HomeMy WebLinkAbout7 Donner Lake Pipeline 2004 v y
Agenda Item #
SEEM,
Memorandum
To: Board of Directors
From: Neil Kaufman
Date: May 18, 2004
Subject: Bid Award for the Donner Lake Pipelines - 2004 Project
1. Why this matter is before the board:
Board Authorization is required to award a contract for construction
2. History:
The Board previously authorized staff to advertise for construction of the Donner Lake Pipelines -
2004 project.
On May 13, Bids were received and opened for this project. Staff has totaled and reviewed all bids.
Three Addenda were issued for this project covering the following issues:
• Addition of conduits, vaults and pull boxes to create a joint trench in part of the project.
• Addition of an additional 1,063 feet of pipeline alignment into the project.
• Issuance of the project Stormwater Pollution Prevention Plan
A summary of the Bids is given below:
Bidder Location Amount
Jurin Construction Willow Creek, CA $1,211,964.00
Hansen Brothers Grass Valle , CA $1,310,366.00
Burdick Excavatin Kin s Beach, CA $1,753,377.00
At the Bid opening, a minor irregularity was identified with the Bid submitted by Jurin
Construction. This issue was been referred to District legal counsel.
3. New information:
The minor irregularity with the Bid submitted by Jurin Construction involved the Debarment
Certification. This is a one-page form that essentially says that the Bidder has not been `
excluded from bidding on any Federal, State or Local contracts for cause. A copy of the
Debarment Certification is attached.
The Bid Opening was held at 11:00 AM on May 13. The Bid Documents call for this certification
to be submitted with the Bid. Jurin Construction failed to submit this completed form with the
Bid.
F
After the Bid Opening, both District legal counsel and the Department of Health Services (DHS)
were contacted in regards to the proper action to take in this circumstance. DHS was contacted
since the project is going to be funded by the SRF loan and I wanted to ensure that the District
did not jeopardize SRF funding for the project.
At about 1:00 PM, Ron Jurin, owner of Jurin Construction called the District inquiring as to the
Bid Opening results. I informed him that Jurin Construction had submitted the apparent low Bid
on a dollar basis. I also informed him that the he had failed to submit the Debarment
Certification with the Bid and that the issue had been referred to the District's legal counsel. Mr.
Jurin indicated that this was an oversight on his part and he delivered the signed certification to
the District at about 3:00 PM.
Richard Hinrichs of Department of Health Services responded that the issue in question was up
the District, and that DHS would not object to dismissal of the apparent low bid if that was the
opinion of District legal counsel. A copy of his response is attached.
In consultation with Steve Gross, it has been determined that Jurin Construction did not gain a
material advantage by failing to submit the Debarment Certification with the Bid, but instead
submitting it four hours late. Therefore, the late submittal of the Debarment Certification can be
considered a minor irregularity.
The following statement is given in the Bid Documents and applies to minor irregularities:
"The DISTRICT reserves the right to reject any and all bids and/or waive any irregularities or
informalities in the bidding."
Based upon this statement, and the opinion of District legal counsel, the issue of late submittal
of the Debarment Certification can be waived and Bid by Jurin Construction can be considered
responsive.
4. Recommendation:
Award the Donner Lake Pipelines-2004 project, as modified by three Addenda prior to the Bid
Opening, to Jurin Construction, in the amount of$1,211,964.00.
Attachments:
Debarment Certification
Response from Richard Hinrichs
i
.......................
SECTION 00350 — CERTIFICATION REGARDING DEBARMENT, SUSPENSION
AND OTHER RESPONSIBILITY MATTERS
The Bidder certifies to the best of its knowledge and belief that it, and its principals:
(1) Are not presently debarred, suspended, proposed for debarment, declared ineligible,
or voluntarily excluded from covered transactions by any Federal department or
agency;
(2) Are not presently debarred, suspended, proposed for debarment, declared ineligible
or voluntarily excluded from covered transactions by any State or local government
entity;
(3) Have not within a three year period preceding this proposal been convicted of or had
a civil judgment rendered against them for commission of fraud or a criminal offense
in connection with obtaining attempting to obtain or performing a public (Federal,
State, or local) transaction �r contract under a public transaction; violation of Federal
or State antitrust statutes or commission of embez
zlement, theft, forgery, bribery,
falsification or destruction of records, making false statements, or receiving stol
en
len
(4) Are not Presently indicted for or otherwise criminally or civilly charged by a
government entity (Federal. State, or local) with commission of any of the offenses
enumerated in paragraph (1) or (2) of this certification; and
(5) Have not within a three-year period preceding this application/proposal had one or
more public transactions (Federal, State, or local) terminated for cause or default.
I understand that a false statement on this certification may be grounds for rejection of this
proposal or termination of the award.
I i
`VC)A � �u N V\ 4,
Typed Nam
e & Title of Authorized Representative
4Sigat6ur—eof Author' d Representative Date
I am unable to certify to the above statements. My explanation is attached.
END OF SECTION -
TRUCKEE DONNER PUD
DONNER LAKE PIPELINES—2004 DEBARMENT CERTIFICATION
PAGE 00350-1
Neil Kaufman
From: Hinrichs, Richard (DHS-DDWEM) [RHinrich@dhs.ca.gov]
Sturm, Gunther(DHS-DDWEM)
Bid Opening Issue
Neil Kaufman ufropnD called to discuss n bid opening issue. The o
' opening ^^"" ' bidders. Apparent lowbidd »ouer Labe Pipeline bid
�i bidder at about l��3 million. The second
»«ao a� about 1.2I million and the second l
but the
apparent t low
and third bidders submitted a federal d b »w
!! 'zemai u reu «n bidder did not submit this fo e aomeo�
certification form,
o oeot�al regarding tbi zm� z called Nadine
who said we should
must be Pr»Pezlv completed and provided t « matter, but make i� clear �ba� the f
District wereeze �u dinmiuo the bid for ca » the District prior to bid award. If the form
us as non-responsive based on their legal
interpretation of their bid documents, we would not have a problem with �b award to the
aer»ud low bidder at the 1.33 milli-on.
�
Richard L� Hinrichs, P.E.
Associate Sauitazy Engineer
ebvue 530-224-4867
Fax No. 530-224-3270
1
Ca€forrda o a
r } t W, ,4, 00-1
." is 1 rryfr. ' 0 q 3F
r Nil
- .
License Detail ` '
CALIFORNIA CONTRACTOR$ STATE_LBCEN$E BOARD
Contractor License # 738369
DISCLAIMER
A license status check provides information taken from the CSLB license data base. Before relyi]nn
this information, you should be aware of the following limitations:
• CSLB complaint disclosure is restricted by law (B&P 71246). If this entity is subject to pub
complaint disclosure, a link for complaint disclosure will appear below. Click on the link or to obtain complaint and/or legal action information.
• Per B&P 7071.17, only construction related civil judgments known to the CSLB are disclos• Arbitrations are not listed unless the contractor fails to comply with the terms of the arbitrati
• Due to workload, there may be relevant information that has not yet been entered onto the
Board's license data base.
Extract Date: 05/14/2004
* * * Business Information
JURIN CONSTRUCTION INC
P O BOX 1434
WILLOW CREEK, CA 95573
Business Phone Number: (530) 629-4534
Entity: Corporation
Issue Date: 07/23/1997 Expire Date: 07/31/2005
* * * License Status * * *
This license is current and active. All information below should be reviewed.
* * * Classifications
Eii;L ENGINEERING CONTRACTOR
* * * Bonding Information
CONTRACTOR'S BOND: This license filed Contractor's Bond number 149821 in the amount of
$10,000 with the bonding company
AMERICAN CONTRACTORS INDEMNITY COMPANY. j
Effective Date: 01/01/2004
Contractor's Bonding History
f
BOND OF QUALIFYING INDIVIDUAL(1): The Responsible Managing Officer (RMO) RONALD RAY
JURIN certified that he/she owns 10 percent or more of the voting stock/equity of the corporation. A
bond of qualifying individual is not required.
Effective Date: 07/23/1997
* * * Workers Compensation Information
This license has workers compensation insurance with the
STATE COMPENSATION INSURANCE FUND
Policy Number: 690-0000152 Effective Date: 08/14/1999 Expire Date: 10/01/2004
Workers Compensation History
Personnel listed on this license (current or disassociated) are listed on other licenses.
Personnel List Other Licenses
License Number Request Contractor Name Request Personnel Name..Request
Salesperson Request Salesperson Name Request
2003 State of California Conditions of Use Privacy_Policy
Y
t
5S
3
'x
°L
}
z
i
f
Agenda Item #
i
Memorandum
To: Board of Directors
From: Neil Kaufman
Date: May 14, 2004
Subject: Bid Award for the Donner Lake Pipelines - 2004 Project
1. Why this matter is before the board:
Board Authorization is required to award a contract for construction
2. History:
The Board previously authorized staff to advertise for construction of the Donner Lake Pipelines -
2004 project.
3. New information:
On May 13, Bids were received and opened for this project. Staff has totaled and reviewed all bids.
Three Addenda were issued for this project covering the following issues:
• Addition of conduits, vaults and pull boxes to create a joint trench in part of the project.
• Addition of an additional 1,063 feet of pipeline alignment into the project.
• Issuance of the project Stormwater Pollution Prevention Plan
A summary of the Bids is given below:
Bidder Location Amount
Jurin Construction Willow Creek, CA $1,211,964.00
Hansen Brothers Grass VaIIe , CA $1,310,366.00
Burdick Excavatin Kin s Beach, CA $1,753,377.00
A minor irregularity was identified with the Bid submitted by Jurin Construction. This issue has
been referred to District legal counsel.
4. Recommendation:
I am not prepared to make a recommendation at the time or preparation of this memorandum,
pending advice of District legal counsel. This issue should be resolved by the time of the Board
meeting and a recommendation for award will be made at that time.
Attachments:
Bid Summary Table
F
}
{
DONNER LAKE PIPELINES-2004
BID TABULATION
BIDS OPENED AT 11:00 AM ON THURSDAY,MAY 13,2004
Junin Construction Hansen Bros. Burdick Excavatin
Bid Item Description Quantity Units Unit Price Subtotal Unit Pt Subtotal Unit Price Subtotal
1 Mobilization 1 LS $20,000.00 $ 20,000.00 $ 7,608-00 $ 7E0800 $ 47000.00 $ 47,000.00
1A 12"Water Main from Station 0+00 to 0+84 84 FT $ 92.00 $ 7,728.00 $ 76.75 $ 6,447.00 $ 120.00 $ 10,080.00
IS 12"Water Main,6'Conduit,4'Conduft and 2"Condu t from Station 0+84 to 3+61 277 FT $ 96.00 $ 26,692.00 $ 99.00 $ 27,423.00 $ 88,00 $ 24,376.00
1 C 12"HDPE Water Main,6"Conduit,4"Conduit and 2"Contluit from Station 3+61 to 4+01 40 FT $ 120.00 $ 4,800.00 $ 118.00 $ 4,720.00 $ 93.00 $ 3,720.00
ID 12"Water Main,6"Contluft,4"Conduit and 2"Contluit from Station 4+01 to 23+39,06 1,938 FT $ 90.00 $ 174,420.00 $ 101.50 $ 196.70ZA0 $ 90.00 $ 174,420.00
1 E 1.5"PE Water Service Lateral 680 FT $ 30.00 $ 20,400.00 $ 63.00 $ 42,840.00 $ 64.00 $ 43,520.00
I 2"PE Water Service Lateral 120 FT $ 32.00 $ 3,840.00 $ 47.00 $ 5,640.00 $ 95.00 $ 11,400.00
1 G Two 1"PE Water Service Laterals in Common Trench 100 FT $ 31.00 $ 3,100.00 $ 53.00 $ 5,300.00 $ 44.00 $ 4,400BO
1 H 6"Conduit,4"Conduit and 2"Conduits in Common Trench 85 FT $ 61.00 $ 5,185.00 $ 63.00 $ 5,355.00 $ 52.00 $ 4,420.00
11 IS'PE Water Lateral,2O"Conduits and 2-2"Conduits at Station 8+95,Offset Right 30 FT $ 55.00 $ 1,650.00 $ 68.50 $ 2,055+00 $ 140.00 $ 4,200.00
1J Double Water Service for Non-Traffic Areas 7 EA $ 2,500.00 $ 17,500+00 $ 3,118.00 $ 21,826.00 $ 2,900+00 $ 20,300.00
1K Double Water Service for Traffic Areas 3 EA $ 3,500.00 $ 10,500+00 $ 3,152,00 $ 9,456.00 $ 3,307.00 $ 9.921.00
1L Single Water Service for Non-Traffic Areas 4 EA $ 2,000.00 $ 8,000.00 $ 2,140.00 $ 8,560.00 $ 1,825.00 $ 7,300.00
1M Single Water Service for Traffic Areas 3 EA $ 2,200.00 $ 6,600.00 $ 2,344+00 $ 7,032.00 $ 2.500.00 $ 7,500.00
1N 1"Commercial Water Service For Traffic Areas t EA $ 2,000.00 $ 2,000.00 $ 2,140.00 S 2,140.00 $ 3,000.00 $ 3.000.00
10 Fire Hydrant Assemblies 4 EA $ 3,500.00 $ 14,000.00 $ 5A21K00 $ 20,112.00 $ 6.200.00 $ 24,800.00
1P Pressure Reducing Station at Summit Drive and Donner Pass Road 1 LS $15,500.00 $ 15,500.00 $29.736.00 $ 29.736.00 $ 30000,00 $ 30,000.00
10 Tee and Valve Assembly at Station 4+01 1 LS $ 5,500.00 $ 5,500.00 $ 3.165+00 $ 3,165.00 $ 12,500.00 $ 12.500.00
1 R Communications Pull Box and Electrical Vault at Station 4+06,Offset Right 1 EA $10,000.00 $ 10,000.00 $11,"4.00 $ 11,4,PtB0 $ 11,000.00 $ 11,000.00
1S Communications Pull Box and Electrical Vauft at Station 7+25,Offset Left 1 EA $10,000AO $ 10,000.00 $11,444.00 $ 11,444,00 $ 11,000.00 $ 11,000.00
1T Communications Pull Box at Station 8+95,Offset Right 1 EA $ 4.500.00 $ 4.500.00 $ 2,054.00 $ 2,054,00 $ 5.200.00 $ 5,200.00
1U 12"Butterfly Valve Assembly 1 EA $ 1,500.00 $ 1,500.00 $ 3,054.00 $ 3,054.00 $ 4,500,00 $ 4,500.00
IV Connection to Existing 12"Piping at Station 0+00 1 LS $ 5,000.00 $ 5.000+00 $ 2,544.00 $ 2,544.00 $ 2,800.00 $ 2,800.00
1 W Connection to Existing 8"Piping at Summit Drive and Donner Pass Road 1 LS $ 5,000.00 $ 5,000,00 $ 4,114.00 $ 4,114.00 $ 2.500.00 $ 2,500.00
1X Connection to Existing 18"Piping at Station 23+39.06 1 LS $ 7,500.00 $ 7,500.00 $ 4,263+00 $ 4,263+00 $ 9,800.00 $ 91800.00
1Y AC Trench Restoration 12,000 SOFT $ 4.60 $ 54,000.00 $ 5.18 $ 62,160+00 $ 7.25 $ 87,000.00
1Z AC Lane Restoration 23,000 SO FT $ 2.00 $ 46,000.00 $ 1.16 $ 26,680.00 $ 2.00 $ 46,000+00
1 AA All Other Work Required by the Contract Documents 1 LS $15,000.00 $ 15,000+00 $35.800.00 $ 35.800.00 $111,000.00 $ 111,000.00
2A 2-6"Conduits&1-2"Conduit from Station 0+00 to 0+41 41 FT $ 60.00 $ 2,460.00 $ 65.00 $ 2,665.00 $ 100.00 $ 4,100+00
2B 12"Water Main,2-6"Conduits&i-2"Conduft from Station 0+41 to 6+00 559 FT $ 90,00 $ 50,310.00 $ 103.00 $ 57,577.00 $ 105.00 $ 58,695.00
2C 12"Water Main,1-6"Contluft,2-4"Conduits&t-2"Conduit from Station 6+00 to 8+a5 285 FT $ 150.00 $ 42,750.00 $ 107.00 $ 30,495.00 $ 114.00 $ 32,490.00
2D 12"Water Main,1.6"Conduit,1 A'Conduft&1-2"Conduit from Station 8+85 to 9+65 80 FT $ 95.00 $ 7,600.00 $ 116.00 $ 9,280.00 $ 227.00 $ 18,160.00
2E 12"Water Main,1-6"Conduit,1.3"Conduit,&4-2'Condufts from Station 9+65 to 13+50 385 FT $ 94.50 $ 36,382+50 $ 92.00 $ 35,420.00 $ 118.00 $ 45,430.00
2F 12"Water Main,1.6"Conduft,&1-2"Contluit from Station 13+50 to 27+67 1,417 FT $ 94.50 $ 133,906.50 $ 80.00 $ 113,360.00 $ 126.00 $ 178,542.00
2G 12"Water Main&1-2"Contluft from Station 27+67 to 28+44 77 FT $ 90,00 $ 6,930.00 $ 89.00 $ 6,853,00 $ 185A0 $ 14.245.00
2H 12"Water Main tram Station 28+44 to 28+60 16 FT $ 60,00 $ 960.00 $ 82.00 $ 1,312.00 $ 590.00 $ 9,440.00
21 1-6"Conduit at Station 27+67 Offset Left 23 FT $ 60,00 $ 1.380.00 $ 63.00 $ 1,449.00 $ 245.00 $ 5,635.00
2J IS'PE Service Lateral 240 FT $ 40.00 $ 9,600.00 $ 55.00 $ 13,200.00 $ 64.00 $ 15,3%00
2K Double Water Service for Non-Traffic Areas 4 EA $ 2,500.00 $ 10,000.00 $ 3,186+00 $ 12,744+00 $ 3,390.00 Is 13,560.00
21 Double Water Service for Traffic Areas 1 EA $ 3500.00 $ 3,500.00 $ 3,629,00 $ 3S29,00 $ 3,500.00 $ 31500A0
2M Single Water Service for Non-Traffic Areas i EA $ 2.000.00 $ 2,000.00 $ 2,072A0 $ 2,072+00 $ 2,000.00 $ 2,000,00
2N File Hydrant Assemblies 2 EA $ 3,500.00 $ 7,000.00 $ 5.023.00 $ 10,046.00 $ 6,200.00 $ 12,400.00
20 Connection to 12"Pipe by Others at Station 0+41 1 LS $ 11000.00 $ 1,000.00 $ 2,544.00 $ 2,54400 $ 3,500.00 $ 3,500.00
2P Connection to Existing 12"Piping at Station 28+64,47 1 LS $ 4,500.00 S 4,500.00 $ 5,490.00 $ 5,490.00 $ 3,889.00 $ 3.889.00
20 Tee and Valve Assembly at Station 16+72 1 LS $ 5,500.00 $ 5.500.00 $ 1 S29.00 $ 1,829.00 $ 8,650.00 $ 8.650.00
2R Electrical Vaults 4 EA $ 7,000.00 $ 28,000.00 $ 9,206.00 $ 36,824.00 $ 8.500+00 $ 34,000.00
2S Communications Pull Boxes 4 EA $ 3,800.00 $ 15,200,00 $ 2,054.00 $ 8,216,00 $ 4,400.00 $ 17,600.00
Junin ConstructionI Hansen Bros. Burdick Excavatin
Bid Item Description Quantity Units Unit Price Subtotal Unit Price I Subtotal Unit Price Subtotal
2T 6"Riser at Station 27+67,Offset Leff 1 LS $ 2.000.00 $ 2,000.00 $ 464.00 $ 464.00 $ 1,200.00 $ 1,200.00
2U Temporary 4"Water Pipe 1 LS $10,000.00 $ 10,000,00 $15,751,00 $ 15,751.00 $ 18,750.00 $ 18,750.00
2V Cut-Off Walls 1 EA $ 11500.00 $ 1,600.00 $ 694.00 $ 694.00 $ 1,800.00 $ 1,800.00
2W Tree Removal 20 PER TREE $ 400.00 $ 8,000.00 $ 523.00 $ 10,460.00 $ 486.00 $ 9,700.00
2X AC Trench Restoration 3,500 SO FT $ 6.00 $ 21,000.00 $ 5,21 $ 18,236.00 $ 9.00 $ 31,500,00
2Y AN Other Work Required by the Contract Documents 1 LS $15,000.00 $ 15,000.00 $40,002A0 $ 40,002.00 $ 45,000.00 $ 45,000.00
3A 1.6"Conduit&2-2"Conduits from Station 0+00 to 0+23 23 FT $ 60.00 $ 1,380.00 $ 65.00 $ 1,495.00 $ 220.00 $ 5,060.00
3B 12'Water Main,1-6"Conduct&1-2'Conduit from Station 0+40 to 3+51 All 312 FT $ 90.00 $ 28,080-00 $ 94.00 $ 29,328.00 $ 132,00 $ 41.184.00
3C Correction to Existing 12"Piping at Station 3+51,48 1 LS $ 800.00 $ 800.00 $ 4,263.00 $ 4.263.00 $ 3,000,00 $ 31000.00
3D Flow Control Station 1 LS $ 9,000.00 $ 9,000,00 $16.733.00 $ 16.733.00 $ 28,000.00 $ 28,000.00
3E Electrical Pull Box 1 EA $ 31500.00 $ 3.500.00 $ 9,206.00 $ 91206.00 $ 61600,00 $ 6.600.00
3F 6-inch and 2-inch Risers at Station 0+00 1 EA $ 1,800.00 $ 1,800M $ 490.00 $ 490.00 $ 3,600,00 $ 3,600.00
3G Cut-Off Wells 3 EA $ 1.501 $ 4,500.00 $ 694.00 $ 2,082.00 $ 1.800.00 $ 5,400.00
3H AC Trench Restoration 120 SO FT $ 8A0 $ 960.00 $ 5.20 $ 624.00 $ 20.00 $ 2.400.00
31 All Other Work Required by the Contract Documents 1 LS $ 5.000.00 $ 6,000.00 $ 1,074M $ 1,074.00 $ 4,375,00 $ 4,375.00
4A 8'HOPE Water Main from Station 0+00 to 0+28 and at Station 8+20 Offset Left 49 FT $ 60.00 $ 2.940.00 $ 76.00 $ 3,724.00 It 170.00 $ fL330,00
48 8"Water Main from Station 0+28 to 10+63.35 1,036 FT $ 75.00 $ T,700.00 $ 6&00 $ 70,448+00 $ 82.00 $ 84,952.00
4C t"PE Water Service Lateral 80 FT $ 40.00 $ 3,200.00 $ 54.50 $ 4,360+00 $ 60M $ 4,800.00
40 1.5"PE Water Service Lateral 400 FT $ 40.00 $ 16,000.00 $ 51.00 $ 20,400.00 $ 64.00 $ 25,600.00
4E 2'PE Water Service Latemi 150 FT $ 40,00 $ 61000,00 $ 50.00 $ 7,500.00 $ 75.00 $ 11,250.00
4F Double Water Service for Non-Traffic Areas 5 EA $ 3,500.00 $ 17,500.00 $ 3,101.00 $ 15,505.00 $ 3,200,00 $ 16,000.00
4G Double Water Service for Traffic Areas 1 EA $ 3,500.00 $ 3,500.00 $ 3,696.00 $ 3,696.00 $ 3,325.00 $ 3,325.00
4H Single Water Service for Non-Traffic Areas 3 EA $ 2,500.00 $ 7,500+00 $ 2,140.00 $ 6,420.00 $ 1,825.00 $ 5,475.00
41 Single Water Service for Traffic Areas 2 EA $ 2,500.00 $ 5,000.00 $ 2,480.00 $ 4,960.00 $ 2,500.00 $ 5,000.00
ad 1"Commercial Water Service For Traffic Areas 3 EA $ 2,000.00 $ 6,000.00 $ 2,344.00 $ 7,032.00 $ 3,000.00 $ 9,000.00
4K Tee and Valve Assembly at Station 0+28 1 LS $ 2.000.00 $ 2,000.00 $ 1,902.00 $ 1,902.00 $ 2,222.00 $ 2,222,00
4L Tee,Vahie and Fire Hydrant Assembly at Station 0+28,Offset Right 1 LS $ 3,500,00 $ 3,500.00 $ 5,067.00 $ 5,067+00 $ 243.00 $ 243.00
4M 8"Water Main at Station 0+28,Offset Right 30 FT $ 75.00 $ 2,250.00 $ 60.00 $ 1,800.00 $ 170.00 $ 5,100.00
4N Cross and Valve Assembly at Station 8+20 1 LS $ 3,000.00 $ 3,000.00 $ 1,902.00 $ 1,902.00 $ 4,225.00 $ 4.225.00
40 4'Water Main at Station 8+20,Offset Right 36 FT $ 60.00 $ 2,160.00 $ 60.00 $ 2,160.00 $ 158.00 $ 5.688.00
4P Connection to Existing 8"Piping at Station 0+00 1 LS $ 1,200.00 $ 1,200.00 $ 2,657,00 $ 2,657.00 $ 3,000.00 $ 3,000.00
4Q Connection to Existing 8'Piping at Station 8+20,Offset Leff 1 LS $ 1,00000 $ 1.000M $ 3,738.00 $ 3,738.00 $ 3,000.00 $ 3,000.00
4R AC Trench Restoration 6,600 SO FT $ 4.00 $ 26,400.00 $ 5.21 $ 34,386.00 $ 7.20 $ 47,520.00
4S AC Lane Restoration 13,900 SO FT $ 2.00 $ 27,800.00 $ 1.16 $ 16,124+00 $ 2.75 $ 38,225.00
4T All Other Work Required by the Contract Documents 1 $21.000.00 000 48,00000 $ 48.0000
,00 3 ,360$1,21196 $ 2060 $
$1,753,377+00
DONNER LAKE PIPELINES•2004
BID TABULATION
BIDS OPENED AT 11:00 AM ON THURSDAY,MAY 13,2004
Jurin Construction Hansen Bros. Burdick Excavatin
Bid Item Description Quantity Units Unit Price Subtotal Unit Price Subtotal Unit Price Subtotal
1 Mobilization 1 LS $20,000di) $ 20,000,00 $ 7,608.00 $ 7,608.00 $ 47,000.00 $ 47,000.00
to 12"Water Main from Station 0+00 to 0+84 84 FT $ 92.00 $ 7,728 00 $ 76,75 $ 6,447.00 $ 120,00 $ 10,080.00
18 12"Water Main,6"Conduit,4"Conduit and 2"Conduit from Station 0+84 to 3+61 277 FT $ 96,00 S 26,592,00 $ 99.00 $ 27,423.00 S 88,00 $ 24,376.00
1C 12'HOPE Water Main,6"Conduit,4"Conduit and 2"Conduit from Station 3+61 to 4+01 40 FT $ 120,00 S 4,800,00 $ 118,00 $ 4,720,00 $ 93.00 $ 3,720.00
ID 12"Water Main,6"Conduit,4"Conduit and 2"Conduit from Station 4+01 to 23+39,06 1,938 FT $ 90.00 It 174,420.00 $ 101.50 $ 196,707.00 $ 90,00 $ 174,420.00
1 E 15'PE Water Service Lateral 680 FT S 30.00 $ 20,400,00 S 63.00 $ 42,840.00 $ 64,00 $ 43,520,00
IF 2"PE Water Service Lateral 120 FT $ 32,00 $ 3,84L00 $ 47,00 $ 5,640,00 $ 95-00 $ 11,400.00
1G Two I"PE Water Service Laterals in Common Trench 100 FT $ 31.00 $ 3,100,00 S 53,00 $ 5,300,00 $ 44.00 $ 4,400,00
1H 6"Conduit,4"Conduit and 2"Conduits m Common Trench 85 FT $ 61.00 $ 5,185.00 $ 63.00 $ 5,355.00 $ 52.00 $ 4,420,00
it 1.5"PE Water Lateral,2-4"Conduits and 2-2"Conduits at Station 8+95,Offset Right 30 FT $ 55.00 $ 1,650.00 $ 68.50 $ 1,055.00 $ 140.00 $ 4,200,00
1J Double Water Service for NonJi-affic Areas 7 EA $ 2,500.00 $ 17,500.00 $ 3,118.00 $ 21,826,00 $ 2,900.00 $ 20,300,00
1K Double Water Service for Traffic Areas 3 EA S 3,500.00 $ 10,500.00 $ 3,152.00 $ 9,456.00 $ 3,307.00 $ 9,921.00
1L Single Water Service for Non,TraffIn Areas 4 EA $ 2,000.00 $ 8,000.00 $ 2,140.00 $ 8,560.00 $ 1,825.00 $ 7,300.00
1M Single Water Service for Traffic Areas 3 EA $ 2,200.00 $ 6,600.00 $ 2,344.00 $ 7,032,00 $ 2,500,00 $ 7,500.00
1N i"Commercial Water Service For Traffic Areas 1 EA $ 2,000.00 $ 2,000.00 IS 2,140.00 $ 2,140,00 $ 3,000.00 $ 3,000.00
10 Fire Hydrant Assemblies 4 EA $ 3,500.00 $ 14,000.00 $ 5,028.00 $ 20,112.00 $ 6,200.00 $ 24,80000
1P Pressure Reducing Station at Summit Drive and Donner Pass Road 1 LS $15.500,00 $ 15,500,00 $29,736.00 $ 29,736.00 $ 30,000,00 $ 30,000,00
10 Tee and Valve Assembly at Station 4+01 1 LS $ 5,500,00 $ 5,500.00 $ 3,165,00 $ 3,165.00 $ 12,500,00 $ 12500,00
1 R Communications Pull Be.and Electrical Vault at Station 4+06,Offset Right i EA $10,000.00 $ 10,000E0 $11,444,00 $ 11,444,00 $ 11,000,00 $ 11,000,00
IS Communications Pull Box and Electrical Vault at Station 7+25,Offset Left 1 EA S 10,000.00 $ 10,000.00 $11,444.00 $ 11,444.00 $ 11 p00.00 $ 11,000.00
I Communications Pull Box at Station 8+95,Offset Right 1 EA $ 4,500,00 $ 4,500.00 $ 2,054,00 $ 2,054_00 $ 5,200,00 $ 5,200,00
1U 12"Sordidly Valve Assembly 1 EA $ 1,500.00 $ 1T500.00 $ 3,054,00 $ ',05400 $ 4,500.00 $ 4,500.00
1V Connection to Existing 12"Piping at Station 0+00 1 LS S 5,000.170 $ 5,000.00 $ 2,544,00 $ 2,544.00 $ 2,800,00 $ 2,800,00
1 W Connection to Existing 8"Piping at Summit Drive and Donner Pass Road 1 LS $ 5,000.00 $ 5,000.00 $ T114.00 $ 4,114.00 $ 2,500,00 $ 2,500,00
1X Connection to Existing 18"Piping at Station 23+39,06 1 LS $ 7,500.00 $ 7,500.00 $ 4,263.00 $ 4,263.00 $ 9,80E00 $ 9,800,00
1 Y AC Trench Restoration 12,000 SO FT $ 4,50 $ 54,000.00 $ 5.18 $ 62,160.00 $ 7,25 $ 87,000.00
1Z AC Lane Restoration 23,000 50 FT $ 2.00 $ 46,000.00 S 1,16 $ 26,680.00 S 2D) $ 46,000,00
1AA All Other Work Required by the Contract Documents 1 LS $15,000,00 $ 15,000-00 $35,800.00 $ 35,800.00 $111,000,00 $ 111,000.00
2A 2-6"Conduits&1-2"Conduit from Station 0+00 to 0+41 41 FT $ 60.00 $ 2,460.00 $ 6SL0 $ 2465.00 $ 100.00 $ 4,100.00
2B 12"Water Main,2-6"Conduits&1-2"Conduit from Station 0+41 to 6+00 559 FT $ boos $ 50,310.00 $ 103,00 $ 57,577.00 $ 105,00 $ 58,695.00
2C 12"Water Main,1-6"Conduit,24"ConduHs&1-2"Conduit from Station 6+00 to 8+85 285 FT $ 15000 $ 42,750.00 $ 10T00 $ 30,495.00 $ 114.00 $ 32,490.00
2D 12"Water Main,1.6"Conduit,1-4"Conduit&1-2"Conduit from Station 8+85 to 9+65 8o FT $ 950o S 7,600.00 $ 116,00 $ 9,280,00 $ 227.00 $ 18,160.00
2E 12"Water Main,1.6"Conduit,13"Conduit,&4-2"Conduits from Station 9+65 to 13+50 385 FT $ 94.50 $ 36,382,50 $ 92.00 $ 35,420.00 $ 118,00 $ 45,430.00
2F 12"Water Main,1.6"Conduit,&1-2"Conduit from Station 13+50 to 27+67 1,417 FT $ 94,50 $ 133,906,50 $ 8000 $ 113,36000 $ 126,00 S 178,542.00
2G 12"Water Main&1.2"Conduit from Station 27+67 to 28+44 77 FT $ 90.00 $ 6,930.00 a 89,00 $ 6,853,00 $ 185,00 $ 14,245.00
2H 12"Water Main from Station 28+44 to 28+60 16 FT $ 60.00 $ 960.00 $ 82.00 S 1,312,00 $ 590,00 $ 9,440.00
21 1-6"Conduit at Station 27+67 Offset Left 23 FT $ 60,00 $ 1,380,00 $ 63.00 $ 1,449,00 $ 245.00 $ 5,635.00
2J 1.5"PE Service Lateral 240 FT $ 40,00 $ 9,600.00 $ 55,00 $ 13,200,00 $ 64,00 $ 15,360.00
2K Double Water Service for Non-Traffic Areas 4 EA $ 2,500.00 $ 10.000.00 $ 3,186.00 $ 12.744,00 $ 3,39(100 $ 13,560.00
2L Double Water Service for Traffic Areas 1 EA $ 31500.00 $ 3,500,00 $ 3,629.00 $ 3,629,00 $ 3,500.00 $ 3,500.00
2M Single Water Service for Non-Traffic Areas 1 EA $ 2,000.00 $ 2,000.00 $ 2,072.00 It 4072.00 $ 2,000.00 $ 2,000.00
2N Fire Hydrant Assemblies 2 EA $ 3,500.00 $ 7,000.00 $ 5,023,00 $ 10,046,00 $ 6.200,00 $ 12,400,00
20 Connection to 12"Pipe by Others at Station 0+41 1 LS $ 1,000.00 $ 1,000.00 $ 2,544.00 $ 2,544.00 $ 3,500.00 $ 3,500.00
2P Connection to Existing 12"Piping at Station 28+64,47 1 ITS $ 4,500,00 $ 4,500,00 $ 5,490,00 $ 5,490.00 $ 3,889.00 $ 3,889.00
20 Tee and Valve Assembly at Station 16+72 1 LS $ 5,500.00 $ 5,500,00 $ 1,829,00 $ 1,829,00 It 8,650.00 $ 8,6%00
2R Electrical Vaults 4 EA $ 7,000D) $ 28,000.00 $ 9,206.00 $ 36,824.00 $ 8,500.00 $ 34,000,00
2S Communications Pull Boxes 4 EA $ 3TS00.00 $ 15,200.00 $ 2,054,00 $ 8.216.00 $ 4,400,00 $ 17,600,00
Jurin Construction Hansen Bros. Burdick Excavatin
Bid Item Description Quantity Units Unit Price Subtotal Unit Price Subtotal Unit Price Subtotal
2T 6"Riser at Station 27167,Offset Left i LS $ 2,000,00 $ 2,000.00 $ 464,00 S 464.00 $ 1,200,00 § 1,200.00
2U Temporary 4"Water Pipe 1 LS $10,000.00 $ 10,000.00 $15,751,00 $ 15,751.00 $ 18,750.00 $ 18,75000
2V Out-Off Walls 1 EA $ 1,50000 $ 1,500.00 $ 694,00 $ 69400 $ 1,800.00 $ 1.800,00
2W Tree Removal 20 PERTREE $ 400.00 $ 8,000,00 $ 52300 $ 10,460,00 $ 485.00 $ 9,700,00
2X AC Trench Restoration 3,500 SO FT $ 600 $ 21,000.00 $ 5,21 $ 12,235,00 $ 9,00 $ 31,500.00
2Y All Other Work Required by the Contract Documents 1 LS $15,000.00 $ 15,000.00 $40,002.00 $ 40,002,00 $ 45,000.00 $ 45,000,00
3A 1-6"Conduit&2-2"Conduits from Station 0+00 to 0+23 23 FT $ 60,00 $ 1,380,00 $ 65.00 $ 1,495.00 $ 220.00 $ 5,060.00
36 12"Water Main,i-6"Conduit&1-2"Conduit from Station 0+40 to 3+51.48 312 FT $ 90.00 $ 28,080.00 $ 94,00 $ 29,328.00 $ 132,00 $ 41,184.00
3C Connection to Existing 12"Piping at Station 3+51 A8 1 LS $ 800,00 $ 800.00 $ 4,263.00 $ 4,263.00 $ 3,000,00 $ 3,000.00
3D Flow Control Station 1 LS $ 9,000.00 $ 9,000.00 $16,733.00 $ 16,733.00 $ 28,000,00 $ 28,000.00
3E Electrical Pull Box i EA $ 3,500.00 $ 3,500.00 $ 9,206,00 $ 9,206,00 $ 6,600.00 S 6,600.00
3F 6-inch and 2-inch Risers at Station 0+00 1 EA $ 1,800.00 $ 1,800.00 $ 490.00 $ 490,00 $ 3,600.00 S 3,600,00
3G Cut-Off Walls 3 EA $ 1,500,00 $ 4,500.00 $ 694,00 $ 2,082.00 $ 1,800.00 $ 5.400,00
3H AC Trench Restoration 120 SO FT $ 8,00 $ 960.00 $ 5.20 $ 62400 $ 20.00 $ 2,400,00
31 All Other Work Required by the Contract Documents 1 LS $ 5,000.00 $ 5,000.00 $ 1,074.00 $ 1,074.00 $ 4,375.00 $ 4,375.00
4A 8"HOPE Water Main from Station 0+00 to 0+28 and at Station 8+20 Offset Left 49 FT $ 60,00 $ 2,940.00 $ 76.00 $ 3,724,00 $ 170.00 $ 8,330,00
46 8"Water Main from Station 0+28 to 10+63.35 1,036 FT $ 75,00 S 77,700.00 $ 68.00 $ 70,448,00 $ 82,00 $ 84,952.00
4C 1"PE Water Service Lateral 80 FT $ 40,00 $ 3,200.00 8 54.50 $ 4,36000 $ 60.00 $ 4,800.00
4D 16"PE Water Service Lateral 400 FT $ 40.00 $ 16,000.00 $ 51.00 $ 20,400,00 $ 64.00 $ 25,600,00
4E 2"PE Water Service Lateral 150 FT $ 40.00 $ 6,000,00 $ 50.00 $ 7,500.00 $ 75.00 $ 11,250.00
4F Double Water Service for Non-Traffic Areas 5 EA $ 3,500.00 $ 17,500.00 $ 3,101 ED $ 15,505.00 $ 3,200,00 $ 16,000.00
4G Double Water Service for Traffic Areas 1 EA $ 3,500.00 $ 3,500.00 $ 3,696.00 $ 3,696.00 $ 3,325.00 $ 3.325,00
4H Single Water Service for Non-Traffic Areas 3 EA $ 2,500.00 $ 7,500.00 $ 2,140.00 $ 6,420.00 $ 1,825.00 $ 5,475,00
41 Single Water Service for Traffic Areas 2 EA $ 2,500.00 $ 5,000-00 $ 2,480.00 S 4,960,00 $ 2,500.00 $ 5,000,00
4J 1"Commercial Water Service For Traffic Areas 3 EA $ 2,000,00 $ 6,000.00 $ 2,344.00 $ 7,032.00 § 2,222,00 $ 2,222,00
4K Tee and Valve Assembly at Station 0+28 7 LS $ 2,00000 $ 2,000.00 $ 1,902.00 $ 1,902.00 $ 2,222.00 $ 2,222.00
4L Tee,Valve and Fire Hydrant Assembly at Station 0+28,Offset Right 1 LS $ 3,500.00 $ 3,500.00 $ 5,067.00 $ 5,067,00 $ 243.00 $ 243,00
4M 8"Water Main at Station 0+28,Offset Right 30 FT $ 75.00 $ 2,250.00 $ 60,00 $ 1,800,00 $ 170,00 $ 5,100.00
4N Cross and Valve Assembly at Station 8+20 1 LS $ 3,000.00 $ 3,000.00 $ 1,902.00 $ 1,902.00 $ 4,225.00 $ 4,225.00
40 4"Water Main at Station 8+20,Offset Right 36 FT $ 60.00 $ 2,160.00 $ 60.00 $ 2,160.00 $ 158.00 $ 5,68600
4P Connection to Existing 8"Piping at Station 0+00 1 LS $ 1,200.00 $ 1,200.00 $ 2,657,00 $ 2,657.00 $ 3,000.00 $ 3,000,00
4O Connection to Existing 8"Piping at Station 8+20,Offset Left i LS $ 1,000.00 $ 1,000.00 $ 3,738,00 S 3.738,00 $ 3,000,00 $ 3,000,00
4R AC Trench Restoration 6,600 SO FT $ 4,00 $ 26,400,00 $ 5,21 $ 34,38600 $ 7,20 $ 47,520,00
4S AC Lane Restoration 13,900 SOFT $ 2.00 $ 27,800100 $ 1,16 $ 16,124.00 $ 2,75 $ 38,225.00
4T All Other Work Required by the Contract Documents 1 LS $10,000.00 $ 10.000.00 $21,000.00 $ 21.000.00 $ 48,000.00 $ 48,000.00
$1,211,964.00 $1,310,366.00 $1,753,377,00