Loading...
HomeMy WebLinkAbout7 Storage Tank change order Agenda Item # DONNER Public Utility District Memorandum To: Board of Directors From: Jessica Wilson Date: July 5, 2007 Subject: Change Order No. 1 for the Storage Tank Rehabilitation— 2007 Project 1. Why this matter is before the board: Approval from the Board of Directors is necessary to issue a Change Order to a construction contract. 2. History: On June 6, 2007, the Board awarded the Storage Tank Rehabilitation — 2007 project to Olympus &Associates, Inc., in the amount of$83,825.00. 3. New information: The following modifications to the Sierra Meadows Tank must be completed before re-coating the interior: • Installation of two 8-inch U-vents on the edge of the roof - Currently there is one mushroom vent in the center of the roof that does not vent well under snow loads. The U-vent design has proven to work well on other District tanks. • Installation of 20 feet of handrail on the roof- Currently there is no handrail. The railing will be placed around the exterior ladder and roof hatch for safety. • Removal of the interior ladder-The existing aluminum ladder is severely corroded and is no longer safe to use. Because having an interior ladder is not a code requirement, the most cost efficient solution is to remove the ladder without replacement. Staff anticipated that the District Operations Crew would complete the above modifications by August 3, 2007, so that the Contractor could begin on August 6, 2007, as scheduled in the Contract Documents. The Contractor, however, requested that they be allowed to begin the Work earlier and submitted a quote to perform the modifications. Page 1 Staff believes that Olympus' proposal would save the District money and time. Their quote is less expensive than what it will likely cost the District to perform the same work because it is their area of expertise. Also, by performing the Work earlier in the year, there is less likelihood that the District will need to pay the Contractor for "Environmental Controls", controlling temperature and humidity within the tank. At the moment, the Water Crews have three less people working than last summer. If Olympus works on the modifications, it will free up crew time to work on other projects and maintenance. 4. Recommendation: I recommend that the Board authorize Contract Change Order No. 1, in the amount of a $3,411.00 payment to Olympus & Associates, Inc., from the District. Attachments: Change Order Form Page 2 FROM OLYMPUS AND ASSOSIATES INC PHONE NO. 775 322 0288 Jun. 29 2007 01: 11PM P2 ,m Jun-2rs-2007 12:070M Fro-''R'WCKEE DONNER PUO +5305871189 T-148 P•002/002 F-343 TRUCKEE DONNE , flange Order Contract Name: Storage Tank Rehabilitation-2007 contract Change Order Nc: _ Crig. Contract Amt.3 83.1825.00 Days NA Date: Julys,2007 Preu. Apprd Charges 3 0.00 Days _,NA Contractor Iympu6&Associate�lrtc. This Change 3 _ 3,411,00 Days NA Riviised Contract Amt. 3 87,236.00 Days _ NA _ This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, fumish equipment and metedais, and perform all work as neomeary or required to comnplete the Change Order lteTns for a lump sum price agreed upon between the Contractor and District. Increase in (Deor'ease) Contract Time Contract in Contract Extension Description of Changes Amount W ; Amount W (days) _ I —Modifications to Tank Aopurtenanoes $3,411.00 NA I i i i Totals I $3,411.00 Net change In contract amount(Increase or decrease) $3,411.00 I The amount of the Contract will be increased by the >gUm e+f $3,411,00 and the Contract Time shall not be sxi tided. The undersigned Contractor approves the foregoing Change Order as to the changer., if arty, in the oontm,61 price specified for each item InelUding any and all suparvlslan COM and other miscelisrieous costs relating to the dhange in work,and as to the extension of tirrie narrowed, if any:for romplelon of the entire work on account or said Change Order. The Co m^a= agreels to rurnish all labor and rnntarlals and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This merit will become a supplarn®tit of the contract and all provisions will apply hereto. It is understood that th range Order shall be effective when approved by the District / 2 t7 Accepted: /Cc-itracwr Date: at�re Approved; District. bate: (Signature) Page 1