HomeMy WebLinkAbout12 Construction Inspection 2021 - BoardAGENDA ITEM #12
Page 1 of 4
MEETING DATE:April 7, 2021
TO:Board of Directors
FROM:Neil Kaufman, Water System Engineer
SUBJECT:Award of a Contract to Perform Construction Inspection
Services.
APPROVED BY______________________________
Brian C. Wright, Interim General Manager
RECOMMENDATION:
Authorize the Interim General Manager to execute a professional services contract with
Construction Materials Engineers to perform Construction Inspection Services during
calendar year 2021 in an amount not to exceed $150,000, plus a ten percent change
order allowance for a total authorization not to exceed $165,000.
DISCUSSION:
Since 2015, the Water Department has utilized an outside consultant to perform
construction inspection of developer-funded projects. The consultants have been
selected through a Request for Proposals (RFP) process.
During the summer of 2020, the Water Department utilized Construction Materials
Engineers (CME) of Reno, Nevada to perform this inspection work.CME was selected
based upon an RFP was issued in 2018.The work performed by CME was satisfactory
and the CME contract was extended to cover construction inspection for 2019 and 2020.
In September 2020, a new RFP intended to cover inspection of developer-funded projects
for 2021 was issued.The submittal deadline for proposals was October 30, 2020.During
November 2020, the Water Department conducted a review of upcoming projects and
anticipated staffing needs for the summer of 2021. There are major District-funded
projects to be constructed during the summer of 2021, including the District Pipeline
Replacement -2021 and the Martiswoods Pump Station projects. It was determined
that the Water Department did not have sufficient internal staff to perform inspection of
these projects. It was then decided that the scope of the construction inspection RFP
should be expanded to cover these District-funded projects.
Review of the original proposals was halted and a revised RFP was issued in January
Page 2 of 4
2021. This RFP included inspection of both the developer-funded and District funded
projects. There are additional requirements associated with District-funded projects,
including:
Inspection of storm water management practices & storm water pollution
prevention plan compliance
Inspection of site safety and traffic control
Tracking of contractor labor and equipment to facilitate review of change order
requests
Payment of prevailing wages to inspection staff
Six proposals were received in response to the revised RFP.
4Leaf –Fair Oaks, CA
Batie Plumbing, Truckee, CA
Construction Materials Engineers (CME)–Reno, NV
Lumos and Associates –Reno, NV
Universal Engineering Services (UES)–Reno, NV
Wood Rodgers –Reno, NV
A staff committee of three employees reviewed the proposals based on the following
criteria:
Experience of the firm with similar water system construction inspection
assignments
Past experience of proposed inspectors with similar water system construction
inspection assignments
Procedures methodology and quality assurance/quality control
Cost
On a technical basis,4Leaf, CME and Lumos were scored closely together as the top
three firms. UES and Wood Rodgers scored into a second tier below the top three. The
rankings are summarized below:
Technical Scoring
Firm Rank
CME 1
4Leaf 2
Lumos 3
Wood Rodgers 4
UES 5
Batie Plumbing 6
Page 3 of 4
The proposed costs were then evaluated.A typical work day was assumed for the
purpose of evaluating costs. This typical work day assumes that there will be a single
inspector that will perform inspection work on both District-funded and developer projects
on a given day. This typical work day involved:
Five hours of inspection of District-funded projects
Three hours of inspection of developer funded projects
40 miles of travel within the Truckee area
Travel time and mileage between the corporate office and Truckee
It should be noted that the actual inspection activities on any given day will vary. On
some days, there may not be any developer-funded work requiring inspections. On other
days, two inspectors might be required due to critical items such as tie-ins or pressure
testing. The cost scoring based on this typical day is summarized below:
Cost Scoring
Firm Rank
Batie Plumbing 1
UES 2
Wood Rodgers 3
CME 4
Lumos 5
4Leaf 6
Among the top three firms from the technical scoring, the costs for CME and Lumos were
essentially the same. 4Leaf has higher cost structure due to the additional travel time
and mileage from Fair Oaks instead of Reno.
The overall ranking (technical capability & cost) of the proposers is:
Overall Scoring
Firm Rank
CME 1
Lumos 2
4Leaf 3
UES 4
Wood Rodgers 5
Batie Plumbing 6
Therefore, it is recommended that the contract be awarded to CME.
GOALS AND OBJECTIVES
1.05.020 Objectives:
3. Provide reliable and high quality water supply and distribution system to meet current
and future needs.
Page 4 of 4
6. Manage the District in an effective, efficient, and fiscally responsible manner.
1.05.030 Goals:
4.5 Provide effective and efficient maintenance and replacement programs.
FISCAL IMPACT:
A separate work order is created for each developer project. Inspection of developer
constructed facilities is billed against the appropriate work order and the costs are paid
by the developer. The Water Department generates an estimate of the level of inspection
effort required for a given project and collects a deposit for those costs at the time the
development agreement is signed. If the total inspection costs exceed the initial deposit,
the developer is billed for these additional costs. It the initial deposit is not exceeded, the
remaining funds are returned to the developer.When an outside firm is used to perform
the construction inspection, those costs are billed against the deposit collected from the
developer. There is a minimal financial impact to the District associated with accounting
and contract management.
The process for District-funded projects is similar in that separate work orders have been
established for the two projects and the inspection time spent on each project will be
allocated to the appropriate internal work order.
About $37,000 was spent on outside inspection of developer funded projects in 2020. As
noted above, this cost was recovered from the developers.
Total construction inspection costs covering both District-funded and developer funded
projects are estimated at $150,000 for the summer of 2021. There is some uncertainty
associated with this estimate and a 10 percent change order allowance is recommended.
There are sufficient funds within the Board Approved Water Utility Operating Budget to
cover the cost of inspection for the District-funded projects.