HomeMy WebLinkAbout8 Martis Valley Well power supply cables #2AGENDA ITEM #8 Page 1 of 2 MEETING DATE: March 2, 2022 To: Board of Directors FROM: Earl Smith, Water Operations Manager SUBJECT: Consideration to Authorize Procurement of Power Supply Cables for the Emergency Backup Generator at Martis Valley Well. APPROVED BY______________________________ Brian C. Wright, General Manager RECOMMENDATION: Authorize the General Manager to execute a procurement contract with WEDCO Inc. for power supply cables for the emergency backup generator at Martis Valley Well in the amount of $37,629.77, plus a 10% change order allowance for a total not to exceed $41,392.75 + incidentals and sales tax. DISCUSSION: The District’s recently updated 10-year Capital Improvement Plan (CIP) has identified multiple locations in which the placement of emergency back-up generators will significantly enhance the reliability of potable water deliveries to our customers during prolonged power outages. In particular, staff has recently prioritized the need for back-up generators to be installed at critical groundwater well facilities due to the adoption of Public Safety Outage Management (PSOM) programs in 2019, and recent updates to the program earlier this summer. One of the key well facilities identified by staff to be prioritized for the procurement of an emergency back-up generation is Martis Valley Well. This prioritization was based upon well production levels and characteristics of the well location, such as ease of access for fueling and maintenance. Page 2 of 2 In March of 2021 the District was awarded grant funds through California Office of Emergency Services (Cal OES) in the amount of $300,000 to procure an emergency backup generator for the Martis Valley Well. To qualify for funding the District must use the awarded funds no later than December 31, 2022. At the July 21, 2021 Board Meeting, the Board approved the procurement of an emergency backup generator. The new emergency backup generator will require a power supply cable system for the operation at Martis Valley Well facility. On January 20, 2022 the District completed its competitive bidding process and received no bids on the power supply cable system. On February 2, 2022 the Board authorized the General Manager to dispense with competitive bidding and authorize staff to negotiate directly with other vendors that can supply this equipment. In February 2022, staff reached out to several vendors supplying electrical power supply cabling seeking pricing and delivery timelines in alignment with District needs. The District received one quote from WEDCO Inc. in the amount of $37,629.77. After review of terms with the vendor, staff has determined the power cabling specifications and delivery timelines will meet the District’s needs. FISCAL IMPACT: This procurement was not included in the Board approved Budget. However, the District has received CalOES grant funding in the amount of $300,000 for the procurement and installation of the Martis Valley Well emergency back-up generator including associated equipment and materials. The procurement of the new generator cables will be funded by these grant monies. ATTACHMENTS: Attachment 1: WEDCO Inc. Quote