TRUCKEE DONNER
Public Utility District
Memorandum
To: Board of Directors
From: Ed Taylor
Date: August 10, 2007
Subject: Bid Awards for the Fiber Board Production Well and Pump Development
&Testing Program
1. WHY THIS MATTER IS BEFORE THE BOARD
The Board has to approve the awarding of the contracts for the Fiber Board Production
Well and Pump Development &Testing Program.
2. HISTORY
The Board previously authorized staff to advertise for, accept, and open the Prosser
Village Production Well Project and Pump Development&Testing Program with bid
opening dates of August 10, 2007.
3. NEW INFORMATION
On August 10, 2007, No Bids were received.
Perspective bidders indicated that equipment availability was the reason that they did
not submit a bid for this project.
4. RECOMMENDATION
Staff will bring the Fiber Board Well Project back for the Board to request authorizion to
rebid in January or February of 2008.