Loading...
HomeMy WebLinkAbout7 Red Mountain Storage Tank Agenda Item # Memorandum To: Board of Directors From: Ed Taylor, Water Utility Manager Date: 8-13-2004 Subject: Authorization to bid for the Red Mountain Water Storage Tank. 1. WHY THIS MATTER IS BEFORE THE BOARD: Approval from the Board of Directors is necessary to advertise and receive bids for construction contacts. 2. HISTORY: There is an existing water storage tank located off Mt. Judah Drive on the south side of Donner Lake. This tank is in poor condition and has been out of service since 2001. The tank was removed from service in 2001 due to fears over a catastrophic collapse of the tank. As part of the rehabilitation of the Donner Lake Water System, construction of a replacement tank is planned. The area around the tank and along the pipeline routing is wetlands and additional permits were required to construct the tank and pipeline replacements. The Board previously awarded a contact to Sauers Engineering for design of the improvements. 3. NEW INFORMATION: The design, CEQA, 401 & 404 permits and all planning for the Red Mountain Water Storage Tank are complete. The project plans, specifications, and contract documents are complete for the Red Mountain Water Storage Tank. We are now asking authorization Storage Tank with at o advertise for, accept and open s for the Red bid opening date of September 9, 2004. Mountain 4. RECOMMENDATION. l recommend that the Board authorize staff to advertise for, accept and open bids for the Red Mountain Water Storage Tank with a bid opening date of September 9, 2004. 0 Page 1 SAUERS ENGINEERING Sao 28S 6624 08/13/04 12:14pm P. 001 Sauers Engineering, Inc. Civil & Environmental Engineers Memorandum August 13, 2004 TO: Ed Taylor, District Water Operations Manager FROM: Keith Knibb, Consulting Engineeev SUBJECT: RED MOUNTAIN TANK REPLACEMENT Project plans, specifications, and contract documents are complete for the Red Mountain Tank Replacement project. The project will include the removal of the existing tank and construction of a new tank in the same location. The project has undergone environmental review in accordance with the California Environmental Quality Act. We are asking for authorization to advertise for bids with a proposed bid opening date of September 9, 2004. RECOMMENDATION I recommend the Board authorize advertising for bids for the Red Mountain Tank Replacement project with a bid opening date of September 9, 2004.