Memorandum
To: Board of Directors
From: Ed Taylor
Date: May 2, 2003
Date of Board Meeting: May 7, 2003
Subject: WATER DEPARTMENT CAPITAL IMPROVEMENT PLAN UPDATE
1, WHY THIS MATTER IS BEFORE THE BOARD
Information and planning
2. HISTORY
The water Department has had a very aggressive construction program for the last two
years (2001, 2002). The projects focus on was Donner Lake, Glenshire Areas and Water
Source. Water source information (Test Well & Geo-physical Testing)
3. NEW INFORMATION
Water source issues: Alder Dr. Test Well & Geo-physic Testing & Quality
Water Source Plan —Test Holes and Well
Projects completed in 2002
Donner Lake plan 2003
Glenshire plan 2003
Capital Improvement Plan for District 2003
Capital Improvement Plan for District 2004, 2005
Project Time lines for the 2003 Capital Projects
Funding for 2003 Capital Projects
Funding for the 2004 & 2005 Capital Projects
Development
4, RECOMMENDATION: Information only
Attachments:
2002 Project List and Map
2003 Project List and Map
2004 & 2005 Project List and Map
Alder Creek Test Well Report
Geo-physical Test Report
WATER DEPARTMENT
CAPITAL IMPROVEMENT PLAN UPDATE
Water source issues: Alder Dr. Test Well & Geo-physic Testing
& Quality
Water Source Plan — Test Hales and Well
Projects completed in 2002
Donner Lake plan 2003
Glenshire plan 2003
Capital Improvement Plan for District 2003
Capital Improvement Plan for District 2004, 2005
Project Time lines for the 2003 Capital Projects
Funding for 2003 Capital Projects
Funding for the 2004 & 2005 Capital Projects
Development
Water Quality Results for Alder Drive Test Well
■Arsenic ■Standard (0.01 mg/L)
231-241
i
i
294-304
I
i
347-357
m
d
U.
m 483-493
c
0
d 525-535
a
E
N 714-724
0
m 798-808
c
t 861-871
a
m
945-955
987-997
1092-1102
0 0.01 0.62 0.03 0.04
Arsenic Results (mg/L)
TOPO!map printed on 05/01/03 from"Califom!a.Mo"and"VnUded.tpg"
120-11.000'W 120-10.000'W 120°09.000'W WGS84120°08.000'W
i
LIN
20
¢ 7j dq Gegk
m Sac No 5
� 1 � � � �Fmfhvstoae IaraLon WeT a l
ProsseH We'I plyy Drive Tat Wdl
toa¢m See,N. 3 .f
locum 96c No 6 !- _
Fzgtooaltm SUN. 2
!4F 9 / f 1 q SYJ1
'. ) LJ Jf�/ i , / Glmsturz Drive Web -.EOV�I"/ �
N '
smaa:Wtlt I a — � 7 I
1.
Z `` _ � I .... t<b I I ,l 2
N..ve We➢ _ . .. _ 7._ •At
I .
i' ayuni oP.rtF Q�\ -!: ImaYm Sae No B 5
SOWbstBe Wdl
Z�7
,X
45 YO
o
w o � 'S - it C � . y. v. . we � R
_ f ,
,
y �IU
120-11,000'W 120-10000'W s 120°09000'Wmt WGS84120°08.000'W
TNT)MN _..
1�, ��<rO fEEI 0 �0 tWO MEiE0.5
F=tea fmm TOPO!0=1 Naneel Geogelt]tz HokbW(w ,W,o.cam)
CAPITAL PROJECTS COMPLETED IN 2002
DISTRICT PROJECTS AMOUNT
DONNER LAKE-NORTH SHORE PIPELINES $1,682,000 "
i/ < �.
DONNER LAKE-WEST END SERVICES $1,148,000 - #`'
DISTRICT PIPELINE REPLACEMENT PROJECT $717,000
BRIDGE STREET 6170 TANK $1,640,000
GLENSHIRE PRV STATION $20,000
GLENSHIRE DR. WELL UPGRADE $150,000
GLENSHIRE TRANSMISSION MAIN $1,826,000
TOTAL $7,183,000
DEVELOPER PROJECTS
THE BOULDERS -PHASE 1
TAHOE FOREST HOSPITAL EXPANSION
PIONEER COMMERCE CENTER
PINE FOREST PHASE - 1
TRUCKEE MIDDLE SCHOOL
EAST RIVER PROPERTIES
RIVERVIEW TOWNHOMES
PROPOSED
CAPITAL PROJECTS FOR 2003
DONNER LAKE AMOUNT FUNDING
DONNER TRACT- PIPELINE $300,000 SRF
TRANSMISSION LINE(SURVEY &DESIGN) $40,000 SRF
TANK DESIGN $50,000 SRF x`
GREENPOINT SPRINGS RESTORATION PLAN $25,000 SRF "
BOOSTER STATIONS -DESIGNS $20,000 SRF
TOTAL $435,000
GLENSHIRE
WELL ABANDONMENT $50,000 GF
STRAND BOOSTER STATION $100,000 GF
PIPELINE PROJECT $250,000 GF
TOTAL $400,000
MAIN AREA
I - 80 UNDER CROSSING � �, $100,000 DEV.
TEST WELLS (7) $240,000 FF
PRODUCTION WELL $800,000 FF
u, u
GROUND WATER STUDY PHASE III $60,000 FF
TOTAL $1,200,000
TOTAL FOR ALL PROJECTS $2,035,000
PROPOSED
CAPITAL PROJECTS FOR 2003 � ' .`
`r
DONNER LAKE AMOUNT START COMPLETE
DONNER TRACT-PIPELINE $300,000 MAY OCTOBER
TRANSMISSION LINE(SURVEY &DESIGN) $40,000 NNE NOVEMBER
TANK DESIGN $50,000 JULY NOVEMBER
GREENPOINT SPRINGS RESTORATION PLAN $25,000 JULY AUGUST
BOOSTER STATIONS-DESIGNS $20,000 JULY NOVEMBER
TOTAL $435,000
GLENSHIRE
WELL ABANDONMENT $50,000 JULY OCTOBER
STRAND BOOSTER STATION $100,000 JUNE OCTOBER
PIPELINE PROJECT $250,000 JUNE OCTOBER
TOTAL $400,000
MAIN AREA
I- 80 UNDER CROSSING $100,000 MAY OCTOBER
TEST WELLS (7) $240,000 MAY AUGUST
PRODUCTION WELL $800,000 JULY OCTOBER
GROUND WATER STUDY PHASE III $60,000 AUGUST DECEMBER
TOTAL $1,200,000
TOTAL FOR ALL PROJECTS $2,035,000
_. . ........ _ _ ........ .
PROPOSED
CAPITAL PROJECTS FOR 2004
DONNER LAKE AMOUNT FUNDING
RED MOUNTAIN HYDRO $150,000 SRF
RICHARDS DRIVE PUMP STATION $200,000 SRFIRATES
CEDAR POINT BOOSTER STATION $100,000 SRF
TRANSMISSION LINE $1,200,000 SRF
STORAGE TANK $400,000 SRF
GREENPOINT SPRINGS RESTORATION PLAN $25,000 SRF
NORTHSIDE AREA SERVICES $1,000,000 SRF
TOTAL $3,075,000
MAIN AREA
6170 -NORTHSIDE PIPELINE $500,000 FF
24" PIPELINE NORTHSIDE TO RANCH WAY $2,300,000 FF
24" SANDERS TO FIBER BOARD $1,350,000 DEV.IFF
PRODUCTION WELL $800,000 FF
PIPELINE LINE REPLACEMENT $1,000,000 RATES
SCADA $400,000 RATES
TOTAL $6,350,000
TOTAL FOR ALL PROJECTS $9,425,000
PROPOSED
CAPITAL PROJECTS FOR 2005
DONNER LAKE AMOUNT FUNDING
ABANDONMENT LAKE INTAKE $30,000
ABANDONMENT FROST DR.WELL $10,000
ABANDONMENT WOLF ESTATES WELL $10,000
RED MOUNTAIN TANK(IF NEEDED) $100,000 SRF
GREENPOINT SPRINGS TANK REMOVAL $25,000 SRF
GREENPOINT SPRINGS RESTORATION $25,000 SRF
TOTAL $200,000
MAIN AREA
24" PIPELINE 6170 TO TAHOE DONNER $1,600,000 FF
PUMP STATION 6170 TO TAHOE DONNER $500,000 FF
PIPELINE LINE REPLACEMENT $1,000,000 RATES
NORTHSIDE WELL REHABILITATION $50,000 RATES
TOTAL $3,150,000
TOTAL FOR ALL PROJECTS $3,350,000
_ _ _ _ _ __ _ _.
WATER CONNECTION HISTORY
ACTIVE ADDITIONAL
YEAR CONNECTIONS CONNECTIONS
1977 1901
1978 1980 79
1979 2397 417
1980 2810 413
1981 3261 451
1982 3385 124
1983 3616 231
1984 3875 259
1985 4177 302
1986 4346 169
1987 4528 182
1988 4707 179
1989 4814 107
1990 4936 122
1991 5386 450
1992 5664 278
1993 6070 406
1994 6354 284
1995 6489 135
1996 6550 61
1997 6793 243
1998 6990 197
1999 7277 287
2000 7704 427
2001 9325 1621*
2002 10896 1571**
2001 *1335 Donner Lake & 286 New Development
2002 **1332 Glenshire & 289 New Development
.. ... .. .... .i.............. ........ r
1
Y
DEVELOPMENT
IRRI. YEAR
PROJECT NAME EDU's EDU IMPACT
DEVELOPER 260 0 2003/04
Truckee Sierra Resorts/The Old Greenwood 4 p 2003
Fish Condos 4 Unit Condos @ 12
176 Unit Condos on Deerfield Dr 176 10 20033
/04
The Boulders 2 2003
Tom Grossman 40 Unit Complex-17437 Northwoods-Meadows at TD Condos 8
1 0 2003
Michael &Amy Zanfagna Zanfagna Commercial Building,Commercial Bldg 7,600 sf 8 0 2003
Joe McGinity Chinatown t2 1 2003
Joe McGinity Develop 12 Residential Lots& 1 Irrigation 0 24 2003
Cal Trans Irrigation Services 17 5 0 2003
Tahoe Truckee Unified School New Truckee Middle School 100,000 sf campus 34 10 2003
The Palisades Truckee-34 Condos 3g 3 2003
Riverview Truckee LLC 60 Unit Townhomes @ 10025 Riverview Dr
Ken Inc. - Robert Schwartz Dev: Robert Schwartz-Pine Forest of Truckee 118 single parcels 188 0 2003
p 2003
Prosser Creek Charter School 65 0 2003
Cambridge Estates Phase 4—Subdivision 31 0 2003
South Shore Capital, LLC Truckee Townhomes 31 condos, 7 affordable housing 8 0 2003
TTUSD Transportation Maintenance Operations Facility
2003
Intermountain Development Coyote Run Planned Devel-20 lot planned residential development 22 0 2003
Bob Hunt Hunt-Tapken Brickeltown add new bldg 10250 DPP
John Zerweck/Shire Invest Arbor Meadows 53 townhomes in Martis Valley 14 structures 53 4 2003
Daniel Schnurrenberger Single family residence &4 unit subdivision annexation pending 4 0 2003
2003
Dennis Chez Chez Subdivision 6 0 2003
Dana Tucker Water service extension to 11015 Royal Crest 2003
Howard Henn Subdivide parcel into 2 additional single family residences-Strand 2 0
4 parcels @ 11896 Frond Rd 4 0 2003
Pine Marten Properties P g p 2003
Siotos/Schellinger Townhomes 4 Duplex Townhomes @ 13239& 13257 Northwoods 2.5 0 2003
Jibboom Street Retail 2 0 2003
David Yardas Frond Road water service annexation 4 0 2003
Northwoods 4 Alderhaus Chalets Residential 4-plex @ 11403 Northwoods 5 0 2003
Ztd/Grossman ZTD, LLC 8 0 2003
Gateway East of Truckee LLC Gateway East Bldg C 8 0 2003
Goldie Knapp Knapp Paired Homes 4 0 2003
Eric Penman 4 unit Subdivision 220 10 2004
Joerger Ranch Hands LLC Joerger Ranch Waistreet Phase 1 8 0 2003
MC Taylor MC Taylor Planned Development 67 4 2003
267 Partners LLP Ponderosa Village and Greens at Ponderosa 55 4 2003104
Panderick LLC Pinyon Creek 2 80 4 2003/04
Fitch & Company Ridgeview
Truckee Industrial Park 3 2 2003
/04
Ciro Mancuso 3 0 20033
John Brayton Enterprises Subdivide parcel into 3 lots 2 1 2003
Plumes Bank 1 0 2003
Hunt Mtn Homes
03
Lake Tahoe Mortgage 1 0 203/
1
Subdivision to 4 Parcels 4 200
Robert Montano 2 1 20033
Taco Bell 80 5 2003
Pioneer Commerce On-Site
Old Greenwood 1 2003
d Swim Fitness
Old Greenwood 94 2 2003
Silverwood 94 Unit Development 4 0 2003
Grossman Skislope 4 Unit Condominium 250 0 2004
Tahoe Boca 223-250 Single Family residence subdivision 2003
Old Greenwood
Old Greenwood Maintenance/Resource Center 3 0
TOTALS 1832 88
Problems to avoid
Do not let Electric General Fund be default cash source
Do not let Facility Fee and Developer projects default to rates
Do not spend Surplus Land Trust Fund without knowing exactly how
it is restored
So what do we do?
Have money in hand before we go to bid
If Surplus Land Trust Fund is temporary source, have a plan to
restore it.
Understand the Finance Master Plan (May 21 workshop)
Review how we raise money to fund projects that are related to
growth related
G
t
Cash Requirements vs Cash on Hand
2003 2004 2005 Total
SRF 435,000 3,075,000 Cash on hand
Glenshire 400,000 200,000 3,710,000 0
Developer 100,000 1,350,000 400,000 106,000
Facilities Fee 1,000,000 1,450,000 0
Rates 3,600,000 1,100,000 5,700,000 100,000
1,400,000 1,500,000 2,900,000 0
Surplus Land Trust Fund 14,160,000
4,000,000