HomeMy WebLinkAbout10 Attachment 1, Coldstream Phase 3 Water Development Agreement - first ame...Attachment 2
{00894323.DOCX 2 }First Amendment to Development Agreement – Coldstream Phase 3
-1-
FIRST AMENDMENT
TO
PHASE 3 FINAL DEVELOPMENT AGREEMENT AND REIMBURSEMENT
AGREEMENT BETWEEN THE TRUCKEE DONNER PUBLIC UTILITY DISTRICT
AND COLDSTREAM PROPERTIES, LLC FOR CONSTRUCTION OF CERTAIN
POTABLE WATER SYSTEM IMPROVEMENTS
This FIRST AMENDMENT TO the PHASE 3 FINAL DEVELOPMENT AGREEMENT
("First Amendment") is made and entered into as of July ___, 2020 (the "Effective Date"), by
and between COLDSTREAM PROPERTIES, LLC, a Delaware limited liability company
("Developer") and the TRUCKEE DONNER PUBLIC UTILITY DISTRICT, a local public
agency of the State of California ("District"), who agree as follows:
1. Background and General.
1.1. Development Agreement. Developer and District are parties to that certain
Phase 3 Development Agreement dated June 10, 2020 (the "Development Agreement") with
respect to the construction of potable water facilities on certain real property located in the Town
of Truckee, County of Nevada, California known as Coldstream. All capitalized terms not
otherwise defined herein shall have the meanings ascribed to them in the Development Agreement.
1.2. Tank Facilities and Reimbursement. The Development Agreement provides
that Developer shall construct the Tank Facilities and be reimbursed for the construction of the
Tank Facilities on the terms contained therein. The Development Agreement further provides in
Section 14C that the Developer and the District shall meet and confer if bids to construct the Tank
Facilities are all in excess of $500,000. The stated purpose of the meet and confer is for Developer
and the District to determine a mutually agreeable solution to reimburse Developer for all costs to
construct the Tank Facilities, including any amounts in excess of $500,000. Because all bids to
construct the Tank Facilities exceeded $500,000, Developer and District have met and conferred
pursuant to section 14C and have agreed to a reimbursement structure for the Tank Facilities that
is set forth in this First Amendment.
1.3. Purpose. The purpose of this First Amendment is to amend the
Development Agreement in the manner set forth herein.
2. Reimbursement for Tank Facilities.
2.1. Lump Sum Payment for Amounts in Excess of $500,000. Notwithstanding
any other provision of the Development Agreement, the District shall provide Developer with a
“Lump Sum Payment” in the amount of the actual costs incurred to design and construct the Tank
Facilities in excess of $500,000 (i.e. actual costs to design and construct the Tank Facilities minus
$500,000 equals Lump Sum Payment). The entire Lump Sum Payment shall be paid by the
District, in cash or other readily available funds, to Developer within 30 days following the
completion of the construction of the Tank Facilities. Construction of the Tank Facilities shall be
deemed complete upon either delivery by the Tank Facilities contractor of final lien waivers or the
filing of a notice of completion for the Tank Facilities.
Attachment 2
{00894323.DOCX 2 }First Amendment to Development Agreement – Coldstream Phase 3
-2-
2.2. Reimbursement of $500,000. The District shall reimburse Developer
$500,000 of costs to design and construct the Tank Facilities (i.e. those costs not reimbursed by
the Lump Sum Payment) in the manner set forth in Sections 14D through F of the Development
Agreement.
3. Authorization to Contract for the Construction the Tank Facilities. Prior to
entering into a construction contract for the Tank Facilities, Developer shall obtain authorization
from the District’s Water Utility Director that the selected contractor’s bid is adequate and that
Developer may enter into a construction contract with the selected bidder (such contract being
the “Construction Contract”).
3.1. Change Orders to the Construction Contract. Any change order to the
Construction Contract (a “Change Order”) must be approved by the District. The District’s
General Manager may approve a Change Order so long as the Change Order would not increase
the original amount owed under the Construction Contract by more than 10%. Any Change
Order that would increase the original amount owed under the Construction Contract by more
than 10% may be approved by the District’s Board of Directors. Any costs incurred by way of a
Change Order shall be included in the actual costs to design and construct the Tank Facilities that
are subject to reimbursement under the Development Agreement as amended by this First
Amendment.
4. Development Agreement Remains in Effect. Except as amended herein either
expressly or by necessary implication, the Development Agreement, and all terms and provisions
therein, remain in full force and effect and are ratified in all respects by all parties hereto.
5. Counterparts. This First Amendment may be executed in any number of
counterparts and each counterpart shall be deemed to be an original document. Delivery of the
executed First Amendment may be accomplished by facsimile transmission and, if so, the facsimile
copy shall be deemed an executed original counterpart of this First Amendment. All executed
counterparts together shall constitute one and the same document, and an y signature pages,
including facsimile copies thereof, may be assembled to form a single original document.
IN WITNESS WHEREOF, the parties have executed this First Amendment as of the
Effective Date.
DEVELOPER: DISTRICT:
COLDSTREAM PROPERTIES, LLC,
a Delaware limited liability company
Attachment 2
{00894323.DOCX 2 }First Amendment to Development Agreement – Coldstream Phase 3
-3-
By:
Name: Randall Sater
Its: President
By:
Name: Ronald Gatto
Its: Executive Vice President
TRUCKEE DONNER PUBLIC UTILITIES
DISTRICT, a local public agency of the State of
California
By:
____________________________________
Name: Remleh Scherzinger
Its: General Manager/CEO