HomeMy WebLinkAbout7 Spring Street Pipeline Rehab Project Agenda Item # 7
FIV
DONNER
Public Utility District
CONSENT
To: Board of Directors
From: Neil Kaufman
Date: August 20, 2014
Subject: Consideration of Final Completion of the Spring Street Pipeline
Rehabilitation Project
1. WHY THIS MATTER IS BEFORE THE BOARD
The Spring Street Pipeline Rehabilitation project is complete. A resolution
accepting the project as complete requires Board approval.
2. HISTORY
The Spring Street Pipeline Rehabilitation project involved sliplining an existing 10-
inch pipe in Spring Street with a new 6-inch pipe and replacing one service lateral.
This work was undertaken in coordination with the Town Truckee's planned
Brickeltown Streetscape project.
In April 2014, the Board authorized award the construction contract for the Spring
Street Pipeline Rehabilitation project. This authorization covered a construction cost
up to $60,000, along with a change order allowance not to exceed $6,000.
In May 2014, the contract was awarded to Aspen Developers with a bid price of
$59,200.
3. NEW INFORMATION
The project began construction in late May 2014 and was completed on July 1, 2014.
During the course of the project, there were two change order items.
The first item involves the installation of an additional 26 feet of pipe at the intersection
on Spring Street and Jibboom Street. The District requested a price proposal from
Aspen Developers for this work after determining that this pipe section was also in
poor condition. Aspen was authorized to proceed with this work based upon a price
proposal of$4,500.
The second item involves a reconciliation of Bid Quantities vs. Actual Constructed
Quantities. The contract is based on a unit price bid. Attachment 1 shows the
differences between bid totals and the amounts actually constructed. This analysis
results in a $2,834.00 credit to the District.
4. FISCAL IMPACT
The original bid price was $59,200. Once adjustments are made for the change order
items, the final contract price is $60,866.00 as shown in the table below. This final
amount is less than the Board authorization of$66,000.
Description Amount
Original Bid Price $59,200.00
CO Item No. 1 - Additional Pipe $4,500.00
CO Item No. 2 - Bid vs. Actual Quantities ($2,834.00)
Total $60,866.00
5. RECOMMENDATION
Adopt a Resolution 2014-18 accepting the Spring Street Pipeline Rehabilitation
project as complete and authorize the filing of the Notice of Completion.
Michael D. Holley
General Manager/Water Utility Manager
Analysis of Bid Quantities vs. Actual Quantities Constructed
Spring Street Pipeline Rehabilitation
Contractor: Aspen Developers
Bid Amounts Actual Amounts
Bid Item Description I Quantity Units Unit Price Subtotal Quantity Units Unit Price Subtotal
1 Mobilization 1 LS $ 6,500.00 $ 6,500.00 1 LS $ 6,500.00 $ 6,500.00
2 Perform Excavation and Backfill at Access Pits 1 LS $ 8,700.00 $ 8,700.00 1 LS $ 8,700.00 $ 8,700.00
3 Slipline Existing 10" Steel Pipe with 6" PE Pipe 425 FT $ 30.00 $ 12,750.00 431 FT $ 30.00 $ 12,930.00
4 1.5" PE Water Service Lateral at 10184 Spring Street 10 FT $ 480.00 $ 4,800.00 8 FT $ 480.00 $ 3,840.00
5 Connection to New 6"Valve at Station 0+00 1 LS $ 2,950.00 $ 2,950.00 1 LS $ 2,950.00 $ 2,950.00
6 Connection to New 8"Valve at Station 4+29.55 1 LS $ 4,000.00 $ 4,000.00 1 LS $ 4,000.00 $ 4,000.00
7 Rock Excavation 2 HRS $ 870.00 $ 1,740.00 0 HRS
$ 870.00 $ _
8 AC Pavement and Base (trench restoration) 230 SF $ 26.00 $ 5,980.00 271 SF $ 26.00 $ 7,046.00
9 Additional '/i' Thickness of AC Pavement (trench restoration) 230 SF $ 6.00 $ 1,380.00 0 SF $ 6.00 $ -
10 IAII Other Work Required by the Contract Documents 1 LS $ 10,400.00 $ 10,400.00 1 LS $ 10,400.00 $___IL400.00JI
$ 59,200.00 $ 56,366.00
Credit to TDPUD $ 2,834.00
D
v
n
3
rn
.i III
Resolution No. 2014 - 18
AUTHORIZING THE ACCEPTANCE OF
THE SRPING STREET PIPELINE ii�'�REHABILITAT
hhION PROJECT
Ii�il�ll
AND DIRECTING FILING OF THE NOTIC ;, 'F; COMPLETION
P�I�iPGuo�,.
� it�ll,11
WHEREAS the Board of Directors of the Truckee Donner Public�ll I i Dis to 19! ade the determination to
undertake the Spring Street Pipeline Rehabilitation Project a 01,:, ��°oll�� � ��
WHEREAS, Aspen Developers was selected by the Distric ,i.;Qj Of orm the work; and
WHEREAS, Aspen Developers has completed all of th �f' ,'o" included in Project; and "+II�h1j''III
Il�lill'C �',y �� '� �Ila. II„I;�,l���hi
�,8� h�ihi,, �lhl� ilif I�
WHEREAS,The District's Water System Engineer, Neil Kau no 1,I I ies the completion of the project;and
II?
WHEREAS,the District's Water Utility Manaichael D. Holle , recommended that the work be accepted
by the District
I,il!Ib liu �,
NOW THEREFORE BE IT RESOLVED by the Bo rd of`Di�e to, of the 611s !' t as follows:
r
��ll �h�1i� oii I1��I i,.
U"`�I�
JIIIUipI@oli:lo111i1��„ iill�4: ��ill'11"11�1�1�'�' ,1'��hil�l°�'iln�., .
1. That the District here•� �� og a Spring,� t I e � ,� eline''Re �htation Project as complete.
ih l i p qua, I p
I Ili ,
pil k}�o1' � ,
2. That the Clerk o , ,,,istrict be di��e,ed to file '#f�pt;he County of Nevada the Notice of Completion,a copy
of which is att ec�hereto.
3. That 35 days follo �,. the i b t ofotnpletion, the monies retained from the contractor
I „�li��l ,�,.I llt�:�, Ihii i �1II11� pre
paymes be release �iiQ tracto�i �� i?�I � I �;Nfiave been made to the District by material suppliers,
u V�Ia�Q:u111��1 r�'i tlll �I,I ltiil��a1 1111111111�1�,1
laibp°ijr!eilbs,ki'otl�,Sb�lcontrac
I4�u,u1,1,,i,,
PASSE�,AND ADOPTED,�j�,the B r of Directors at a meeting dulycalled and held within the District on the
00,��9iiaialr' �'i� ,lil,in glLi {ill g
twentie,l�{day of August 2014�1 the fo�� t g roll call vote:
, ' �,�(, �1i�1111�,, ly�� a�hdd,
, ��':!,
AYES: ,,jll11,il�'
NOES:
AB II!11i�
ABSENT:
,:,�'�;ili��lll;{l�,�il
TRUCKEE DONNER p� �i!V,Ql'' ILITY DISTRICT
lild l;
By
Tony Laliotis, President of the Board
ATTEST:
Michael D. Holley, Clerk of the Board
RECORDING REQUESTED BY:
Truckee Donner Public Utility District
WHEN RECORDED, RETURN TO:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
11570 Donner Pass Road
Truckee, CA 96161lijillf.F.
�.
THE UNDERSIGNED DECLARES
V I,II<h�l Ildl:
DOCUMENTARY TRANSFER TAX- NONE �I�
�,!.,
'II! 6
Ililljli4l!��IIIHI �IIr'
�{,I!I�N Il�ill' l,'!IIIIII(I lll' I,
.a I�IN�u 1INN 'I i,I il.dl�;IN
NOTICE OF COMPI_ I FN
III �����Ill�hllhl
NOTICE IS HEREBY GIVEN: all, ��i
,I��r�ll
�I yfl;jl{ hl lil 018l'�I
1. That the name and address of the public entity for w o he �rtcement project was done, as owner
k I, hWi �i
thereof, is the Truckee Donner Public Utility Distric",11p1'' 0' Donner Pass Road, Truckee, CA
l N
lil,il�llll;I,{;I
I'q,ll l I ulh;Il�,
96161. ,I;�.IIII���II
+!i�d�l{Nllly�liu� Nil I ';�
��
2. Nature of interest or estate of owner be► sfic ia`llpj61brest of a pc .,,utility easement for installation of
III
water facilities. I,a I I
Nijl�i�llii ,,I+''u� Ili;l IIIII�I�I�'
lily I�II(71 III +1 N'
3. That on August 20,201 II l N �� I rafter desc l e�� provemet�ts�� ere accepted as complete pursuant
to Resolution 2014 1 'I I; he T� e Donne 7,11J ,'Itc Utility District, the awarding authority.
�llla�h�ll�llllii•, ' �II I I;,
4. That the subject,l, I vements oft i1Notice arel geperally described and identified as follows: Spring
III I II aq�➢1 li { h'�';II!
Street Pipeline tation P
II;II'� ,llh ,III I��i l���IIItII�II�I�I I��I'I I I
��Gil�lh� i��
5. That the.nqu e,a,nd ad �, I' ' Ef f C contracfo�►�IN I project was:Aspen Developers,P.O.Box 34145,
��{lu.
Renoaf95S,31i!��II;�II°,�,1 lg 'lyl�
I certify under penalty of perjury under the laws of the State of
California that the foregoing is true and correct.
�9ghl� I��;,II
li
Dated: Au ,0, 0, 2014 Ili�i';!I,, TRUCKEE DONNER PUBLIC UTILITY DISTRICT
B
y
Michael D. Holley, General Manager
MAIL TAX STATEMENTS TO:
SAME AS ABOVE
Legal References: CC-3093,CCP-2003 (oath), 2015.5 (unsworn statement)