HomeMy WebLinkAbout9, SCADA Conduit and Vault Project
Consent Item# 9 April 6, 2011 Contract for the SCADA Conduit Consideration of the Award of a
Award of a Contract for the 2 March 28, 2011Bid period began on February 28 and ended on •Glenshire Drive Well–6170 Tank–Martis Valley Substation–Truckee Substation–conduit system to
improve overall SCADA reliability to:Subsequent to this project, the District plans to use this •and make the system continuousThis project will close several gaps in the conduit system
•electric system line extensions since 2000The District has been installing communication conduit with •Background / History SCADA Conduit and Vault Project
New Information No$149,907&ExcavationS&R Snow Removal Yes$117,117X-AMYes$94,500Longo, Inc.Yes$82,470Dale BurtYes$73,004Aspen DevelopersNo$46,950Heavy EquipmentResponsiveAmountBidder
SCADA Conduit and Vault ProjectAward of a Contract for the 3 District’s estimate was $64,000•Six bids were received:•The bid opening was held at 2:00PM on March 28•
Fiscal Impact SCADA Conduit and Vault ProjectAward of a Contract for the 4 Electric and Water capital budgetsSufficient monies exist within the approved FY11 •
Recommendation SCADA Conduit and Vault ProjectAward of a Contract for the 5 bid this project-Direct staff to re•the DistrictReject all bids as not being in the best interests of •