Loading...
HomeMy WebLinkAbout12 C District Pipeline Contract C Agenda Item # 12 C TRUCKEE DONNER Public Utility District i ACTION To: Board of Directors From: Neil Kaufman Date: March 4, 2009 Subject: Award of the District Pipeline Replacement—2009 — Contract C 1. WHY THIS MATTER IS BEFORE THE BOARD Board approval is required for expenditures in excess of$15,000. 2. HISTORY In 2005 and 2006, the Water Department made Board presentations regarding the condition of existing water pipelines and the need to pursue a pipeline replacement program. The District subsequently issued a COP in 2006 and dedicated a portion of those funds for the pipeline replacement program. Pipeline construction projects have been undertaken during 2006, 2007 and 2008 as part of this program. The planned construction for 2009 entails about 18,000 feet of pipeline and has been broken into three separate construction contracts. • Contract A— Hillside Drive, Solvang Way, Staghorn Road & St. Croix Way • Contract B — Oslo Drive, Sierra Glen Way, Skiview Loop, Snowpeak Way&Tyrol Road • Contract C — Chamonix Road, Donner View Tank site, Innsbruck Tank site, Rhineland Avenue, Skislope Way, &West Reed Avenue 3. NEW INFORMATION The bid opening for Contract C was held at 2:00 PM on February 24, 2009. Nineteen bids were received. A summary of the bids is given below: Bidder Location Amount Wunschel &Sons Placerville, CA $654,240.00 Cruz Excavating Incline Village, NV $656,993.00 AM-X Construction Truckee, CA $662,080.50 Herback General Engineering Minden, NV $667,010.00 -Heavy Equipment Truckee, CA $687,508.00 -Aspen Developers Truckee, CA $696,770.00 WES Construction Reno, NV $701,055.61 Mary McQueary Excavating Carson City, NV $732,063.78 Suter Construction Reno, NV $736,050.00 Teichert Construction Roseville, CA $759,182.00 Campbell Construction Sparks, NV $782,491.00 Lon o Inc. pRocklin- Ci , CA $838,511.00 Loran Brothers , CA $879,884.00 West Valle Construction CA $898,221.00 Koch Excavatin Valley. CA $912,466.21 Hansen Brothers Grass Valley, CA $975,131.60 Q& D Construction Sparks, NV $986,629.00 Pacific Underground San Jose, CA $1,167,650.00 Delta Excavating Antioch, CA $1,195,252.60 At the time of the bid opening, the apparent low bidder was Herback General Engineering with a bid of $647,198.00. However, upon reviewing this bid, two mathematical errors were identified. After correcting these errors using the procedures described in the bid documents, the bid total from Herback General Engineering was revised to $667,010.00. The bid from Wunschel &Sons was then determined to be responsive and the lowest bid. 4. FISCAL IMPACT The Bid Price for Contract C is $654,240.00. The majority of funding for the construction will be the COP issued in 2006. There is some pipeline upsizing involved in the project that will be funded from Water Department Facility Fees. The project also includes the installation of some electric conduit, electrical vaults and communication pull boxes on Skislope Way that will be paid for by the Electric Department. The proposed breakdown of funding between the COP funds, Facility Fees and the Electric Department is: Funding Source Amount 2006 COP Funds $583,067.82 Water Department Facility Fees $11,956.68 Electric Department Facility Fees $59,215.50 Total $654,240.00 Additional costs will be incurred associated with construction inspection, environmental compliance and geotechnical testing. It is also recommended that the Board of Directors authorize a 10 percent allowance for change orders at this time. 5. RECOMMENDATION: 1) Award the District Pipeline Replacement— 2009— Contract C to Wunschel & Sons in the amount of $654,240.00. 2) Authorize the transfer of $583,067.82 from COP funds to the Water Department General Fund, $11,956.68 from Water Department Facility Fees to the Water Department General Fund and $59,215.50 from the Electric Department General Fund to the Water Department General Fund to cover the cost of the project. 3) Authorize a change order allowance of$65,000 associated with this contract. '/-t Ed qT;ajy'1 r, Water Utility Manager Michael D. Holley, General Manager