HomeMy WebLinkAbout9 Brockway Transmission Pipeline Project Agenda Item #
Nunn i
Memorandum
To: Board of Directors
From: Neil Kaufman
Date: March 30, 2006
Subject: Bid Award for the Brockway Transmission Pipeline Project
1. Why this matter is before the board:
Board Authorization is required for expenditures in excess of$15,000.00.
2. History:
The Board previously authorized staff to advertise for construction of the Brockway Transmission
Pipeline project.
3. New information:
On March 29, Bids were received and opened for this project. Staff has totaled and reviewed all bids.
Two Addenda were issued for this project covering the following issues:
• Issuance of permits from the Town of Truckee, TSD, TTSA, Caltrans and CaIOSHA.
• Clarification of issues regarding traffic control downtown
• Revision to asphalt mix design
A summary of the Bids is given below:
Bidder Location Amount
Vulcan Construction Fresno, CA $2,976,939.00
Loran Brothers Construction Colfax, CA $4,878,744.00
4. Recommendation:
The Board of Directors award the Brockway Transmission Pipeline project to Vulcan
Construction in the amount of 2,976,939.00.
Attachments:
Bid Summary Table
Project Map
i
BROCKWAY TRANSMISSION PIPELINE
BID TABULATION
BIDS OPENED AT 2:00 PM ON WEDNESDAY, MARCH 29, 2006
Bid Item Description Vulcan Construction Loran g Brothers
1 Mobilization Quantity Units Unit Price Subtotal Unit Price Subtotal
2 24"DI Pipe and 2"Conduit from Station 0+00 to 9+50 1 LS $ 70,000.0 0 $ 70,000.00 $175,000.00 $ 175,000.00
FT
3 24"DI Pipe and 2"Conduit from Station 9+50 to 12+75(Alignment A) 950 950 FT $ 234.00 $ 222,300,00 $ 346.00 $ 328,700.00
4 24"DI Pipe and 2"Conduit from Station 12+75 to 16+65 325 390 FT $ 311.00 $ 121,290.00 $ 394.00 $ 153,660.00$ 289.00 $ 93,925.00 $ 487.00 $ 158,275.00
5 24"DI Pipe and Three 2"Conduits from Stations 16+65 to 16+90 and 18+65 to 18+70 30 FT
6 24"DI Pipe and Three 2"Conduits from Station 16+90 to 18+65 inside 36"Steel Casing 30 FT $ 435.00 $ 13,050.00 $ 426.00 $ 35,525.00
7 24"PVC Pipe and Three 2"Conduits from Station 18+70 to 19+46 7 FT $ 148.00 $ 25,900.00 $ 203.00 $ 35,525.00
8 24"PVC Pipe and 2"Conduit from Station 19+46 to 20+25 79 FT
9 24"PVC Pipe from Station 20+25 to 21+83 $ 313.00 $ 24,727.00 $ 500.00 $ 39,500.00
10 24"DI Pipe from Station 21+g3 to 23+54 158 FT $ 265.00 $ 41,870.00 $ 465,00 $ 73,470.00
11 24"DI Pipe from Station 25+72 to 27+75 203 FT $ 225.00 $ 45,675.00 $ 484.00 $ 82:764.00
12 24"DI Pipe and 2"Conduit from Station 27+75 to 41+69 203 FT $ 215.00 $ 99,710.00 $ 430100 $ 98,252.00
13 24"DI Pipe and 2"Conduit from Station 41+69 to 46+60 1,394 FT $ 215.00 $ 299,710.00 $ 307.00 $ 427,958.00
14 24"DI Pipe and 2"Conduit from Station 46+60 to 48+75 491 FT $ 218.00 $ 107,038.00 $ 330.00 $ 162,030.00
15 24"DI Pipe and 2"Conduit from Station 48+75 to 51+75 300 FT $ 242.00 $ 72,600.00 $ 260.00 $ 55,900.00
16 24"DI Pipe and 2"Conduit from Station 51+75 to 54+55 280 FT $ 175.00 $ 49,000.00 $ 320.00 $ 96,000.00
17 24"DI Pipe and 2"Conduit from Station 54+55 to 55+57 280 FT $ 175.00 $ 49,000.DO $ 262.00 $ 73,360.00
18 24"DI Pipe,2"PE pipe and 2"Conduit from Station 55+5710 56+75 102 FT $ 200.00 $ 20,400.00 $ 276.00 $ 28,112.00
19 24"DI Pipe and 2"Conduit from Station 56+75 to 58+15 118 FT $ 210.00 $ 24,780.00 $ 282.00 $ 33,276.00
20 24"DI Pipe and 2"Conduit from Station 58+15 to 65+95 360 FT $ 145.00 $ 52,200.00 $ 373.00 $ 134,280.00
21 24"DI Pipe and 2"Conduit from Station 65+95 to 76+55 780 FT $ 185.00 $ 146,640.00 $ 260.00 $ 202,800.00
22 24"DI Pipe,8"Pipe and 2"Conduit from Station 76+55 to 80+39 1,060 FT $ 207.00 $ 219,420.00 $ 304.00 $ 322:241.00
23 24"DI Pipe and 2"Conduit from Station 80+39 to 82+11 172 FT $ 208.00 $ 135,776.00 $ 357.00 $ 137,088.00
24 24"DI Pipe from Station 82+11 to 97+06 ,49 FT $ 217.00 $ 24,415.00 $ 361.00 $ 62,092.00
25 24"DI Pipe from Station 97+06 to 98+55 1,495 FT $ 217.00 $ 324,415.00 $ 367.00 $ 548,665.00
26 24"DI Pipe from Station 98+55 to 98+95 149 FT $ 215.00 $ 32,035.00 $ 325,00 $ 48,425.00
27 24"DI Pipe from Station 98+95 to 99+00.61 40 FT $ 195.00 $ 7,800.00 $ 360.00 $ 14,400.00
28 36"Steel Casing from Station 16+90 to 18+65 6 FT $ 145.00 $ 870.00 $ 306,00 $ 1,836.00
29 Connection to Existing Piping at Station 0+00 1 LS $330,000.00 $ 330,000.00 $380,200.00 $ 380,200.00
30 Connection to Existing Piping at Station 23+54 1 LS $ 12,850.00 $ 12,850.00 $ 81290,00 $ 8,290.0'
31 Connection to Existing Piping at Station 25+72 1 LS $ 10,900.00 $ 10,900.00 $ 38,380.00 $ 38,381.ou
32 Tee/Valve Assembly at Station 37+47 1 LS $ 10,375.00 $ 10,375.00 $ 40,780.00 $ 4Q780.00
33 Connection to Existing Piping at Station 37+47,Offset Right 1 LS $ 16,900.00 $ 16,900.00 $ 44,875.00 $ 44,875.00
34 TeeNalve Assembly at Station 59+50 1 LS $ 19,350.00 $ 19,350.00 $ 29,530.00 $ 29,530.00
35 Connection to Existing Piping at Station 99+00.61 1 LS $ 17.950.00 $ 17,950,00 $ 37,610.00 $ 37,"0.00
36 24"Butterfly Valve Assembly 1 LS $ 9,725.00 $ 9,725.00 $ 16,362.00 $ 16,362.00
37 Air Valve Assemblies 4 LS $ 4,800,00 $ 19,200.00 $ 20:600.00 $ 82,400.00
38 Blow-Off Assembly at Station 23+56 7 EA $ 3,450.00 $ 24,150,00 $ 7,000,001 $ 49,000.00
39 Blow-Off Assemblies 1 EA $ 1,710.00 $ 1,710.00 $ 8,020.001 $ 8,020.00
40 16"HDPE Pipe Inside Existing 18"Steel Casing 7 EA $ 2,175.00 $ 15,225.00 $ 4,705.00 $ 32,935.00
1 LS $ 51,830.00 $ 51,830.00 $ 86,456.001 $ 86,456.00
BROCKWAY TRANSMISSION PIPELINE
BID TABULATION
BIDS OPENED AT 2:00 PM ON WEDNESDAY, MARCH 29, 2006
Bid Item Description Vulcan Construction Lorang Brothers
Quantity Units Unit Price Subtotal Unit Price Subtotal
42 2"Conduit Trench Outside Pavement
41 2"Conduit Trench Within Pavement 60 FT $ 88.00 $ 5,280.00 $ 14 16 FT $ 68.00 $ 1,088.00 8.00 $ 8,880.00
43 8"Pipe at Station 22+92 $ 48.00 $ 768.00
44 8"Pipe Connections at Station 22+92 48 FT $ 170.00 $ 8,160.00 $ 120.00 $ 5,760.00
45 Furnish and install pull boxes for conduit 1 LS $ 4,225.00 $ 4,225.00 $ 13,920.00 $ 13,920.00
46 AC Lane Restoration 2 EA $ 800.00 $ 1,600.00 $ 2,235.00 $ 4,470.00
47 Perform Rock Excavation 29,000 SO FT $ 2.75 $ 79,750.00 $ 2.70 $ 78,300.00
40 Hours $ 1,000.00 $ 40,000.00 $ 1,200.00 $ 48,000.00
48 All Other Work Required by the Contract Documents 1 LS $ 37,000.00 $ 37,000.00 $310,000.00 $ 310,000.00
49 Credit for District Furnished Equiloment 1 LS $ 9,150.00
( ) $ (9,150.00 $ (10,000.00} $ (10,000.00
3 2,976,939.00 $4,878,744.00
License Detail
Page I of 2
tea= 'ornia Horne
71.
h� Oril€ tO '� : rA#WB
License Detail CALIFORNIA CONTRACTORS STATE LICENSE BOARD
Contractor License # 414892
DISCLAIMER
A license status check provides information taken from the CSLB license data base. BeforJor
on this information, you should be aware of the following limitations:
. CSLB complaint disclosure is restricted by law (B&P 7124.6). If this entity is subject t
complaint disclosure, a link for complaint disclosure will appear below. Click on the lin
button to obtain complaint and/or legal action information.
. Per B&P 7071.17, only construction related civil judgments reported to the CSLB are
disclosed.
. Arbitrations are not listed unless the contractor fails to comply with the terms of the arbitration.
• Due to workload, there may be relevant information that has not yet been entered onto the
Board's license data base.
Extract Date: 03/29/2006
* * * Business Information
VULCAN CONSTRUCTION & MAINTENANCE INC
2610 W SHAW LANE SUITE 103
FRESNO, CA 93711
Business Phone Number: (559) 265-4711
Entity: Corporation
Issue Date: 12/08/1981 Reissue Date: 04/27/1993 Expire Date: 04/30/2007
* * * License Status
This license is current and active. All information below should be reviewed.
* * * Classifications
Class Description
�� GENERAL ENGINEERING CONTRACTOR #
C36 PLUMBING
* * * Bonding Information
CONTRACTOR'S BOND: This license filed Contractor's Bond number SP5507 in the amount of
$10,000 with the bonding company
UNITED STATES FIDELITY AND GUARANTY COMPANY.
Effective Date: 01/01/2004
http://www2.cslb.ca.gov/CSLB_LIBRARY/License+Detail.asp 3/29/2006
License Detail
Page 2 of 2
Contractor's Bonding History
BOND OF QUALIFYING INDIVIDUAL(1): This license filed Bond of Qualifying Individual number
SP5581 for CHRISTIAN GEOFFREY DIETL in the amount of$7,500 with the bonding company
UNITED STATES FIDELITY AND GUARANTY COMPANY.
Effective Date: 06/03/2003
BQI's Bonding History
* * * Workers Compensation Information
This license has workers compensation insurance with the
STATE COMPENSATION INSURANCE FUND
Policy Number: 046-0004341 Effective Date: 01/01/1994 Expire Date: 01/01/2007
Workers Compensation History
Personnel listed on this license (current or disassociated) are listed on other licenses.
Personnel List Other Licenses
License Number.Request Contractor Name.Request Personnel Name Request
Salesperson_Request Salesperson Name Request
2006 State of Calremia Conditions of Use Privacy Policy
i
f
i
t
r
s
attp://www2.cslb.ca.gov/CSLB_LIBRARY/License+Detail.asp 3/29/2006
\ PROJECT START
BRIDGE STREET&INDIAN JACK ROAD t i"
PROJECT END
� / RANCH WAY&SR 267
c Oyu
NOT TO SCALE
TRUCKEE DONNER
Public Utility District Brockway Transmission Pipeline