HomeMy WebLinkAbout10 Red Mountain Tank Change Order Allowance
AGENDA ITEM #10
Page 1 of 3
MEETING DATE: July 21, 2021
TO: Board of Directors
FROM: Neil Kaufman, Water System Engineer
SUBJECT: Consideration of an Additional Change Order Allowance for the
Construction of the Red Mountain Water Storage Tank
APPROVED BY______________________________
Brian C. Wright, General Manager
RECOMMENDATION:
Approve an increase in change order allowance for the Red Mountain Tank Construction
Project from 10% ($86,982) to 12% ($104,379), for a new total project amount not to
exceed $974,199.
BACKGROUND:
At the August 5, 2020 meeting, the Board approved an amendment to the Coldstream
Development and Reimbursement Agreement between the District and Coldstream
Properties, LLC for the construction of ce rtain potable water system improvements
associated with Phase 3 of the Coldstream Development (PC -1). The water utility system
improvements included the on-site water utility distribution system infrastructure within the
development's Phase 3 parcels, as well as the design and construction of a potable water
storage tank at the Red Mountain site, which is located on the south side of Donner Lake.
A copy of the First Amendment to the agreement has been included with this report as
Attachment 1
In June, 2020, the developer had issued a request for bids for the construction of the Red
Mountain Tank. The scope of work included the construction of a welded steel potable
water storage tank as well as site work such as grading, foundation construction and the
associated underground piping. Following review of bids for compliance with District
standards and specifications, contractor experience and familiarity with similar projects in
the region, and proposed construction schedules, the developer with approval f rom staff,
identified Crosno Construction from Arroyo Grande, CA as the most favorable contractor
for the project. The total bid price for the tank project was $869,820.
The development agreement outlines specific provisions for reimbursements to the
developer for construction of the storage tank. An initial change order allowance of ten
Page 2 of 3
percent ($86,982) was included in reimbursement agreement.
Construction of the tank began in June 2020. It was planned to complete all of the grading,
tank foundation and site piping work during 2020. Work would then pause for the winter of
2020-21, with construction of the actual tank and completion of the project planned for the
summer of 2021.
The contractor encountered some difficulties during the site grading p ortion of the project
involving large boulders and saturated soils. A number of discussions occurred involving
Crosno, the developer and the District along with the design engineer and geotechnical
engineer for the project. It was eventually agreed that Crosno was due an additional
$55,428.68. This total covered the issues associated with the boulders and soils, along
with some modifications to the site piping and additional rebar for the retaining wall at the
site.
In June 2021, a change order for $26,551 was approved by District staff. This change
order covered the addition of three items not included in the original design:
A safety handrail along the top of the retaining wall
A safety platform for improved access to the exterior tank ladder
A stilling well for level sensing instrumentation inside the tank
These change order items total $81,979.68, which is approximately 9.4% of the original
contract amount.
Additionally in June 2021, District staff worked to finalize approval of the proposed exterior
coating for the tank. The area near the Red Mountain tank site has heavy tree cover. The
tank site is generally not visible to the community with the exception of two existing
residences. One is adjacent to the tank site and the other is across the street and uphill
from the tank site. A site meeting was held with the se two property owners identified a
coating color with a shade of dark green acceptable to both owners was selected.
During this time, a number of discussions were also held with the local representative for
the tank coating manufacturer (Tnemec). The District has used the same exterior coating
specification since the mid-1990s and construction of Gateway Tank. There have been a
number of changes and improvements regarding the coatings for steel water tanks since
that time.
The intermediate coating system listed in the specification has been discontinued.
A different intermediate coating system is required due to regulatory changes
associated with volatile organic compounds (VOCs).
Better exterior coatings for steel tanks have been developed. Tnemec is currently
recommending that the finish coating system listed in the specification be used on
concrete only. They are recommending a newer product with improved durability
Page 3 of 3
and graffiti resistance for steel tanks.
Based on the new recommendations from Tnemec, Crosno was contacted to determine
if there would be a cost increase associated with the exterior coating changes. Crosno
provided a revised quote for the proposed coatings with a total price increase of
$14,110 (materials only). There was no change in the labor costs. It is the opinion of
staff that the improved durability and graffiti resistance is worth the additional expense.
Based upon recent experiences in graff iti repairs and early signs of exterior coating
failures observed at other District owned storage tank facilities, staff intends to modify
District construction standards to reflect the updated coating specifications on all future
projects. However, an increase in the change order allowance is necessary to proceed
with the modifications associated with this project. Section 3.1 of the First Amendment
to Phase 3 Final Development Agreement and Reimbursement Agreement Between
Truckee Donner Public Utility District and Coldstream Properties, LLC for Construction
of Certain Potable Water System Improvements requires that “any Change Order that
would increase the original amount owed under the Construction Contract by more than
10% may be approved by the District’s Board of Directors.”
FISCAL IMPACT:
As noted above, there is aBoard approved reimbursement agreement between the District
and the Developer associated with the construction of the Red Mountain storage tank.
Construction costs due to change orders are funded from the Water Department’s Facility
Fees Reserve Fund. Sufficient funds exist within this reserve to cover the increased cost,
with a current balance of approximately $1.84M.