HomeMy WebLinkAbout10 Donner State Park Project Agenda Item #
Memorandum
To: Board of Directors
From: Joe Horvath, District Electrical Engineer
Date: August 31, 2005
Date of Board Meeting: September 7, 2005
Subject: Bid Award Recommendation for the "Installation Of Electric Conduit And Vaults
In Donner State Park" Project
1. WHY THIS MATTER IS BEFORE THE BOARD
Only the Board can approve bid awards.
2. HISTORY
The District has an existing high voltage primary cable system, installed in the late 1960s,
supplying three sewer pumping stations located within Donner State Park with electric service
via a radial feed originating at the District's overhead power line at Donner Pass Road (see
Drawings 1 and 2). The cable system consists of a single direct buried cable, operating at a
system voltage of 12.47kV, with bare (i.e. exposed) concentric neutral conductors located on
the outside of the cable. The District no longer installs cables with bare neutral conductors or
uses direct buried cable construction due to neutral conductor corrosion problems and cable
replacement issues. The existing cable through the Park is at the end of its projected 35 to 40
year life and must be retired and replaced with new cable.
In anticipation of the need to replace this cable and establish a loop feed to the existing
overhead distribution circuit on South Shore Drive, the District identified this work as a capital
improvement project. Early in 2003, staff learned that the California Department of Parks and
Recreation (Parks Department) was proceeding with a project to replace about 6,500 feet of
existing water pipeline through the Park. The pipeline alignment followed the day use road from
the Park entrance kiosk to the China Cove area. This was exactly the alignment the District
needed to replace a majority of our direct buried cable and establish a loop connection to our
overhead circuit on South Shore Drive. We immediately began a discussion with the Parks
Department about installing a conduit in the same trench as the new water pipeline. By the time
the Parks Department gave the District permission to install a conduit, they had awarded their
project to the low bidder. One of the Parks Department's requirements was that the District
could not use a different contractor to install the electric conduit. Therefore the District
negotiated directly with their contractor. The agreed upon price and contract was brought to the
Board for their approval on September 2, 2003. Attached for your reference are copies of the
memorandum to the Board and Resolution Dispensing with Bidding. The installation of 6,500
feet of conduit was completed in the fall of 2003.
One of the limitations of the project at the time was that the State's CEQA documents only
allowed for excavation within the existing pipeline trench alignment. In other words, the District
could not install vaults or any other conduit outside of this alignment. Therefore, in order to
make use of this new conduit, it was recognized that the District would need to pursue the
necessary permits and approvals for the remaining work at some future time. This remaining
work included the installation of vaults every 700 to 800 feet along the conduit alignment for
cable pulling purposes, approximately 10 vaults in total. Since the water pipeline project started
and ended at locations near, but not immediately adjacent to, the District's existing overhead
electric facilities, short sections of new trench and conduit would also be required at each end of
the existing empty conduit system to make the necessary electrical connections. In addition,
the existing electric transformers that serve the three sewer pumping stations, fed via the old
direct buried cable, are located some distance away from the existing empty conduit alignment.
These sections will also require trenching and conduit installation. In summary, approximately
10 vaults and 2,400 feet of new trench and conduit would be required to complete the project.
3. NEW INFORMATION
Contributing to the need to replace the District's direct buried cable system in a timely manner is
the Truckee Meadows Water Authority's (TMWA) Donner Dam Improvement Project. The Dam
Improvement Project will extensively modify the existing dam to increase its structural strength,
including the installation of a new electric service from the District to automate the gate controls.
Construction started in July and is expected to be complete by October of this year. The
District's direct buried cable crosses through the existing dam structure and must be de-
energized to allow construction to proceed.
District staff met with TMWA and Parks Department officials in Donner State Park in late June of
this year to discuss the Dam Improvement project. The District proposed energizing a short
section of our new empty conduit system through the Park by the construction of three vaults
and a small amount of new trench and conduit, enough to bypass the portion of the direct buried
cable system through the dam. Although the Parks Department recognized that this was the
best solution to allow the Dam project to proceed, the construction of vaults and trenches could
not proceed until the necessary CEQA documents were filed and approved. In addition, the
Parks Department emphasized that the CEQA documents must cover the entire work necessary
for the District to replace the direct buried cable system through the Park, not just the portion to
bypass the Dam. As a temporary measure to allow the direct buried cable to be de-energized
while TMWA proceeds with construction, the District spliced into the old cable and installed
cable risers on two newly placed 60 foot tall wood poles, located on either side of the dam, with
overhead conductors spanning the project work area.
Shortly after the on site meeting, the District prepared a project description and drawings
depicting the proposed work necessary for the CEQA filing. The Parks Department filed the
CEQA documents and PRC 5024 Project Evaluation documents on the District's behalf. The
Parks Department State Archaeologist recommended that only archaeological monitoring be
required during construction activities. Donner State Park is listed on the National Register of
Historical Places and is known to have extensive cultural resources still in place. The
archaeological monitoring requirement is the least burdensome and least costly of the options
that the State could have imposed on the District. In short, I believe we have the good will and
cooperation of the Parks Department to proceed with this project. By way of contrast, TMWA
had to hire consultants to prepare the CEQA documents for the Dam Improvement project.
The Parks Department emphasized that they want as much of the construction to be completed
this fall as possible. Therefore District staff prepared, on short notice, construction plans and
specifications necessary to solicit bids. Bid opening is scheduled for Tuesday, September 6,
allowing for a minimum 2 week long bid period. Bid results therefore are not available at this
time to make a recommendation of award.
Because Parks Department archaeologists were already committed to other projects, they
recommended the services of a local archaeologist, Dr. Susan Lindstrom to perform the
required archaeological monitoring during construction. Dr. Lindstrom lives in the Donner Lake
area, has performed work in Donner State Park, and is very familiar with the Park Department's
requirements and procedures. Her rate sheet is attached for the Board's consideration.
4. RECOMMENDATION
1. I expect to have bid results and present a recommendation for bid award at the Board
meeting.
2. 1 recommend the Board authorize staff to retain Dr. Susan Lindstrom and her associates,
on a time and materials basis per the attached rate sheet, as the monitoring
archaeologist for the project per California Department of Parks and Recreation
requirements.
---
susury L1NllSIR6 PACE 01
Susan UndstrSm, Ph.D.
Coasaltiog Archaeobgist
P.O. BOX 3324
Truckee CA%160
530-587.7an voice
530-587-7083 to
sliadatrom�q jlq,uet
DATE: August 17, 2005
TO: Jo Horvath
TDPUD
RE: Donner Memorial State Park.
Electrical Line/Vault,
Archaeological Monitoring
Hourly rates for archaeological monitoring are as follows. Note that rates include a 15%
overhead fee:
Principal Archaeologist $110.00
Assisting Archaeologist _ $ 35.00 Per hour
p
Native American Consultant = $ 30.00 e hour
per
hour
Mileage = $ .40 per mile
Per Diem $125.00 per day
Out-of-pocket expenses = (as incurred)
}
E
F
s
f
4
Agenda Item #
• DONNER
Public UtilityI� District
Morrio
To: Board of Directors
From: Peter Holzmeister
Date: August 29, 2003
Subject: Dispensing with bidding for installation of electric conduit through Donner
Memorial State Park
WHY THIS MATTER IS BEFORE THE BOARD
This matter involves adopting a resolution dispensing with bidding. Only the Board can do that.
HISTORY
The District has wanted to establish a loop feed to serve electric load at Donner Lake for many
years. We have tried on several occasions to secure an easement from Donner Memorial State
Park, but they have always refused our request. If we had a loop feed the weeklong outage at
Donner Lake last December would have effected fewer customers. We would have been able
to restore power to many of them by means of the feed through the Park. There as many
similar outages experienced over the years that would have been less severe if the loop had
been in place.
NEW INFORMATION
The State Park owns its own internal water system. We serve water to that system from a
delivery point at the edge of the park. The internal water system is being replaced. The Park
officials have granted permission for us to install a conduit in their trench during construction of
their water line. We can then install an electric wire in the conduit at a future time, along with
necessary vaults, thus establishing the necessary loop.
The price quoted by the State's contractor is $35 per linear foot. The length of conduit is
approximately 6,500 linear feet, for a total price of $227,500. We have sufficient funds in the
electric facilities fund to cover this cost.
We will not have this opportunity again.
RECOMMENDATION
1. 1 recommend that the Board adopt the resolution dispensing with biding and authorizing
execution of a contract to install electrical conduit through the Donner Memorial State Park.
2. 1 further recommend that the Board authorize the transfer of $227,500 from electric facilities
fees to cover the cost of this contract.
i
...........................
RLICK.. I
b ,� Il ��a
Resolution No. 2003- 38
DIRECTING THAT COMPETITIVE BIDDING BE DISPENSED WITH IN
CONNECTION WITH THE DISTRICT'S PURCHASE AND CONSTRUCTION OF
UNDERGROUND ELECTRIC CONDUITS IN CONJUNCTION WITH THE
CALIFORNIA DEPARTMENT OF PARKS & RECREATION'S REPLACEMENT OF
THEIR WATER LINES WITHIN THE DONNER MEMORIAL STATE PARK
WHEREAS, the California Department of Parks & Recreation ("State") is currently starting
excavation through the Donner Memorial State Park to replace its water lines; and
WHEREAS, joint trenching is beneficial because it reduces the noise and other environmental
impacts of excavation by only trenching in an area once, rather than twice; and
WHEREAS,joint trenching is beneficial to the District's customers because it reduces the trenching
costs by approximately fifty percent and obtains the best economic result for the public; and
Whereas, the District for years has tried to obtain access through the Donner Memorial State Park
for underground electrical facilities and has been denied an easement by the State; and
Whereas, the District for years has had a direct buried electrical cable feeding into the Donner
Memorial State Park; and
Whereas, the existing direct buried cable is many years past its' life expectancy; and
Whereas, the existing direct buried cable serves two sewer pump stations along Donner Lake;and
Whereas, the failure of this cable could possibly result in a sewage spill near Donner Lake; and
Whereas,an electrical connection through the Donner Memorial State Park would result in improved
electrical service reliability for the entire Donner Lake area; and.
Whereas, if this electrical connection would have been in place during the December 2002 storm,
the outage to many customers could have been reduced by days; and
Whereas, the State will be replacing its failing water lines within the Donner Memorial State Park;
and
Whereas, the State has completed the CEQA process to replace its water lines; and
Whereas, there is an existing contract by the State to replace its water lines; and
Whereas the State has now agreed to let the District have electrical conduit installed into the same
trench with the new water lines and through the Donner Memorial State Park,and has informed the
District that if it does not install its facilities at this time, it will not be allowed to do so in the future;
and
Whereas, the electrical conduit will be installed into a trench width that was described in the CEQA
review; and
1
t
Whereas, the State's contractor has agreed to install the District's electrical conduit into the same
trench as the water facilities for$35.00 per foot; and
Whereas, there is approximately 6,500 feet of trench within which the District would like to install
joint electrical facilities with the State's new water facilities; and
Whereas, if the District were able to install its own trench (which the State would not allow)it would
cost more than joint trenching with another entity; and
Whereas, the cost of installation of this conduit is comparable to other installations the District has
bid in the past; and
Whereas, the District must purchase conduit for the joint trench project; and
Whereas, the District will not have sufficient time to competitively bid for some of the conduit
required for the joint trenching with the Donner Memorial State Park project; and
Whereas, if the District has electrical conduits installed,the State Park has agreed to work with the
District on an electrical easement through the Donner Memorial State Park; and
Whereas, the District learned that the State's contractor is currently mobilizing for this project and
will start excavation during the first week of September 2003; and
WHEREAS, various California court decisions, including Graydon v. Pasadena Development
Agency 104 Cal. App.3d 631 (1980), hold that if the subject of a contract is such that competitive
proposals would be unavailing or would not produce an advantage and the advertisement for
competitive bids would thus be undesirable, impractical or impossible, a public agency may
dispense with competitive bidding; and
WHEREAS,due to the facts set forth above, competitive bidding would be unavailing and would not
produce an advantage to the District,and the advertising for competitive bids would not produce an
advantage to the District and would be undesirable; and
WHEREAS, the District has determined that entering into a joint trenching agreement with the
contractor installing the new water lines for the State is required to integrate the trenching activities
of the two entities and obtain the advantages outlined above; and
WHEREAS Public Utilities Code Section 20201 generally requires that the District seek competitive
bids when engaging in new construction if the cost of materials,supplies and labor exceed$15,000;
and
NOW THEREFORE, BE IT RESOLVED that the Board of Directors adopts the above recitals as its
findings; and
BE IT FURTHER RESOLVED by the Board of Directors that for the reasons set forth above, the
District finds that seeking competitive bids for the excavation of trenches and installation of electric
facilities through Donner Memorial State Park would be unavailing,would not produce an advantage
to the District, and would be undesirable and costly in that it would result in the District not being
able to install new electric facilities through the Donner Memorial State Park.
BE IT FURTHER RESOLVED that the District shall therefore dispense with competitive bidding for
the excavation of trenches and installation of electrical facilities through the Donner Memorial State
Park; and that the District General Manager is authorized to negotiate and execute contracts with
the State and/or its contractor for such excavation and installation work.
2
BE IT FURTHER RESOLVED that the District shall therefore dispense with competitive bidding to
purchase the necessary conduit and electric facilities for installation through Donner Memorial State
Park, and that the District General Manager is authorized to negotiate and execute contracts forthe
purchase of such conduit and facilities.
PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the
District on the second day of September, 2003 by the following roll call vote:
AYES: Directors Aguera, Hemig and Maass
NOES: None
ABSENT: Directors Sutton and Van Gundy
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
J. emig, Pre —�
ATTEST:
' t' ) W,
t r' n,
Peter L. Holzmeister, District Clark
3
Agenda Item # 10
Memorandum
To: Board of Directors
From: Joe Horvath, District Electrical Engineer
Date: September 7, 2005
Date of Board Meeting: September 7, 2005
Subject: Bid Award Recommendation for the "Installation Of Electric Conduit
And Vaults in Donner State Park" Project
1. WHY THIS MATTER IS BEFORE THE BOARD
Only the Board can approve bid awards.
2. HISTORY
The District opened bids for the subject project on Tuesday, September 6, 2005. Two
bids were received with the results shown below:
Hard Longo
Line
Bid Unit Unit
Item Description Ot Units Price Subtotal Price Subtotal
1 Mobilization 1 LS 20,000 20,000 38,000 38,000
2 4" Conduit 2400 FT 65 156,000 59 141,600
3 Vaults 10 EA 11,000 110,000 17,600 176,000
4 Bridge Conduit 1 LS 7,000 7,000 1,200 1,200
5 Conduit Risers 2 EA 5,000 10,00 11,250 2,500
6 Rock 3 HRS 12,000 36,000 750 2,250
Excavation
7 AC Pavement 1500 SQFT 25 37,500 12.50 18,750
8 All Other Work 1 LS 15,000 15,000 17,500 17,500
Totals $391,500 $397,800
j
3. NEW INFORMATION
Hard Line Excavating is the low bidder for the work. However, I recommend that the
Board reject their bid as not being in the best interest of the District. The reason for this
recommendation is their extremely high unit price for rock excavation and the unknown
amount of rock excavation that will be required for the project. On recent District
projects, unit prices for rock excavation have varied between $350 and $850 per hour.
Hard Line's price of$12,000 per hour is 15 to 30 times more expensive than the
average. We expect to encounter rocks on this project and although we have no way
of predicting the exact amount of time required to perform rock excavation work, it
would not be surprising to have spent 10 or more hours to remove rocks. If we select
Hard Line as our contractor, we potentially would have to approve a change order of
over $100,000 due to a day's worth of rock excavation. This is unacceptable in my
opinion.
The Board has the authority to reject bids. This authority is clearly stated in Section
00100 of the Contract Documents and in California's Public Contract Code, repeated
below:
The DISTRICT reserves the unqualified right in its sole and absolute
discretion to reject any and all Bids, and to accept the Bid or Bids which, in
its sole and absolute judgment, will, under all circumstances, best serve the
interests of the DISTRICT. (Section 00100, Article 6, Contract Documents)
In considering bids the board may accept or reject all or any of them, or
may accept or reject part of a bid, preference being given to the lowest
responsible bidder. (PCC Section 20207.1)
Time is of the essence for this project. The Parks Department emphasized that they
want as much of the construction to be completed this fall as possible. They have
given us a deadline of June 15, 2006 to complete the work. For this reason, and the
others mentioned in my memorandum dated 8/31/05, 1 believe the Board should award
the contract to the next lowest bidder so that construction can begin this fall.
4. RECOMMENDATION
1. 1 recommend that the Board reject Hard Line's bid as not being in the best
interest of the District. I recommend the Board award the project to next lowest
bidder, Longo Construction, for a Contract price of $397,800 to be paid from
Electric facility fee funds.
2. 1 recommend the Board authorize staff to retain Dr. Susan Lindstrom and her
associates, on a time and materials basis per the attached rate sheet, as the
monitoring archaeologist for the project per California Department of Parks and
Recreation requirements.