HomeMy WebLinkAbout8 Approval of a Coldstream Development Agreement with Teichert ConstructionAgenda Item #8
To:
From:
Date:
Subject:
Board of Directors
Brian Wright
June 03, 2020
Approval of a Coldstream Development Agreement with Teichert
Construction
ACTION
1. WHY THIS MATTER IS BEFORE THE BOARD
Per District Code Section 7.12.030, approval by the Board of Directors is required for
any development agreement where the total value of on-site improvements being
installed by the applicant to be conveyed to the District for ownership, operation and
maintenance exceeds $400,000.
2. HISTORY
When a developer proposes to construct a new project, a development agreement is
necessary when there are facilities that will be constructed by the developer and then
conveyed to the District for ownership, operation and maintenance. The development
agreement is essentially a contract between a developer and the District. It describes
the responsibilities of each party with respect to a particular project. Separate
development agreements are created for the Electric Department and the Water
Department. Items addressed in a development agreement typically include:
Costs and fees;
Dedication of easements where necessary;
Dedication of facilities constructed by the developer;
Insurance;
Indemnification;
Project acceptance; and
Warranty.
The development agreement will normally reference the approved drawings for a
project and the District’s construction standards.
The development agreement process typically takes the following steps:
1) Initial discussions between the developer and the District regarding project
feasibility;
2) Development agreement application;
3) Review and revision of project plans (this may involve multiple rounds of review
& revision);
4) Preparation of development agreement;
Brian Wright Michael D. Holley
Water Utility Director/Assistant GM General Manager
4) Preparation of development agreement;
5) Signing of development agreement and payment of costs and fees;
6) Project construction; and
7) Project acceptance and administrative closeout.
3. NEW INFORMATION
The Coldstream (PC-1) is located at the entrance to Coldstream Canyon on the west
side of Truckee, south of Interstate 80 and just east of the Donner Memorial State
Park. The project involves the construction of up to 300 residential units and 30,000
square feet of mixed use commercial space on land formerly utilized by A.Teichert
and Son, Inc. for the purposes of harvesting aggregate materials.
The Coldstream Specific Plan has been designed by Stonebridge Properties, a
subsidiary of Teichert Land Co. The District has been working with Coldstream
Developers on a development agreement for the construction of water utility
infrastructure associated with Phase 3 of the Coldstream Specific Plan including
residential and mixed use commercial space. Separate development agreements will
be required for future phases of the project.
The water utility infrastructure associated with this development includes necessary
potable water distribution system to serve Phase 3 and the construction of an above
ground steel potable water storage tank (approximately 230,000 gallon capacity) at
the District's Red Mountain Tank site in order to provide adequate potable water
supply and fire protection upon full build-out of the development. Construction cost for
these improvements will exceed $400,000.
4. FISCAL IMPACT
There is no direct fiscal impact to the District associated with this item. The developer
shall be reimbursed for the actual costs for construction of the potable water storage
tank through water facility fees collected by the District from parcels within the
development.
5. RECOMMENDATION
Approve the development agreement and authorize the General Manager to execute
the agreement between Coldstream Developers, LLC and the District for the
Coldstream Development, Phase 3.