HomeMy WebLinkAbout14 Power Point Final Completion of SCADA Conduit and Vault
Action Item # 14 September 7, 2011 Conduit and Vault ProjectChange Order for SCADA Completion and Closeout Resolution Accepting Final
Final Completion for SCADA Conduit and 2 allowanceContract price $64,750 + 10% ($6,475) change order –2011 Construction contract awarded to Heavy Equipment in May, •electric and water
facilitiesProject to improve communication reliability to remote •Background / HistoryVault Project
New InformationVault ProjectFinal Completion for SCADA Conduit and 3 Project is complete•Cost overrun due to changes between bid and actual quantities–Exceeded change order allowance
by $5,622–Total for all change orders was $12,097•Field conditions differed from contract drawings–Two change orders required•
Fiscal Impact$76,847.00TotalCapital Projects$12,679.76AdministrationProjectsCapital$32,083.62Waterand ProjectsCapital Reserves$32,083.62ElectricSourceCostDepartment Vault ProjectFinal
Completion for SCADA Conduit and 4 Sufficient funds exist in the FY11 budget•Project funded as follows:•
RecommendationVault ProjectFinal Completion for SCADA Conduit and 5 Notice of Completion2011 as complete and authorize the filing of the -ProjectAdopt a resolution accepting the SCADA
Conduit and Vault •2011 in the amount of $5,622-Conduit and Vault ProjectAuthorize Contract Change Order No. 2 to the SCADA •