordance with Bid Item 9.
2.9 FURNISH AND INSTALL AN ADDITIONAL 1/2-INCH OF A.C. PAVEMENT (TRENCH
RESTORATION) (Bid Item No. 9)
A. Measurement of A.C. pavement shall be based on measurement of the actual square
footage and additional thickness of A.C. pavement installed as determined by the
DISTRICT. The CONTRACTOR shall be paid for A.C. pavement based on the unit prices
shown in the Bid Schedule and on the DISTRICT'S determination of the square footage
and additional thickness of A.C. pavement installed. The price given by the
CONTRACTOR shall include all labor, equipment, and materials necessary to perform this
Work.
2.10 FURNISH AND INSTALL ALL OTHER WORK REQUIRED BY THE CONTRACT
DOCUMENTS (Bid Item No. 10)
A. No measurement shall be made for this item. The CONTRACTOR will be compensated
for all costs in this item based on the lump sum price provided in the Bid Schedule.
TRUCKEE DONNER PUD MEASUREMENT AND PAYMENT
SPRING STREET PIPELINE REHABILITATION PAGE 00310-4
B. The price given by the CONTRACTOR shall include all labor, equipment and materials
necessary for all WORK in the Contract Documents not covered by the other Bid Items
required for successful completion of the project. Such WORK shall include, but is not
limited to, pipeline pressure testing and disinfection, implementation of the stormwater
pollution prevention plan and traffic control.
- END OF SECTION -
TRUCKEE DONNER PUD MEASUREMENT AND PAYMENT
SPRING STREET PIPELINE REHABILITATION PAGE 00310-5