HomeMy WebLinkAbout12 District Pipeline Closeout Change Order Agenda Item # ic Public Utility Distr t 0-1, Memorandum To: Board of Directors From: Neil Kaufman Date: November 14, 2007 Subject: Final Completion and a Closeout Change Order for the District Pipeline Replacement— 2007— Contract B Project 1. WHY THIS MATTER IS BEFORE THE BOARD The District Pipeline Replacement — 2007 — Contract B project is complete. A closeout change order and a resolution accepting the project require Board approval. 2. HISTORY The Board previously awarded the District Pipeline Replacement— 2007— Contract B project to Hard Line Excavating (HLE) as part of the District's pipeline replacement program. This pipeline replacement program is part of the District's Objective No. 1 — Provide an adequate, reliable, and high quality water supply and distribution system to meet current and future needs and Goal No. 1.4 — Provide effective and efficient maintenance and replacement programs. On May 16, 2007, the Board approved Change Order No. 1 for this contract. That Change Order included some additional service lateral replacement into the project. 3. NEW INFORMATION On November 13, 2007, District staff performed a final walkthrough on the project. All portions of the project have been completed. I am requesting a Closeout Change Order to the Contract for issues under eight general items that will include all of the change order issues that arose during this project. Item 1: The contract is based on a unit price bid. The attached table shows the differences between bid totals and the amounts actually constructed. This analysis results in a $11,584.00 payment to HLE. Item 2: After opening of the Bids, District staff determined than an additional valve was needed at the intersection of Basel Place and Mougle Way. HLE was directed to install this valve. In addition, an MJ plug on Skiview Loop was left off the drawings and HLE was directed to install it. The associated cost is $2,817.24. Item 3: There were two locations where the field locations appeared to differ significantly from the Drawings. At these locations, HLE was directed to perform some Page 1 exploratory excavation to confirm the existing utilities. It was determined that new construction was not necessary and HLE was directed to backfill the excavations. The associated cost is $1,972.96. Item 4: The District's standard construction of a double service for single-family residences consists of two side by side meter boxes that are not rated for vehicular traffic. In locations where the meter boxes may be impacted by vehicle traffic or snow removal equipment it is necessary to install an additional traffic rated concrete box to protect these facilities. The original bid did not include installation of any traffic rated services. However, field conditions dictated that traffic protection be installed for six double services. The cost for each service was $939.70 for a total of$5,638.18. Item 5: As is typical with pipeline replacement projects, it is often necessary to perform repairs to the existing pipelines so that service to customers can be maintained while the new pipeline is constructed. There were at least 12 locations requiring repairs. In addition, there were also a couple of mismarked service laterals that were damaged by the contractor requiring repair. The total value of this repair work is $41,164.96. Item 6: As noted in Item 5, there were a number of locations where the existing pipeline required repairs. There were other locations where leaks on the existing pipe were not heavy enough to require repair. However, these leaks were close enough to the new pipeline trench so that the backfill around the new pipe became saturated. After the old pipe was abandoned, and prior to paving, HLE was directed to excavate the saturated soils and recompact the area at two locations comprising about 400-500 feet of trench. The cost of this work was is $11,110.80. Item 7: A total of 10,336 square feet of additional paving was performed by the contractor. As noted in Item 5, there were a number of locations where the existing pipeline required repairs. This pavement restoration work is not included in the original bid. In addition, there were a number of locations where previous pavement patches were in poor condition, requiring repaving. The total cost of this additional paving work is $62,017.50. Item 8: The project included replacing and reconfiguring the pipelines at the Ski Run tank site. The pavement at this tank site was in poor condition prior to HLE starting work. After completion of the pipeline work, it was determined that none of the original asphalt should be retained and that the entire site should be repaved. A portion of this cost was allocated to HLE as part of the original bid. The remainder is the responsibility of the District for a total of$18,483.28. Item 9: Change Order No. 1 added some additional service lateral replacement into the project. One of the service laterals replaced was over 200 feet in length and the District chose to upsize the lateral from 1.5" to 2" to ensure that adequate pressure could be provided to the customers. The cost of this upgrade is $786.00 4. SOURCE OF FUNDING The source of funding for this work is the funds generated by issuance of the 2006 COP. Page 2 5. RECOMMENDATION a) That the Board authorize Contract Change Order No. 2, in the amount of a $155,574.92 payment from the District to Hard Line Excavating. b) That the Board pass a Resolution accepting the District Pipeline Replacement — 2007 — Contract B project as complete and authorizing the filing of the Notice of Completion. �j �zi Ed Taylor, Water Utility Manager 'John Ulrich, rm GM- 1 Attachments: Change Order Form Draft Resolution Page 3 Change Order Public Contract Name: DISTRICT PIPELINE REPLACEMENT—2007—CONTRACT B Contract Change Order No: 2 Orig. Contract Amt. $ 944,275.00 Days NA Date: November 14, 2007 Prev. Apprd Chang$ 0.00 Days NA Contractor: Hardline Excavating This Change$ 155,574.92 Days NA Revised Contract Amt. $ 1,099,849.92 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District. Increase in (Decrease) Contract Time Contract in Contract Extension Description of Changes Amount $ Amount $ (days) 1) Bid vs.Actual Quantities $11,584.00 NA 2) Design Changes $2,817.24 NA 3) Investigate Unknown Conditions $1,972.96 4) Traffic-Rated Boxes at Double Services $5,638.18 5) Leak Repairs & Mismarked Utilities $41,164.96 6) Recompaction due to Leaks $11,110.80 7) Additional Paving $62,017.50 8) Additional Paving at Ski Run Tank Site $18,483.28 9) Upgrade Service Lateral from 1.5 to 2" $786.00 Totals $155,574.92 Net change in contract amount(increase or decrease) $155,574.92 The amount of the Contract will be increased by the sum of $155,574.92 and the Contract Time shall not be extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the District. Accepted: /Contractor Date: 1 l-t 5'-C 7 (Signature) Approved: /District Date: (Signature) " DONNER Public Utility District Resolution No. 2007 - xx AUTHORIZING THE ACCEPTANCE OF THE DISTRICT PIPELINE REPLACEMENT — 2007, CONTRACT B PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to undertake the District Pipeline Replacement—2007— Contract B project; and WHEREAS, Hardline Excavating was selected by the District to perform the work; and WHEREAS, Hardline Excavating has completed all of the work included in the Project; and WHEREAS,The District's Water System Engineer, Neil Kaufman,now certifies the completion of the project;and WHEREAS,the District's Water Utility Manager, Ed Taylor, has recommended that the work be accepted by the District; NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows: 1. That the District hereby accepts the District Pipeline Replacement- 2007 Project— Contract B as complete. 2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion,a copy of which is attached hereto. 3. That 35 days following the filing of the Notice of Completion, the monies retained from the contractor payments be released to the contractor if no claims have been made to the District by material suppliers or laborers. PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the 19th day of November 2007 by the following roll call vote: AYES: NOES: ABSTAIN: ABSENT: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Tim F. Taylor, President of the Board ATTEST: John Ulrich, Clerk of the Board RECORDING REQUESTED BY: Truckee Donner Public Utility District WHEN RECORDED, RETURN TO: TRUCKEE DONNER PUBLIC UTILITY DISTRICT Post Office Box 309 Truckee, CA 96160 THE UNDERSIGNED DECLARES DOCUMENTARY TRANSFER TAX-NONE NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. That the name and address of the public entity for whom the improvement project was done, as owner thereof, is the Truckee Donner Public Utility District, Post Office Box 309, Truckee, CA 96160. 2. Nature of interest or estate of owner: beneficial interest of a public utility easement for installation of water facilities. 3. That on November 19, 2007 the hereinafter described improvements were accepted as complete pursuant to Resolution 2007-XX of the Truckee Donner Public Utility District, the awarding authority. 4. That the subject improvements of the Notice are generally described and identified as follows: District Pipeline Replacement-2007 Project—Contract B project Installation of water pipeline and appurtenances on portions of Basel Place, Skislope Way and Skiview Loop in Truckee, California. 5. That the name and address of the contractor for such project was: Hardline Excavating, P.O. Box 10029, Truckee, Ca. 96162 1 certify under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By John Ulrich, Interim General Manager MAIL TAX STATEMENTS TO: SAME AS ABOVE Legal References: CC-3093,CCP-2003 (oath), 2015.5 (unsworn statement) Bid Item D Mounts it Price Subtotal 1 Mg3,000.00 $ 33,000.00 1A 8"' $75.00 $ 163,275.00 1 B 8" $63.00 $ 43,974.00 1 C 1.E $55.00 $ 32,230.00 1 D 1.f $45.00 $ 28,845.00 1 E Dg2,500.00 $ 65,000.00 Skiview 1 F Dg2,500.00 $ 25,000.00 1G Sir,1700.00 $ 3400.00 1 H Sir,1,700.00 $ 1:700.00 11 Fir,5,250.00 $ 31,500.00 1J Cc5,500.00 $ 5,500.00 1K Te5,500.00 $ 5,500.00 1 L Te5,500.00 $ 5,500:00 1M Te5,500.00 $ 5,500.00 1N Gz1,500.00 $ 1,500.00 10 Rc$500.00 $ 12,500.00 1 P A113,000.00 $ 3,000.00 Skislope 2A Sty $75.00 $ 66,675.00 213 St; $75.00 $ _ 2C St"$110.00 $ 68,200.00 2D St;$110.00 $ 11,440.00 2E St; $75.00 $ 110,025.00 2F 1.! $55.00 $ 16,280.00 2G 1.E $45.00 $ 16,965.00 2H Do,500.00 $ 20,000.00 21 Siq,700.00 $ 1,700.00 2J DO'500.00 $ 30,000.00 2K Fi5,250.00 $ 26,250.00 2L R�250.00 $ 5,250.00 2M 1";500.00 $ 7,000.00 2N C(5,500.00 $ 5,500.00 20 Cc),500.00 $ 5,500.00 2P Tee 250.00 $ 5,250.00 2Q Tg,250.00 $ 5,250.00 2R Si>500.00 $ 22,500.00 2S Rc$500.00 $ _ 2T A11,000.00 $ 3,000.00 3A 8" $75.00 $ 30,375.00 3B 1.' $55.00 $ 660.00 3C 1.; $45.00 $ 900.00 Basel 3D Sij,000.00 $ 3,000.00 3E C5,500.00 $ 3,500.00 3F C1,500.00 $ 3,500.00 3G R$500.00 $ _ 3H AI,000.00 $ 3,000.00 CO 1 Work 4B 1�DR500.001 $55.00 $ 12,540.00 $45.00 $ 675.00 500.00 $ 2,500.00 $ 1,500.00 $ 955,859.00 to HLE $ (11,584.00)