Memorandum
To: Board of Directors
From: Neil Kaufman
Date: November 14, 2003
Subject: Glenshire Pipelines -2003
1. WHY THIS MATTER IS BEFORE THE BOARD
The Glenshire Pipelines - 2003 Project is complete. It is time for the board to consider a
closeout change order and a resolution accepting the project.
2. HISTORY
The purpose of this project was to construct approximately 2,500 feet of 12-inch water
pipeline, approximately 300 feet of water service lateral, water meter boxes, fire hydrants
and laterals, connections to existing pipelines, and ancillary items such as fittings,
valves, marking tape and other appurtenances. The Glenshire Pipelines - 2003 Project
bid was awarded to FW Carson in the amount of$298,400 on July 8, 2003.
3. NEW INFORMATION
Attached for your review are the change order and the resolution.
4. RECOMMENDATION
a) Consideration of a contract change order Number 1 to the Glenshire Pipelines -
2003 Project
b) Consideration of a resolution accepting the Glenshire Pipelines - 2003 Project as
complete and authorizing the filing of the notice of completion.
TDPUD MEMORANDUM
October 28, 2003
TO: Board of Directors
FROM: Neil Kaufman, Water System Engineer
SUBJECT: GLENSHIRE PIPELINES - 2003
CHANGE ORDER #1
AGENDA #
BACKGROUND:
The Board of Directors previously awarded the Contract for construction of the
GLENSHIRE PIPELINES — 2003 project to FW Carson. The project was completed on
October 24, 2003, 1 am requesting a Change Order to the Contract for issues covered
under three general items that will cover all of the outstanding issues on this project.
Item 1: The contract was based on a unit price bid. The attached table shows the
differences between bid totals and the amounts actually constructed. This
analysis results in amount of $45,260 owed to FW Carson. Please note that
the additional cost is related entirely to pavement restoration issues.
Item 2: During construction of the project, two mismarked water pipes were
encountered and broken. The Contractor is owed $11,283.09 for extra work
related to the repair of these pipes and associated delays.
Item 3: There are a number of existing utilities located at the intersection of The
Strand and Donnington Lane (1-36" Storm Drain, 2-6" Water Pipes, 1-10"
Water Pipe and 1-2" Gas Pipe). The Contract drawings called for the new
pipe to be installed underneath all of these facilities. However, the existing
facilities were deeper than anticipated and the new pipeline had to be
installed about 2-3 feet deeper for a length of about 50 feet. The Contractor
is due $8,400 for extra work associated with this additional depth.
RECOMMENDATION:
I recommend that the Board authorize Contract Change Order #1, in the amount of a
$65,843.35 payment to FW Carson from the District.
Attachment-Contract Change Order #1
Page 1
Analysis of Bid Quantities vs. Actual Quantities Constructed
Glenshire Pipelines-2003
Contractor: 'FW Carson
Bid Amounts Actual Amounts
Bid Item Description Quantity Units Unit Price Subtotal Quantity Units I Unit Price Subtotal
1 Mobilization 1 LS $ 14,000.00 $ 14,000.00 1 LS $ 14,000.00 $ 14,000.00
1A 12"Water Main 1,673 FT $ 50.00 $ 83,650.00 1,671 FT $ 50.00 $ 83,550.00
1B 1.5"PE Water Service Lateral 50 FT $ 80,00 $ 4,000,00 43 FT $ 80,00 $ 3,440.00
1C Double Water Service 1 EA $ 2,000.00 $ 2,000.00 1 FT $ -
1 D Connection to Existing 6"Piping At Station 0+00 1 EA $ 2,000.00 $ 2,000.00 1 FT $ 2,000.00 $ 2,000.00
1E Connections to Existing 6"and 10"Piping At Station 13+ 1 EA $ 2,000.00 $ 2,000.00 1 FT $ 2,000.00 $ 2,000.00
1 F Connection to Existing 8"Piping At Station 16+48 1 EA $ 2,000.00 $ 2,000.00 1 FT $ 2,000.00 $ 2,000.00
1G Connection to Existing 10"Piping At Station 16+73,41 1 EA $ 2,000.00 $ 2,000.00 1 FT $ 2,000.00 $ 2,000.00
1H AC Pavement 7,700 SO FT $ 5.00 $ 38,500.00 14,850 FT $ 5.00 $ 74,250.00
11 All Other Work Required by the Contract Documents 1 LS $ 15.000.00 $ 15,000.00 1 FT $ 15,000.00 $ 15,000.00
2A 12"Water Main 881 FT $ 50.00 $ 44,050.00 874 FT $ 50.00 $ 43,700.00
2B 1.5"PE Service Lateral 240 FT $ 80.00 $ 19,200.00 224 EA $ 80.00 $ 17,920.00
2C Double Water Service 7 EA $ 2,000.00 $ 14,000.00 4 EA $ 2,000.00 $ 8,000.00
2D Fire Hydrant Assemblies 2 EA $ 4,500.00 $ 9,000.00 2 EA $ 4,500.00 $ 9,000.00
2E Connection to Existing 10"Piping At Station 0+00 1 EA $ 2,000.00 $ 2,000.00 1 EA $ 2,000.00 $ 2,000.00
2F Connection to Existing 6" Piping At Station 3+93 1 EA $ 2,000:00 $ 2,000.00 1 EA $ 2,000.00 $ 2,000,00
2G Connection to Existing 6"Piping At Station 5+90 1 EA $ 2,000.00 $ 2,000.00 1 EA $ 2,000.00 $ 2,000.00
2H Connection to Existing 10"Piping At Station 8+80.11 1 EA $ 2,000.00 $ 2,000.00 1 EA $ 2,000.00 $ 2,000.00
21 AC Pavement 4,800 SO FT $ 5.00 $ 24,000.00 8,760 EA $ 5.00 $ 43,800.00
2J All Other Work Required by the Contract Documents 1 LS $ 15,000.00 1 $ 15,000.00 1 EA $ 15,000.00 $ 15,000.00
8 298,400.00 $ 343,660.00
Amount Owed to FW Carson: $ (45,260.00)
NOQ-3-2003 09:47 FROM:F W CARSON CO 7758315068 TO: 15305871189 P:2,2
Oct-31-03 12:53cm Fran-TRUCKEE DOiNER PUD + T-146 P.02/02 F-329
TRUCKEE DONNER Change Order
Contract Name: Glenshire Pipelines-2003
Contract Change Order No: 1 Orig. Contract Amt. $ 298.400.00 Days NA
Date: October 28,2003 Prev.Apprd Changes$ 0.00 Days NA
Contractor, FW Carson This Change$ 85.843.35 Days NA
Revised Contract Amt$ 364,243.35 Days NA
This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct,
furnish equipment and materials, and perform all work as necessary or required to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District
Increase in (Decrease) Contract Time
Description of Changes Contract in Contract Extension
P 9 Amount $ Amount $ da
1) Bid vs.Actual Quantities $45,260.00 NA
2) M(smarked Water Pipelines $12,163.35 NA
3) Additional Trench Depth $8,400.00 :... NA
Totals $65,843.36
Net change in contract amount(increase or decrease) $65,843-35
The amount of the Contract will be increased by the sum of $64,943.09 and the Contract Time shall not be
extended. The undersigned Contractor approves the foregoing Change Order as to the changes, rf any, in the
contract price specified for each item including any and all supervision costs and other miatallaneous costa
rotating to the change In work, and as to the extension of time allowed, if any,for completion of the entire work on
mount of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other
necessary work, Inclusive of the directly or Indirectly related to the approved time extension, required to complete
the Change order items_ This document will become a supplement of the contract and all provisions will apply
hereto. It is understood that the Change Order shall be effective when approved by the District.
Accepted: �C /Contractor Date:
(Signature)
Approved: /District Date:
(Signature)
UCKEE DONNER
Public UtilityDistrictit
Resolution No . 2003- XX
AUTHORIZING THE ACCEPTANCE OF THE GLENSHIRE PIPELINES - 2003 AND
DIRECTING FILING OF THE NOTICE OF COMPLETION
WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the
determination to undertake the Glenshire Pipelines -2003 Project; and
WHEREAS, F.W. Carson Co., was selected by the District to perform the work; and
WHEREAS,the District's Water Systems Engineer, Neil Kaufman, has recommended that the work
be accepted by the District;
NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows:
1. That the District hereby accepts the Glenshire Pipelines - 2003 Project as complete.
2. That the Clerk of the District be directed to file with the County of Nevada the Notice of
Completion, a copy of which is attached hereto.
3. That 35 days following the filing of the Notice of Completion, the 10% retained from the
contractor payments be released to the contractor if no claims have been made to the District
by material suppliers or laborers.
PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the
District on the 191h day of November 2003 by the following roll call vote:
AYES:
ABSTAIN:
NOES:
ABSENT:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
J. Ron Hemig, President of the Board
ATTEST:
Peter L. Holzmeister, Clerk of the Board
bhc
RECORDING REQUESTED BY:
Truckee Donner Public Utility District
WHEN RECORDED, RETURN TO:
TRVCKEGnONNER PUBLIC UTILITY DISTRICT
Post Office Box 309
Truckee, CA901O0
NOTICE 0FCOMPLETION
NOTICE |S HEREBY GIVEN:
1. That the name and address of the public entity for whom the improvement project waSdone' asowner
thereof, iS the Truckee Donner Public Utility District, Post Office Box 300. Truckee, CA9H1GU.
2. That on November 19. 2003' the hereinafter described improvements were accepted as complete
pursuant to a resolution of the Truckee Donner Public Utility District, the awarding authority.
3. That the subject improvements of the Notice are generally described and identified as follows:
Glem$hire Pipelines ~2903 Project, l[ruckee, Ca.
4. That the name and address of the contractor for such project was: F.W. Carson, 1064 Tahoe Blvd,
Incline Village , NVD945D.
| certify under penalty of perjury under the laws of the State of
California that the foregoing io true and correct.
Dated: TRUCKEED0NNFR PUBLIC UTILITY DISTRICT
B