PRELIMINARY DESIGN BUDGET
Project: 20-005 Truckee Donner PUD Facility Modernization
Date: Thursday, May 20, 2021
Original Estimates - 2020
1) Demo stucco and add metal siding 600K
2) Awning Construction : 330K (original 180 + 150K for additional awnings)
3) Window Replacement: 250K (220K + 30K for new hall windows)
4) Streetscape Landscaping & bench: 100K
5) New Monument Signage: 75K
6) Demo and rebuild new Entry: 575K (500K +75 columns)
7) New Lighting Sconces: 50K
8) New window trim/siding: 50K
9) New roof at Employee patio: 200K
10) Subgrade waterproofing: 100K (previously not in the scope)
11) Add 1-1/2” rigid insulation under siding: 100K
Total: 2.43m
Notes:
- Please note the following are estimates only, based on mid-2020 industry standards and are
subject to changes. The market is very volatile and it is difficult to anticipate the 2022 market
projections with any accuracy.
- Lumber has roughly doubled in price from last summer and is anticipated to continue to rise
throughout this summer. However the scope of this project is not primarily lumber.
- Metal costs have also risen. This project has structural steel and metal siding, so this cost will be
affected.
- Labor costs are rising due to quantity of building in our area and abroad. This project is labor
intensive due to the demolition work needed to remove the stucco.
- Please note unforeseen issues with the building might be revealed during demolition and
addressing larger problems might take priority, regardless of the original scope.