HomeMy WebLinkAbout12 District Pipeline Replacement 2005 Agenda Item #
Memorandum
To: Board of Directors
From: Neil Kaufman
Date: August 12, 2005
Subject: Change Order No. 1 for the District Pipeline Replacement-2005 Project
1. Why this matter is before the board:
Approval from the Board of Directors is necessary to issue a Change Order to a construction
contract.
2. History:
The Board previously awarded the District Pipeline Replacement-2005 project to Hard Line
Excavating (HLE).
3. New information:
The pipeline construction along Richards Boulevard has been completed. Completion of this
pipeline was critical to the District meeting the June 30, 2005 deadline for converting the Donner
Lake area to a groundwater supply.
I am requesting a Change Order to the Contract for issues covered under four general items
that will cover all of the issues encountered during the Richards Boulevard construction.
Item 1: For a small portion of Richards Boulevard, there are two pipelines in parallel, a 6-
inch pipe that was installed in the 1960s and the 14-inch pipe installed in the early
1970s. Pressures in the 14-inch were not adequate to serve the residences in the
area, so it was necessary to keep the 6-inch pipe (which was higher pressure) in
service. In the Fall of 2004, a 6-inch intertie between these two pipelines was
constructed to accommodate additional flows generated by the Richards Pump
Station. At the time that this intertie was constructed, it was anticipated that the high
water elevation of the new tank to be constructed off Donner Lake Road would be at
the same elevation as the existing Armstrong Tank.
i
During design of the Donner Lake Road Tank, it was determined that the new tank
would have to be at a lower elevation than the Armstrong Tank. As a result, it was
necessary to change a tee/valve assembly originally shown in the plans. The
t
Page 1
original Bid Item totaled $17,500,00 and was deleted from the contract. The
changed design totaled $7,091.71 in cost and HLE is owed this $7,091.71.
Item 2: During the Winter of 2004-2005, a District crew removed a 22 degree elbow from
inside the existing manhole structure between Richards Boulevard and Interstate 80.
This elbow was removed in order to accommodate pressure testing of the pipeline
section underneath Interstate 80. Due to other commitments, the District crew did
not have time to reinstall the 22 degree elbow and 1 directed HLE to perform this
work. HLE is owed $597.11 for this work.
Item 3: Due to the high pressures along Richards Boulevard it is necessary to have pressure
reducing valves (PRVs) installed on the services. These pressure reducing valves
were inadvertently omitted from the original Bid Documents. HLE was directed to
install the PRVs at a cost of$1,354.92.
Item 4: There are a number of springs and seeps located along Richards Boulevard. In
addition, there are significant drainages that run through the project area carrying
runoff and snowmelt from uphill areas.
In an ideal situation, construction of the pipeline along Richards Boulevard would
have been postponed until later in the Summer to allow the area to dry out.
However, as noted above, completion of the Richards Boulevard Pipeline had to be
achieved by June 30tn
It was necessary to begin construction of May 2 in order to meet the June 30tn
deadline. Consequently, HLE was forced to divert surface drainage around the pipe
trenches and encountered a significant amounts of groundwater during the pipeline construction. In response to the groundwater I directed that the bottom portion of the trench be bedded with drain rock
The wet conditions contributed to sloughing of the trench walls and undermining of
the roadway pavement. In addition, it was not possible to reuse the excavated
trench spoils because they were too wet. These problems likely would not have
arisen in dry conditions.
HLE submitted a claim for $83,367.34 related to installation of the drain rock,
importation of additional backfill, disposal of additional trench spoils and the wider
trench resulting from the sloughing. Also included in this claim was additional
excavation required to remove a 30 foot long concrete cap over the top of the old
pipe that the District was unaware of.
I have reviewed the data submitted by HLE and had three meetings with the owners
regarding this issue. We finally agreed upon an amount of $38,057.67 in regards to
this issue.
As a result of this groundwater issue, I will be revising the excavation and earthwork
specifications for projects that are constructed in the future.
t
Page 2
4. Recommendation:
I recommend that the Board authorize Contract Change Order No. 1, in the amount of a
$47,101.41 payment to Hard Line Excavating from the District.
Attachments:
Change Order Form
s
t
K
s
z
F
Page 3 —
K
TRUCKEE s • !
Change Order
Contract Name: DISTRICT PIPELINE REPLACEMENT-2005
Contract Change Order No: 1
Orig. Contract Amt. $ 600,904.00 Days NA
Date: August 12 2005
Prev.Apprd Changes $ 0.00 Days
Contractor: Hard Line Excavating -�------------- NA
This Change$ $4.7,101.41 Days NA
Revised Contract Amt. $ $64_-8,005 41 Days NA
This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct,
furnish equipment and materials, and perform all work as necessary or required to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District.
Increase in (Decrease) Contract Time
Description of Changes Contract in Contract Extension
Amount $ Amount $ da
1) Tee/Valve Assembly at Station 0+61 s
2) 22'Elbow at Manhole Structure $7,091.71 NA
3) Pressure Reducing Valves at Meter Boxes $597.11 NA
4) Mud&Groundwater $1,354.92 NA
$38,057.67 NA
Totals
$47,101.41
Net change in contract amount(increase or decrease)
$47,101.41
The amount of the Contract will be increased by the sum of
$ an theextended. The undersigned Contractor approves the foregoing Change40rdetlas toCthet hangeseif anonract Tim shely,fntthe
contract price specified for each item including an y an a supervision costs and other relating to the change in work, and as to the extension of time allowed, if any, for completion ofrt a miscellaneous
work o on
account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other
necessary work, inclusive of the directly or indirectly related to the approved
the Change order items. This document will become a supplemet of the contract me e and all provisions complete
hereto. It is understood that the Change Order shall be effective when approved by the District.
Accepted:
n.vnrractor Date:
(Srgnature}
Approved:
(Signature) District Date: