HomeMy WebLinkAbout6 Biomass cost Agenda Item # 6
UCKEE f
Public Utility District
Memorandum
To: Board of Directors
From: Peter Holzmeister
Date: February 2,2007
Subject: Biomass plant cost overruns
Why this matter is before the Board: This matter involves a request from the Truckee
Donner Park and Recreation District that TDPUD pay the cost of contract overruns
associated with construction of the building housing the biomass plant at Regional Park.
History: It is my understanding that the history of this project is as follows. Western Area
Power Administration contacted a group of public utilities and informed them that there was
money available from the California Energy Commission (CEC) for a variety of possible
projects. This District was contacted and Scott Terrell worked with McNeil Technologies Inc,
a consultant working for CEC, and applied for a grant to construct a biomass plant in
Truckee. A grant was approved in the amount of $240,000. It is my understanding that a firm
named Community Power Corporation had already been identified as the supplier of the
actual biomass plant. McNeil Technologies was to oversee installation of the plant and
perform data gathering to ultimately prepare a report on the feasibility of the plant. The plant
was not like other biomass plants that exist. This plant was to use a gasification technology
which might reduce the emission of pollutants common to other biomass plants.
Truckee Donner Recreation and Park District was contacted and agreed to allow the plant to
be constructed at Regional Park. They agreed to operate the plant during its study period.
Wood chips from the Forest Service would be the fuel.
Eventually the project team realized that no plan had been made for a building to house the
biomass plant. Additional money was secured from the U.S. Forest Service ($30,000), the
CEC ($90,000) and the TDRPD ($10,000) for a total of $130,000 for a building. McNeil
prepared plans for the building, which were woefully inadequate. Michael Horn Company of
Kings Beach was contracted to acquire and erect a steel building for a contract price of
$125,450.00. Since the building was to be erected at Regional Park, the contract was
between Michael Horn Company and the Recreation and Park District. A copy of that
contract is attached.
A series of problems then occurred. The site initially chosen for erection of the building
turned out to be an old dump site, so the building could not be placed in that location. The
1 Biomass
building needed to be re-permitted. Michael Horn processed the new permits. He also
needed to secure the building, which had been delivered, so he rented a fence. The new site
chosen for the building was sloped, so the foundation needed to be redesigned and
additional foundation work needed to be done. Because of the slope of the land a deck had
to be constructed according to Fire District requirements. When it came time to connect up,
the biomass plant in the building the electrical system that had been specified by McNeil and
installed by Michael Horn was inadequate and needed to be reworked. A series of other
changes needed to be made to the building. The end result is that Michael Horn requests
payment in the amount of $28,803.36 to cover the cost of the overruns.
Attached is an analysis of extra costs submitted by Michael Horn. The list totals $32,446.89,
but he is requesting payment in the amount of $28,803.36 by reducing his claim for profit and
overhead by $3,643.53. See the attached letter dated August 9, 2006 from Michael Horn to
Scott Terrell.
believe that Michael Horn is entitled to payment of $28,803.36. The question is who
should pay?
Truckee Donner Recreation and Park District believes that it is not their obligation to pay the
bill. It is their position that they were simply cooperating with TDPUD in a demonstration
project. Their participation was an overwhelming burden because operation of the biomass
plant was labor intensive and produced very little electricity. The Recreation and Park District
hoped to break even, that their labor investment in operating the plan would equal the value
of electricity generated for their facility. In fact, they lost money. For every $78.12 of labor
expended by the Recreation and Park District, the plant produced $4.17 worth of electricity.
During the entire year that the plant was operational, it produced a total of 660 kilowatt hours
of electricity. The plant had a capacity factor of about 1.5%. They are fed up with the plant
and want it removed as soon as possible. Once the biomass plant is removed from the
building, the building remains the property of the TDRPD.
They believe that since this project was pushed by TDPUD, we should pay the cost overruns.
If TDPUD agrees to pay the bill, it can come from public benefits.
There are some costs that benefit TDRPD directly that should be paid by them. Water line
extension amounting to $660, and a gas line amounting to $210.55 should be paid by the
Recreation and Park District.
McNeil may have some obligation to pay portions of this bill, although it may be difficult and
costly to collect from them.
Recommendation: I recommend that TDPUD pay Michael Horn $27,932.81 and that the
remaining $870.55 be paid by TDRPD
2 Biomass
CONSTRUCTION CONTRACT
1. Parties. This Contract is between Truckee Donner Recreation and Parks District
(hereinafter"Parks" or"Owner") as Owner, and The Michael Horn Company,Inc.
(hereinafter"Horn"or"Contractor")as Contractor.
Owner's address is:
Truckee Donner Recreation and Parks District
10046 Church St.
Truckee, CA 96161
Horn's address is:
The Michael Horn Company, Inc.
Post Office Box 628
Kings Beach, CA 96143
2. Description of Work(Scope of Work). Except as set forth herein, Horn will
furnish labor,material,tools, scaffolding and safety equipment to construct and
complete in a good, expeditious, and workmanlike manner,the work necessary for
the proposed Biomass Generator Building in the Truckee River Regional Park
located at 10500 Brockway Rd. The Work shall consist of construction of a 48'x 30'
steel building purchased and paid for by Truckee Donner Recreation and Parks
District from the Michael Horn Company, Inc. on June 30th, 2004. The construction
shall include the following: Design services, engineering, plans,permits,
excavation,transformer pad(transformer supplied and installed by TDPUD), special
inspections, foundation,build erection, insulation, framing labor and material for
chip storage stalls inside and 3'-6"x I P deck and stairs to grade outside, 1-3' x 7'
walk door 1-4'x4' window, 1-10'x10' sectional steel garage door, electric from new
meters to bio max unit(including lighting and outlets),ventilation fans,hydronics to
park office, approximately 900sq ft of paving for chip storage and snow removal,
snow melt between park office and biomax building, cleanup and rental equipment.
3. Contract Price; Labor Rates; Statements; Payments.
a. Contract Price. Owner shall pay Horn for the performance of the contract the sum
of ONE HUNDRED TWENTY FIVE THOUSAND FOUR HUNDRED FIFTY
DOLLARS ($125,450.00)and pursuant to the procedures set forth in Section 3.c.,
below,to complete the Work requested by Owner pursuant to this Contract. It is
hereby acknowledged that the above contract price includes the cost of the
1
48'x30'steel building and the Contractor received full payment of$22,728.55 on
June 30th, 2004 for the building.
b. Labor Rates. Owner shall pay Horn for extra labor, if any, at the following rates:
- $70.00 per hour for Michael Horn
- $65.00 per hour for carpenters
- $48.00 per hour for apprentice carpenters
- $32.00 per hour for laborers
Owner shall also pay Horn for the cost of extra material and subcontractors, if any,
incurred by Horn in the performance of its duties under this Contract, plus fifteen
percent (15%). The 15% shall only apply to material and subcontractors and not to
Horns labor.
c. Billing Statements and Payment. Horn shall transmit to Owner or Owners Agent
billing statements (invoices) approximately every two (2)weeks for work completed
as of the cut off date shown on each statement. Payment is due Five (5) working
days from date of statements (invoices).
4. Commencement and Completion Dates. Horn shall commence work on the
project June 6t , 2005. Horn shall reach substantial completion by August 1st, 2005
Substantial completion means the new building is ready for installation of bio max
generator. There may be some minor pick up work to finish.
5. Materials and Subcontractors. Horn shall supply and pay for all subcontractors
and construction materials, including lumber, for the Project. Owner shall reimburse
Horn for the above Subcontractors materials in accordance to section 3.c. of contract
documents.
6. Extra Work, Changes, and Deletions. If Owner, Owner's agent, Construction
lender, or any public agency or inspector directs Horn to perform any modification
or addition to Horn's scope of work under this contract Owner shall pay Horn the
cost of that work pursuant to the rates and procedures set forth in Sections 3.b. and
3.c., above. All changes or deviations from the Plans, additional work, or deletions
to the Project shall be affected by written change orders. These change order forms
shall be provided by the Contractor and signed by both Owner and Contractor.
7. Job Information. The name and address of the project owner, the original
contractor, construction lender, and Owners Agent(if any) are as follows:
Project Owner:
2
Truckee Donner Recreation and Parks District
10046 Church Street
Truckee, CA 96161
Contractor:
The Michael Horn Company,Inc.
P.O. Box 628
Kings Beach, CA, 96143
Construction Lender:
Owners Agent:
8. Right to Stop Work; Right to change Contractors. If Owner fails to make any
payment when it is due, Horn may stop work, and keep the Project idle until all
amounts owing have been paid. If Horn does not perform work at the Project
without valid reason for a period of ten (10) business days, Owner may give Horn a
written notice advising Horn that if Horn does not resume work within five (5)
business days of notice, Horn will be in breach of this Contract that Horn may be
terminated from the Project, and that Owner will be entitled to engage another
contractor to complete Hom's scope of work under this Contract. In the event that
Owner decides to take the above action, Horn shall be paid for all cost incurred to
the date of termination. If Owner terminates this contract for any reason Horn shall
draft a letter of release of any liability and interest as Contractor of record and
supply this letter to Owner upon receipt of final payment to Horn as stated above.
9. Interest. Overdue payments will bear interest at the rate of 1-1/2%per month.
10. Delay. Horn shall be excused for any delay in completion of this Contract caused
by acts of God, of Owner, of Owner's agents or employees, or subcontractors, or of
other contractors; inclement weather; labor trouble; acts of public utilities, public
bodies or inspectors (but not related to possible defects in Hom's performance);
changes requested by Owner; failure of Owner to make progress payments
promptly; or other contingencies unforeseen by Horn and beyond its reasonable
3
control.
11. Destruction of or Damage to Premises. If the Project is destroyed or damaged by
fire, storm, flood or other catastrophe,or by vandalism, Owner shall pay Horn for all
work performed to date and this contract shall become void unless a written change
order to proceed is signed. In the event that a change order is signed, Owner shall
pay Horn in rebuilding or restoring the Project as extra work and pursuant to Section
3.b. and 3.c. above.
12. Insurance. Contractor shall keep workers compensation insurance and liability
insurance policies in force throughout the Project. Owner is responsible for all other
insurances. Owner is advised to check with its insurance agent for proper coverage.
13. Cleanup. Throughout the course of the Project, Horn shall keep its work area at the
property organized and free from excessive accumulation of waste material or
rubbish caused by its operations. On completion of the Project, Horn will remove its
tools and equipment from the Project, leaving that area in a neat and broom-clean
condition.
14. Dispute Resolution.
(a) Mediation. The parties agree that if any dispute arises from or relates to this
Agreement or the breach thereof, and if the dispute cannot be settled through
direct discussions, the parties agree to endeavor first to settle the dispute in an
amicable manner by mediation administered in Nevada County, California, by a
mutually acceptable mediator, or if the parties are unable to agree on a mediator,
by the American Arbitration Association under its Commercial Mediation Rules,
before resorting to arbitration. The mediation shall be conducted by a single
neutral mediator agreed to by both Parties. Any agreement achieved through
mediation shall be reduced to writing and signed by all parties. Except as
otherwise specifically provided, neither party shall initiate arbitration or other
dispute resolution procedure unless and until the dispute resolution procedures of
this subparagraph have been employed or waived.
(b) Mandatory Arbitration. Thereafter, any unresolved controversy or claim
arising from or relating to this Agreement or breach thereof shall at the request of
any party be determined in a binding arbitration proceeding conducted in Nevada
County, California, administered by a mutually acceptable arbitrator, or if the
parties are unable to agree on an arbitrator, by the American Arbitration
Association in accordance with its Commercial Arbitration Rules. The arbitration
may be conducted by the person who served as the mediator under subparagraph
(a) if all of the parties agree in writing to such appointment. If not, the arbitration
4
shall be conducted by a single neutral arbitrator agreed to by both parties. The
arbitrator may award legal fees and costs and shall have the authority to grant both
equitable and legal relief, and judgment upon the decision rendered by the
arbitrator may be entered in any court having jurisdiction thereof. The decision of
the arbitrator shall be final and binding upon all parties and in the event of any
need to clarify or interpret the decision of the arbitrator, the matter will be
resubmitted to the arbitrator for clarification or interpretation.
(c) Provisional Remedies. No provision of subparagraph (b) shall limit the right
of a party to obtain provisional or ancillary remedies from a court of competent
jurisdiction before, after, or during the pendency of any mediation or arbitration.
15. Notice. Any notice required or permitted under this Contract shall be deemed
given, if in writing,upon the earlier of delivery or three(3) days following deposit in
the United States mail, first-class postage prepaid and addressed to the parry at the
address set forth in Section 1, above, but such addresses may be changed by written
notice from one parry to the other.
16. Attorneys' Fees. In the event of litigation or arbitration between the parties to this
Contract concerning any provision of this Contract, or the rights or obligations of
either party in relation thereto, the prevailing party in such proceedings shall be
awarded reasonable attorneys' fees in addition to such other relief as may be granted.
17. Signatures and Contractors' License Numbers.
OWNER: Truckee Donner Recreation and Parks District
Dated: By: (Authorized TDRPD Representative)
CONTRACTOR: The Michael Horn Company, Inc.
CA Contractor's License No. 671428
Dated /
By: Michael Ho
Its: President
5
The Michael Horn Company, Inc. Extras Invoice
P.O. Box 628
Kings Beach, CA 96143 DATE JINVOICE#
1/27/2006 1 Extras
BILL TO SHIP TO
Truckee Donner Parks
and Recreation District
582-2360 Donna
582-7724 Fax
TERMS DUE DATE
on receipt
DISCRIPTION LINE AMOUNT
Permits $ 118.10
Design Services $ 420.00
Engineering $ 1,842.50
Temporary Facilities $ 647.28
Excavation and Grading $ 5,745.27
Fence Rental $ 1,078.76
Propane $ 132.27
Foundation and site prep $ 6,007.79
MHCO Labor $ 1,318.00
Asphalt paving $ 60.00
Electrical $ 4,758.65
MHCO Labor $ 1,574.00
Fans $ 609.49
MHCO Labor $ 180.00
Rear Deck $ 2,055.13
MHCO Labor $ 2,050.00
Water Line $ 660.00
Gas Line $ 70.55
MHCO Labor $ 140.00
Muffler
MHCO Labor $ 210.00
Steam trap $ 84.43
MHCO Labor $ 360.00
Profit and Overhead Overhead and profit is not charged to $ 3,643.53
MHCO labor
Credit $(1,318.86)
THANK YOU! TOTAL $ 32,446.89
The Michael Horn Company, Inc.
General Contractor
CA LIC#671428
NV LIC#0040442
August 9,2006
Cost Overruns Report
Bio Mass Building
Truckee River Regional Park
Permits: Plan check for revised deck plan(note: there was no charge for revisions to the new site or
foundation plans). SITE MOVE
Design Services: Services of the Michael Horn Co., Inc. staff,to survey, draft,copy,get approval from
various agencies and submit revised plans to Town of Truckee Building Dept. for the relocated site. SITE
MOVE
Engineering: Charges for GRC Engineering to revise the foundation engineering and add the deck to the
rear of the building. SITE MOVE
Temporary Facilities: Porta-Poti not in original estimate.
Excavating and Grading: TTSD requested that the sewer line going under the new building be replaced
with C-900 pipe and hand trenching had to be done to avoid unknown pipes that were along side the
sewer line.At least one of these pipes wa.�,the main power coming from the transformer located at the old
site. SITE MOVE
Transformer Pad: Bio Mass generator was set up for single phase not 3 phase power and as there
was no single phase to the park at that time a new transformer and pad had to be set and additional
trenching performed. Lazzareschi Excavating performed the task as directed by the TDPUD. This
included a tie into the existing 3 phase transformer and large boulders were encountered which added to
the difficulty. SITE MOVE/TDPUD
Additional gravel for backfill: Due to the height of the foundation and the large quantity of
boulders that had to be removed for the foundation and sewer line replacement area, an additional amount
of gravel backfill for the slab prep had to be imported. The use of a vibra plate was necessary due to the
depth of the fill to insure proper compaction. SITE MOVE
Fence Rental: Upon delivery,the building was set at the original site. When it was learned that the
project would be delayed a fence was rented to protect the public and protect the building from traffic.
SITE MOVE
Propane: There was no allowance for propane as the tank was to be provided by Suburban Propane.
Before the commissioning of the generator I found out that the system needed liquid propane and it was
determined that a small tank would be more convenient,therefore a 10 gallon tank was purchased. Reno
was the only location that had this type of tank. COMMUNITY POWER CORP.
Foundation& site prep: Town of Truckee required erosion control at the new site. Foundation quote
was based upon original drawings. Contractor made every effort to get the building dept.to allow use of
P.O. Box 628 - Kings Beach, CA 96143 - Phone (530) 546-7865 - Fax (530) 546-2441
The Michael Horn Company, Inc.
General Contractor
CA LIC#671428
NV LIC#0040442
the original plans but was denied.The revised foundation plan called for a substantial increase in both
rebar and concrete as well as an increase in material cost. SITE MOVE
Asphalt Paving: Paving between buildings was extended adding a minimal charge.
Electrical: When designing the electrical requirements for the building it was determined that a single,
125 amp circuit to the generator, several outlets along each wall and florescent lighting on the ceiling
would be adequate. The estimate of$4,930.00 was more than enough for this work. It wasn't until a week
before Mike Walker form Community Power arrived to commission the generator that we began to
realize the complexity of the electric service needed. This came to light through many phone calls
between me,Mike Walker, and Sveri Vandehei(Vanhehei Electric). Once Mike arrived to set up the
system it was determined that even more circuits were needed and this continued to change with the
TDPUD's requirements to make the system safe for service techs on the PUD's end of the system. Work
was performed by Mick Horn,The Michael Horn Co. employees and Sveri Vandehei. COMMUNITY
POWER CORP./MCNEIL TECHNOLOGIES
Fans: The power vented fan at the rear of the building was included in the original quote however the
chain operated vent at the front of the building was not. It was determined that it would be necessary to
add this vent in the event that air flow was need through the building while the sectional door was closed,
to avoid air starvation to the generator. RANDY HUNSBURGER—MCNEIL TECHNOLOGIES
Rear Deck: Because the building had already been designed and manufactured before the site was
changed, a rear deck was required and also deemed necessary to allow the public to see the bio mass
generator while the building was closed. SITE MOVE/TRUCKEE FIRE DISTRICT
Water Line: Water and sewer were added for future Parks and Rec. use. PARKS AND REC.
Gas Line: A natural gas was added from the office deck to the outside of the bio mass building for future
use. PARKS AND REC.
Muffler: MHCO was directed to measure, have fabricated and install the muffler for the generator.The
materials were paid for by McNeil Technologies. SCOTT TERRELL/MIKE WALKER(C. P. C.)
Steam Trap: Mike Walker and Community Power determined that a steam trap was necessary for the
heat exchange unit in line with the muffler. MHCo. was directed to locate, order,purchase and install the
steam trap. C. P. C.
Respectfully,
Michael Horn
President
The Michael Horn Company, Inc.
P.O. Box 628 • Kings Beach, CA 96143 • Phone (530) 546-7865 • Fax (530) 546-2441
The Michael Horn Company, Inc.
General Contractor
CA LIC#671428
NV LIC#0040442
8/9/2006
Scott Terrell
TDPUD
Truckee, CA 96161
Re: Bio Mass
Dear Scott,Enclosed is information pertaining to the extra costs for the Bio Mass Building.Most of this
you have but I'm not sure how complete it is as you stated that you received it as a fax from Steve
Randall from TDPRD. The information is a complete copy of the cost over runs invoice, report and
backup documentation. Per your request,the Cost Overruns Report has red lettering after the description
to help clarify where the costs came from.The amounts are on the invoice with the back up
documentation following. As per our conversation,while meeting with Steve Randall,I was willing to
take out the overhead and profit from the extras in order to clear this up as soon as possible. Below is the
Final amount due:
Invoice amount: $32,446.89
Overhead and profit - 3 643.53
Balance due $28,803.36
Two other kems you asked me to check on;
1)Check the figures on the main accounting as a couple of figures did not add up.The building cost was
did not get added in,and,when done, balanced the sheet(this would not change the extras charges
regardless).
2)Check to be sure that no overhead and profit was added to MHCO labor.This was checked and did not
occur.
I hope this clears up any question you have as I'm not sure how to be any more concise with the reports
provided. Hopefully in the 3 months since our meeting you were able to get the ok on funds and this is the
final info needed before I receive final payment.
Respectfully,
Michael Horn
President
The Michael Horn Company, Inc.
P.O. Box 628 - Kings Beach, CA 96143 - Phone (530) 546-7865 - Fax (530) 546-2441
• ■.
AI
&FE
Public Utility District i
IF
Staff Report
To: Board of Directors
From: Scott Terrell
Date: January, 2007
Western Area Power Administration Staff formed a group called the Public Renewable Partnership
made up of about 15-20 publically-owned electric utilities throughout California. PRP applied and
received$6,000,000+in grant funding from the California Energy Commission.The grant money
included funding to run and test a 15 kilowatt biomass unit as a research,development and
demonstration project and to conduct an assessment of whether a large-scale biomass plant could be
built in the Tahoe-Truckee area that could provide a reliable and economical supply of electrically
generated power.
The purpose of the 15 kW biomass demonstration project was to conduct research on the bio-
gasification technology and to educate the community to help them understand how the technology
works and the pros and cons of it's use at it's early stage of development. Staff collected a lot of data
on the Biomax 15 unit's operation and maintenance to identify it's shortcomings to help in it's future
development with the idea of one day becoming a dependable,commercially available technology.
The grant funding did not originally include monies for a building that was needed to protect the unit
and equipment from inclement weather.The need for a building caused significant delays in the project.
Even after building funding was procured the project was once again delayed by the need to change
the location of the project from near the tennis courts at Regional Park to land adjacent to the Park
office building. Once the building was up we were able to locate the biomass unit in the building to
begin the research and demonstration of this Biomax 15 technology.
The first step in beginning to implement the project was unit assembly,commissioning and start-up and
operator training.Community Power Corporation (CPC)performed this first step in early November,
2005.The Biomax 15 unit became grid-tied and operating in the last week in December.We were only
able the run the unit for a few weeks before McNeil Technologies,the project consultant to the CEC,
needed to submit the Final Report to the CEC in early January,2006. Since the project ran about one
year behind schedule because of the need to build and relocate the building,TDRPD staff agreed to
continue to collect data through 2006.The pilot project operation and data collection period was
extended through February,2007 to collect more data and educate a few more groups about the
project before it is decommissioned.
The other element of the grant involved a report on the feasibility of a 1-5 Megawatt biomass plant in
Truckee. This feasibility study included many elements including assessing the potentially available
biomass material for a future biomass plant,a look at what large-scale, state-of-the—art plants were
being tested or commercially available and the economics of running a large-scale biomass plant in
Truckee as compared to the cost of other power generation resources.This report has been completed
and it is available for review,TDRPD and TDPUD staff prepared a power point presentation on both
the 15 kilowatt Biomax unit and the feasibility and economics of a large-scale biomass plant in Truckee.