HomeMy WebLinkAbout10 Prosser Village Well Change OrderCONSENT To: Board of Directors From: Brian Wright Date: April 06, 2016 Subject: Consideration for Change Order No.1 for the Prosser Village Well Maintenance 2016 project 1. WHY THIS MATTER IS BEFORE THE BOARD District Code requires that all procurements in excess of $15,000 recieve Board approval. 2. HISTORY In December, 2015 the District publicly advertised request for bids for the Prosser Village Well Maintenance 2016 project. At the January 20, 2015 meeting the Board awarded a contract to Carson Pump, LLC. in the amount of $27,100, plus a $15,000 change order allowance for a total amount not to exceed $42,1000 The scope of work for this project include removal and reinstallation of the 250hp motor, 450 of line shaft and inspection of 8" Flowserve pump assembly. Additionally, the contractor shall conduct video inspection of the well column, perform an axial alignment survey, and perform shop maintenanc and inspection to the pump and 3. NEW INFORMATION During the removal and inspection of the Prosser Village Well pump and motor assembly it has been determined that the well shaft and pump bowl assembly have experienced signifcant wear damage and require replacement. The cost of replacing a section of the well shaft, bearings, reatiners and pump bowl assembly is $18,637 and exceeds the Board approved change order allowance of $15,000. Approval for an additional change order allownace in the amount of $6,000 will be required to pocure the necessary materials, labor and taxes. 4. FISCAL IMPACT Sufficient funds for this change order allownace are available in the FY16 Water General Fund 5. RECOMMENDATION Authorize an additional change order allowance for the Prosser Village Well Maintenance 2016 Project in the amount of $6,000, for additional maintenance work negotiated by the General Manager, for a total project amount not to exceed $48,100. Michael D. Holley General Manager /Water Utility Manager