HomeMy WebLinkAbout10 Donner Lake Pipeline 2004 Rev sC } j Agenda Item # { { Memorandum To: Board of Directors From: Neil Kaufman Date: September 14, 2004 Subject: Change Order No. 3 for the Donner Lake Pipelines-2004 Project 1. Why this matter is before the board: Approval from the Board of Directors is necessary to issue a Change Order to a construction contract. 2. History: The Board previously awarded the Donner Lake Pipelines-2004 project to Jurin Construction, On August 4, the Board approved Change Order No. 1 that covered all outstanding issues from the project start through June 2, 2004. On August 18, the Board approved Change Order No. 2 that covered all outstanding issues from June 3 through August 6, 2004. 3. New information: I am requesting a Change Order to the Contract for issues covered under three general items that will cover all of the outstanding issues encountered from August 7 through September 3, 2004. Item 1: A total of 50 hours of rock excavation were performed during the period of August 7 through September 3. Jurin's rate is $450 per hour for an excavator with a rock hammer and $525 per hour for a rock saw. Jurin is owed $22,125.00 for this rock excavation work. Item 2: During excavation of the pipe trench, there were a number of locations where the trench was involuntarily widened due to the removal of rocks. These locations require importation of additional backfill material and extra compaction effort. At total of about 92 cubic yards of excess backfill material was necessary due to this issue and Jurin is due $9,624.30 for this work. Page 1 Item 3: As part of the project, the Contractor is supposed to install risers on a new pole to be a installed by the District. Due to a miscommunication between the Water and Electrical Departments, the Electric Department started to install pole on the wrong date. This created a conflict and stopped the contractor's work until the pole installation could be rescheduled. Jurin is due $253.25 associated with this delay. t Item 4: Unmarked and/or mismarked utilities were encountered at five locations. Jurin is due $2,496.90 associated with repair of these utilities. Item 5: As part of the project, the Water Department performed a hot tap of an existing pipe. t Due to a malfunction of the District's tapping machine, it was necessary for Jurin to disassemble some assembled pipe to allow the District to tap the pipe a second time. g Jurin is due $342.83 for this extra work. Item 6: As the Board was previously informed, there was an issue that arose regarding slash and braches that were dumped into a wetland area. After on-site meetings with Scott Ferguson of Lahontan RWQCB, Jurin was directed to perform some exploratory excavations under the supervision of Glenn Merron to investigate the hydrology in this area. This work involved a backhoe and operator for 4 hours. Jurin is due $444.75 for this work. Item 7: The existing TSD lift station at the corner of Donner Pass Road (DPR) and Summit Drive was previously fed by a direct bury cable that ran along the south side of DPR. One component of this project involved installed new conduits to the transformer for the lift station so that a new cable could be run. The location of the existing direct bury cable was shown on the Drawings and the Electrical Department de-energized this cable when the contractor was working in the area as a safety measure. The lift station is equipped with a backup generator and TSD had been informed of the planned work. One Tuesday evening, the Electrical Department was unable to re-energize the cable due to a fault. The Electrical Department spent all day Wednesday attempting to locate the fault with no success. On Thursday, it was decided to pull a new cable into a 4" conduit that had been installed in 1999 jointly with Southwest Gas and Williams Communications. Through a fortuitous stroke of luck, the conduit installed in 1999 ended adjacent to a newly installed electrical vault. It was necessary to excavate an extra 10 feet of trench to connect the conduit installed in 1999 to the new vault. Jurin is owed $1,438.54 for this work. Item 8: The drawings indicated installation of a fire hydrant on the northeast corner of Donner Pass Road (DPR) and Summit Drive. However, after installation of the hydrant side of DPR. Jurin s determined wed $813.21 associated with that a better location for the relocation wouldrant t relocationofhis fire on the south e hydrant. Page 2 4. Recommendation: I recommend that the Board authorize Contract Change Order No. 3, in the amount of a $37,538.78 payment to Jurin Construction from the District. z Attachments: { Change Order Form s i s s Page 3 f� Change Order . . Public UtilitY District Contract Name: DONNER LAKE PIPELINES 2004 r Contract Change Order No: 3 Orig. Contract Amt. $ 1,211,964.00 Days NA Date: September 10 2004 Prev. Apprd Changes $ 74,541.85 Days NA e$Change Days NA Contractor: Jurin Construction This 37 1 Revised Contract Amt. $ 1,324,044.63 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipmentm and price agr eed and upon dorm between work as necessary District.uired to complete the Change Order Items a Increase in (Decrease) Contract Time Contract in Contract Extension Description of Changes Amount $ Amount $ e 125.00 NA 1) flock Excavation $22, NA 2) Trench Overexcavation $9,624.30 25 NA 3} Electric Pole Installation Conflict $253. NA 4) Unmarked Utilities $2,496.90 83 NA 5) Hot Tap Pipe Disassembly $342.75 NA 6) Exploratory Excavations $444. NA 7) Conduit to Power TSD Lift Station $1,438.54 8) Relocate Fire Hydrant $813.21 NA $37,538.78 Totals Net change in contract amount(increase or decrease) The amount of the Contract will be increased by the sum of $37,538.78 and the Contract Time for Milestones der 1 and No. 2 be extended by five working days. The undersigned Contractor approvesthe foregoing Change as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to compapply ete the hereto.Change understood items, that the Change Order shall be effective whenlement f the contract app approved by and all provisions will apply the District. Accepted: /Contractor Date: (Signature) /District Date: Approved: (Signature)