HomeMy WebLinkAbout11 NOC Donner Lake SubstationCONSENT To: From: Date: Board of Directors Sanna Schlosser January 20, 2016 Agenda Item # 11 TRUCKEE DONNER Public Utility District ------------------ Subject: Consideration of Resolution 2016-02, Accepting Final Completion for the Donner Lake Substation Rebuild Project 1. WHY THIS MATTER IS BEFORE THE BOARD The Donner Lake Substation Rebuild-2015 Project is complete. A resolution accepting the project as complete requires Board approval. 2. HISTORY This project involved rebuilding the Donner Lake Substation to improve reliability, increase capacity, and ensure compliance with current code requirements. The Board awarded the engineering contract in July 2014 and equipment purchase contracts in December 2014. The construction contract was awarded to PAR Electrical Contractors on June 3, 2015, in an amount not to exceed $855,743 . 3. NEW INFORMATION During the course of the project, three change orders were reviewed by staff and approved by the General Manager . In addition to these changes ,. additional work rock work was required as shown in Attachment 1. These changes totaled $53,577.97, and did not exceed the $77,795 change order allowance established by the Board of Directors. The items covered by these change orders generally fell into the following categories: • Additional work not included in the original contract: During the course of the project, it was necessary to perform some additional work that was not covered by the original bid items. This work included equipment modifications, and installation of a larger service cable than originally specified . Additionally, this work included necessary transformer anchoring at Martis Valley Substation. This work totalled $22,517.34. • Field conditions differing from the contract drawings: There were several locations where the field conditions differed from the contract drawings. The work to rectify these conditions included additional drainage work, reinfocement of the spill containment wall, and additional rock excavation. This work totalled $31,060.63 . Page 1 of 5 I he U1stnct statt pertormed a t1na1 walkthrough on the project, and the work pertormed is considered complete and should be accepted by the District. Also attached is draft Resolution 2016-02 (Attachment 2) accepting the project and directing that a Notice of Completion be filed. 4. FISCAL IMPACT The Electric Facility Fee Fund will be used for this project until depleted. The remaining costs will then be funded from the Electric General Fund. 5. RECOMMENDATION Adopt Resolution 2016-02 accepting the Donner Lake Substation Rebuild -2015 Project as complete and authorize the filing of the Notice of Completion. Stephen Hollabaugh Assistant General Manager /YJ. /J .. ~--- Michael D. Holley General Manager Page 2 of 5 Bid It 1 2 3 IL 'ption Mobilization Rock Excavation Analysis of Bid Quantities vs. Actual Quantities Con structed Donner Lake Sub station Rebuild Project -2015 Contractor : PAR Electrical Contractors, Inc. Bid Amounts Qty Units Unit Price Subtotal Qty 1 LS $ 26,373.00 $ 26,373 .00 1 2 HRS $ 1,525 .00 $ 3,050 .00 12 All other work as de scrib ed by Contract 1 LS $ 748 ,525.00 $ 748 ,525 .00 1 I Total I $ 777,948.00 I Actual Amounts Units Unit Pric e Subtotal Is $ 26,373 .00 $ 26 ,373.00 FT $ 1,525 .00 $ 18,300 .00 LS $ 748,525 .00 $ 748 ,525 .00 Total $ 793,198 .00 Page 3 of 5 Resolution No. 2016 -02 TRUCKEE DONNER Public Utility District AUTHORIZING THE ACCEPTANCE OF THE DONNER LAKE SUBSTATION REBUILD· 2015 PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to undertake the Donner Lake Substation Rebuild -2015 Project and WHEREAS, PAR Electrical Contractors, Inc. was selected by the District to perform the work; and WHEREAS, PAR Electrical Contractors, Inc. has completed all of the work included in the Project; and WHEREAS, The District's Electrical Engineer, Sanna Schlosser, now certifies the completion of the project; and WHEREAS, the District's Electric Utility Manager, Stephen Hollabaugh, has recommended that the work be accepted by the District; NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows: 1. That the District hereby accepts the Donner Lake Substation Rebuild -2015 Project as complete. 2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a copy of which is attached hereto . 3 . That 35 days following the filing of the Notice of Completion, the monies retained from the contractor payments be released to the contractor if no claims have been made to the District by material suppliers, laborers, or sub-contractors . PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the twentieth day of January 2016 by the following roll call vote: AYES: NOES: ABSTAIN: ABSENT : TRUCKEE DONNER PUBLIC UTILITY DISTRICT By~~~~~~~~~~~~~- Bob Ellis, President of the Board ATTEST: Michael D. Holley, Clerk of the Board Page 4 of 5 RECORDING REQUESTED BY : Truckee Donner Public Utility District WHEN RECORDED, RETURN TO: TRUCKEE DONNER PUBLIC UTILITY DISTRICT Shanna D. Kuhlemier, Deputy District Clerk 11570 Donner Pass Road Truckee, CA 96161 THE UNDERSIGNED DECLARES DOCUMENTARY TRANSFER TAX -NONE NOTIC E OF COMPLETION NOTICE IS HEREBY GIVEN: 1. That the name and address of the public entity for whom the improvement project was done, as owner thereof, is the Truckee Donner Public Utility District, 11570 Donner Pass Road, Truckee, CA 96161 . 2. Nature of interest or estate of owner: benefic ial interest of a public utility easement for installation of water facilities. 3. That on January 20 , 2016 the hereinafter described improvements were accepted as complete pu rsuant to Resolution 2016-02 of the Truckee Donner Public Utility District, the awarding authority. 4. That the subject improvements of the Notice are generally described and identified as follows : Donner Lake Substation Rebuild -2015 Project. 5 . That the name and address of the contractor for such project was: PAR Electrical Contractors, 1465 West 4th Street , Reno, NV 89503 Dated : January 20 , 2016 I certify under penalty of perjury under the laws of the State of California that the foregoing is true and correct. TRUCKEE DONNER PUBLIC UTILITY DISTRICT Michael D. Holley, General Manager MAIL TAX STATEMENTS TO: SAME AS ABOVE Legal References : CC -3093 ,CCP-2003 (oath), 2015.5 (unsworn statement) Page 5 of 5