HomeMy WebLinkAbout13 Renew Contract for Geotechnical TestingAGENDA ITEM #13
Page 1 of 2
MEETING DATE:April 7, 2021
TO:Board of Directors
FROM:Neil Kaufman
SUBJECT:Renewal of a Contract to Perform Geotechnical Testing Services
APPROVED BY______________________________
Brian C. Wright, Interim General Manager
RECOMMENDATION:
Authorize the Interim General Manager to renew the contract with NV5 to perform
geotechnical testing services for 2021 in an amount not to exceed $75,000.
BACKGROUND:
Geotechnical Testing involves testing of materials such as soil, asphalt and concrete
associated with the District’s construction projects. The District has a need for such
testing associated with its construction projects and District personnel are not trained nor
equipped to perform the necessary testing work.
In April 2020, the District issued a Request for Proposals (RFP) for Geotechnical Testing
Services associated with the planned construction for the summer of 2020.Six proposals
were received in response to the RFP. A staff committee reviewed the proposals and a
recommendation was presented and approved by the Board to execute a contract with NV5
at the May 20,2020 Board meeting.
The District has the need for geotechnical testing associated with three projects for the
summer of 2021:
District Pipeline Replacement -2021
Martiswoods Hydropneumatic Pump Station Replacement Project
Truckee Substation Improvements -2021
The selection of NV5 in April 2020, was performed in accordance with District Code Section
3.08.070. It is current District practice that contracts for professional services such as
geotechnical testing are reviewed on an annual basis and that a contract may be renewed for
Page 2 of 2
at most two additional years after the initial award before the issuance of a new RFP is
required.The work performed by NV5 in 2020 was satisfactory and renewal of the NV5
contract to perform testing during 2021 is being recommended by staff.
The purpose of this contract is to ensure proper construction of District-funded capital
projects in accordance with District Goals 3.4 and 4.5.
3.4. Conduct effective and efficient operations, maintenance, and replacement
programs. (Water Department)
4.5. Provide effective and efficient maintenance and replacement programs.
(Electric Department)
FISCAL IMPACT:
Geotechnical testing is paid on an hourly basis and the hourly cost allocated to the project
for which the work is performed. The estimated cost for geotechnical testing for all three
projects is $60,000. An additional change order allowance of $15,000 is recommended
for a total authorization of $75,000 for 2021.
Work on the District Pipeline Replacement -2021 and Martiswoods Hydropneumatic
Pump Station projects will be funded by the Water Utility.Work on the Truckee Substation
Improvements –2021 project will be funded by the Electric Utility.Sufficient funds exist in
the Board approved FY21 operating budgets for each of the three projects to cover the
cost of the geotechnical testing work.
It should be noted that the District Pipeline Replacement –2021 project was not identified
by name in the Water 2021 Capital budget adopted by the Board in the fall of 2019. As
discussed in the agendized District Pipeline Replacement-2021 project approval (Item
#15), sufficient funds are available in the Board approved FY21 Water Utility Operating
Budget to cover the cost of this project.