HomeMy WebLinkAbout16 2016 Purchase Power Load and Budget ForecastAgenda Item #16 To: Board of Directors From: Stephen Hollabaugh Date: March 1, 2017 Subject: Discussion of 2016 Purchase Power Load, Resources, Peaks, and Comparison to 2016 Budget Forecast 1. WHY THIS MATTER IS BEFORE THE BOARD This workshop is to review the District's actual versus budgeted purchase power costs and energy consumption for 2016. 2. HISTORY On September 16, 2015 the workshop "FY16 and FY17 Budget: Purchase Power Plan" was presented to the Board. This workshop covered the following topics: Mission Statement and Objectives, Renewable Portfolio Standard Target, Conservation as First Resource, Diversified Power Supply Plan, Future Renewable Resources, CARB Cap and Trade, Proposed Resources for 2016 & 2017, Risk to Budget Analysis and 2016 & 2017 Forecast Costs. The Purchase Power Plan 2016 and 2017 Budget was approved by the Board on November 18, 2015. The 2016 Purchase Power Plan budgeted amounts, based on a forecasted energy purchase of 163,778 MWh, are shown in the following table: Cost Component Budget $per MWh Total Energy Supply -Various $11,200,896 $68.39 Transmission Wheeling - SPPC $ 927,156 $ 5.66 Totals $12,5955115 $74.05 Historical data for 2016 and prior years to 2006 is included for reference on Attachment A. 3. NEW INFORMATION Summary budgeted versus actual amounts for 2016 are shown in the following table: Description Budget Actual Total Energy Purchases $12,128,052 $11,697,981 Total Energy Consumption, MWh 1631778 1611084 Purchase Cost per MWh $74.05 $72.62 • The total purchased power costs were 3.5% less than budgeted and total energy consumption was about 1.6% less than forecasted during 2016. The two major factors that affect the total purchased power cost are resource cost and energy consumption by our customers. All these factors helped to reduce the District's actual purchased energy cost to $72.62 per MWh, about 1.9% under budget. Energy costs and consumption by month are graphically depicted below. Budgeted versus actual power $13,000,000 $12,000,000 $11,000,000 $10,000,000 $9,000,000 $8,000,000 $7,000,000 $6,000,000 $5,000,000 rchase cost for 2016 is shown in graph below: Budget Actual _ Misc Costs: Transmission ■ Total Energy Supply Budgeted versus actual monthly MWh consumption for 2016 is shown in graph below: 1 111 111 111 ' The Monthly Peak MW for 2008 through 2016 is shown in the graph below: Monthly •- ak MW 11: thru 2016 0* 1 2016 3080 2015 1 4 1 20.0 w, g r0 2012 080 w w s 1 1 Peak MW 1 5 0 Peak MW r -E 2008 Peak MW 1 1 OCTJAN FEB MAR APR MAY JUNE JULY AUG SEPT • The District experienced its 2016 peak load of 37.2 MW in January. The summer months have a constant load with a small peak in July. History of Actual vs. Budget vs. Sales (MWh) Total Bulk Power Actual vs Budget vs Sales MWh 170,000 165,000 160,000 155,000 } 150,1000 s 145,000 ♦Actual MWh 5; 140,000 Budget MWh 135,000 0 sales MWh 130,000 125,000 0 ° 120,000 Annual Graph of Resources used for 2016 2016 RESOURCE MIX T Heat Recovery, 5% Small Hydro, 6% Landfill Gas, 15% Unspecified Pool, 38% Wind, 28% 1, " Natural Gas, 8% Resources (MWh) by Year 2014 — 2025 Resources (MWh) By Year 2014 - 2025 with Veyo Heat Recovery 2017 & 2017-2022 Market Purchase 180,000 160,000 140,000 120, 000 60,000 40,000 20,000 ,y0 ,LO ,LO ,LO ,y0 ,LO ,LO ,LO ,LO ,yO ,LO ,LO ■ Natural Gas ® U nspecified Pool Heat Recovery Small Hydro ■ Landfill Gas ■Wind Open Position -DAMPS Pool /Mkt Veyo Heat Recovery 2017 se Butte Wind -Wind Hor Nebo Power Plant -Natural Gas ■ Pleasant Valley -Wind ■ Fallon Exchange for Stampede ■ Stampede - Small Hydro Trans Jordan - Land Fill Gas ■ Five-year Market 2017-22 (New) ■ Five-year Market 2012-17 (Exist) On December 7, 2011 the Board approved the Renewable Energy Resources Procurement Plan per Senate bill U2. This plan defines the minimum required percentage of renewables per compliance period based on total retail energy sales. Compliance periods and percent renewables are as follows: Period 1 - January 1, 2011 through December 31, 2013 - 20% Period 2 - January 1, 2014 through December 31, 2016 - 25% Period 3 - January 1, 2017 through December 31, 2020 - 33% Section 3201 (bb) of the CEC regulations define retail sales as: "Sale of electricity by a PUD to end -use -customers and their tenants, measured in MWh. This does not include energy consumption by a POU, electricity used by a POU for water pumping, or electricity produced for onsite consumption (self -generation)." Therefore the retail sales for this calculation is equal to 151,527-7,021462=144,044 MWh The District's estimated renewable energy portfolio performance for 2016 is shown in the table below: Eligible Renewables (CPUC Small Hydro Landfill Gas Wind Heat Recovery (w/REC's) Totals MWh REC's 2021 26,088 47,207 7,259 82,575 Sales 1.5% 18.1% 32.8% 5.0% 57.4 % 4. FISCAL IMPACT Detailed budgeted versus actual amounts for 2016 are shown in the following table: Summary 2016 Budget vs Actual Power Purchases, MWh Budget Actual Total Energy Purchase, MWh 163,778 165,866 Percent Difference, Actual vs. Budget -1.6% Power Purchase Costs Total Energy Supply - UAMPS, WAPA, etc Transmission - NV Energy Scheduling - NCPA WAPA cost/(credit) Misc Costs: WECC, WREGIS, etc. Budget $11,200,896 $927,156 $0 $0 $0 Actual , $11,064744 $515,725 $0 $0 $40,492 Total Power Purchase Cost $ 12,128,052 $11,697,981 $ Over/(Under) Budget $ (430,070) Percent Difference, Actual vs. Budget -3.5% Purchase Cost per MWh $74.05 $72.62 Percent Difference, Actual vs. Budget -1.9% Peak Load Information Budget Actual District Peak Load, MW 36.0 37.2 Percent Difference, Actual vs. Budget 3.4% 5. RECOMMENDAiI®N Receive and comment on this report. Stephen Hollabaugh Assistant General Manager Michael ®. Holley General Manager