HomeMy WebLinkAbout8 Change order Donner Lake Pipeline Agenda Item #
Public Utility District
Memorandum
To: Board of Directors
From: Neil Kaufman
Date: July 15, 2004
Subject: Change Order No. 1 for the Donner take Pipelines-2004 Project
1. Why this matter is before the board:
Approval from the Board of Directors is necessary to issue a Change Order to a construction
contract.
2. History:
The Board previously awarded the Donner Lake Pipelines-2004 project to Jurin Construction.
3. New information:
Construction of the project began at the end of May. I am requesting a Change Order to the
Contract for issues covered under three general items that will cover all of the outstanding
issues encountered as of June 2, 2004.
Item 1: Jurin is constructing a new 12-inch pipe in Donner Pass Road that will connect to an
existing 18-inch steel pipe that was installed by Dart Industries in the early 1970s.
This pipe was originally intended as the discharge pipe for a lake intake and water
treatment plant to be located at the current site of the Tahoe Donner Association's
beach at the east end of Donner Lake. The 18-inch pipe was constructed along the
south of Donner Pass Road and crosses Interstate 80 just west of Coldstream Road.
The current plan for the 18-inch pipe is to serve as the transmission line to carry
water from Gateway area to Donner Lake.
Sometime in the 1970s, after completion of the lake intake, treatment plant and
pipeline, Dart was unable to place the facilities into service due to unresolved legal
issues. At that time, the lake intake was filled with concrete and the equipment was
removed from the water treatment plant. There was also a general rumor that 10
feet of pipe had been removed from the 18-inch pipeline, but there were not any
maps to indicate where the missing 10 feet was.
In the Fall of 2003, District crews attempted to fill and pressure test the 18-inch pipe
in anticipation of the 2004 pipeline construction. While filling the line, the "missing 10
feet' was located. It was found that 48 feet of pipe had been removed. The District
then ordered some new 18-inch pipe and couplings to install in the 48-foot gap. By
Page 1
the time that the couplings arrived from the factory, it was too late in the season to
perform the pipe installation and it was postponed until 2004.
After award of the Donner Lake Pipelines-2004 project to Jurin, I requested a price
proposal to install the 48 feet of pipe. The Jurin provided a price of $70 per foot.
This price was acceptable and Jurin was directed to proceed.
The pipe has been installed and Jurin is owed $3,360 for this work
Item 2: The Donner Lake Pipelines-2004 Contract Documents calls for installation of a
temporary 4-inch water pipe that would enable to the District to continue service to
Cedar Point Drive while the new 12-inch pipeline was installed across the Greenpoint
Springs property. This 4-inch pipe was sized based upon the planned Richards
Boulevard Pump Station being in service.
However, construction of the Richards Boulevard Pump Station has not yet begun.
Therefore, it was necessary to upsize the pipe from 4-inch to 6-inch in diameter and
change the points of connection. Jurin is owed $716.80 associated with this
upsizing.
The changes in connection points required a schedule water outage in order to -
connect the temporary water pipe and remove an existing 6-inch pipe from service.
The number of customers that would be impacted by this outage was about 400-500.
It was decided to perform this work overnight in order to minimize the impact upon
the customers. The outage took place beginning at 10:00 PM on June 29 and was
completed by 6:30 AM on June 30. Two District crew members were on-site during
the outage and others were available on call if necessary.
Jurin is owed $3,959.85 for labor and $400 for rental of a light trailer for performance
of this work.
Item 3: A total of 32.5 hours of rock excavation have been performed as of July 2, 2004.
Jurin's rate is $450 per hour. Therefore, Jurin is owed $14,625 for rock excavation
through July 2.
4. Recommendation:
I recommend that the Board authorize Contract Change Order No. 1, in the amount of a
$23,061.65 payment to Jurin Construction from the District.
Attachments:
Change Order Form
Page 2
V TRUCKEE DTINER JTbUlic Utility District
Change Order
Contract Name: DONNER LAKE PIPELINES-2004
Contract Change Order No: 1 Ong. Contract Amt. $ 1,211,964.00 Days NA
Date: July 15, 2004 Prev. Apprd Changes $ 0.00 Days NA
Contractor: Jurin Construction This Change$ 23,061.65 Days NA
Revised Contract Amt. $ 1,235,025.65 Days NA
This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct,
furnish equipment and materials, and perform all work as necessary or required to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District.
Increase in (Decrease) Contract Time
Contract in Contract Extension
Description of Changes Amount $ Amount $ (days)
1) Installation of 18-inch Pipe $3,360.00 NA
2) Modifications to Temporary Water Pipe $5,076.65 NA
3) Rock Excavation $14,625.00 NA
NA
NA
NA
NA
Totals $23,061.65
Net change in contract amount (increase or decrease) $23,061.65
The amount of the Contract will be increased by the sum of $23,061.65 and the Contract Time for Milestones No.
1 and No. 2 be extended by five working days. The undersigned Contractor approves the foregoing Change Order
as to the changes, if any, in the contract price specified for each item including any and all supervision costs and
other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for
completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and
materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time
extension, required to complete the Change order items. This document will become a supplement of the contract
and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by
the District.
Accepted: /Contractor Date:
(Signature)
Approved: /District Date:
(Signature)