ACTION ITEM #9 Phase 4Reliability Improvement ProjectFinal Completion of the SCADA Phase 4Reliability Improvement ProjectFinal Completion of the SCADA October 18, 2017
Final Completion of SCADA Reliability Phase 4 20158facilitiesAncillary SCADA, 1 electric and 6 water320144and 4 water facilitiesDistrict office220115District office, 2 electric and 2
water facilities1CompletedFacilities ServedPhase 17 facilities served by prior phases•communications capabilities to District facilitiesSCADA Reliability Improvement Project provides
up to date •BACKGROUND / HISTORY Final Completion of SCADA Reliability Phase 4
Final Completion of SCADA Reliability Phase 4 Total authorization not to exceed $565,951•10 percent change order allowance was established•Original bid price was $514,401•District facilitiesOriginal
design extended communication connections to six •in July 2016Construction contract awarded to Curtis and Sons Construction Inc. •BACKGROUND / HISTORY Final Completion of SCADA Reliability
Phase 4
NEW INFORMATION Terminations at two additional District facilities (8 total)•attachment license from Liberty Utilitiesrouting one segment of project due to inability to obtain overhead
-Re•Differing field conditions•Change in splice locations•4 change order requests were received and approved totaling $58,258•Construction is Complete•Final Completion of SCADA Reliability
Phase 4Final Completion of SCADA Reliability Phase 4
NEW INFORMATION for fiber optic cableto actuals bid quantity Reconciliation of•Reduced splice locations•$23,977 credit to the District•Reconciliation of bid vs. actual constructed quantities•Final
Completion of SCADA Reliability Phase 4Final Completion of SCADA Reliability Phase 4
FISCAL IMPACT Did not exceed total authorization of $565,951•Final contract price is $548,761.97•Bid price from Curtis and Sons Construction, Inc. was $514,501•Final Completion of SCADA
Reliability Phase 4Final Completion of SCADA Reliability Phase 4
RECOMMENDATION Notice of CompletionImprovement Project Phase 4 as complete and authorize staff to file a 13 accepting the SCADA Reliability -Adopt Resolution 2017•Final Completion of
SCADA Reliability Phase 4Final Completion of SCADA Reliability Phase 4