Memorandum
To: Board of Directors
From: Neil Kaufman
Date: November 8, 2006
Subject: Award of a Contract for CEQA Preparation Associated with the Alder Drive
Pump Station Project
1. Why this matter is before the board:
Board Authorization is required to award a contract for consulting services.
2. History:
The 2004 Water Master Plan identified a planned pump station on the northwest corner of Alder
Drive and Comstock Drive. This location is shown on Figure 1. The purpose of this pump
station is to pump water into the Prosser Heights area from Gray's Crossing and the 6170
Pressure Zone. The District acquired an easement from East-West Partners at this location as
part of the Gray's Crossing project.
On September 1, 2006, there were two wells serving the Prosser Heights and Prosser Lakeview
area (Prosser Heights Well and Prosser Annex Well). On September 27, the Prosser Annex
Well suffered a major failure of the pumping equipment. The well is currently out of service
leaving the Prosser Heights Well as the only water source for this area.
Over the past five years, there has been a significant deterioration in production from the
Prosser Annex Well. The well production has dropped from about 470 gpm in 2001 to about
200 gpm at the time of the pump failure. Property owners with private wells in the Sugar Pine
Estates and Alder Hill areas have reported similar reductions in well production. District records
show that the groundwater table in this area has been dropping over the past few years.
However, no studies have been performed to evaluate the transmissivity, recharge and specific
capacity in this area.
As noted above the Prosser Heights Well is currently the only source feeding the Prosser
Heights and Prosser Lakeview areas. A second supply source is needed to ensure that service
can be provided in the event of a failure at the Prosser Heights Well. Two options exist to
address this issue:
1) Repair and/or replace the pumping equipment at the Prosser Annex Well
2) Construct the planned Alder Drive Pump Station identified in the Water Master
Plan
Re-equipping the Prosser Annex Well will be less expensive in the short term. However, the
long term viability of the Prosser Annex Well is uncertain given the current trend of groundwater
levels at that location. The Water Department Staff recommends that the Alder Drive Pump
Station be constructed. It will draw water from more reliable sources and its capacity would be
needed in the future anyway, as additional houses are built in the Prosser Heights and Prosser
Lakeview areas
3. New information:
At the beginning of October, I toured the project site with Glenn Merron of Inland Ecosystems
and requested that he submit a proposal to prepare a CEQA Initial study for this project. The
proposal is attached:
The current project schedule is given below:
November 15, 2006—Board Approval of Inland Ecosystems Contract
December 20, 2006—Board Approval of CEQA Initial Study
January 17, 2007—Public Hearing on CEQA Initial Study
February 7, 2007—Adoption of Final CEQA Document
May 2007—Begin Construction
4. Recommendation:
The Board of Directors accept the proposal submitted by Inland Ecosystems and award a
contract for preparation of the CEQA Initial Study associated with the Alder Drive Pump
Station project in an amount not to exceed $4,796.00.
Attachments:
Figure 1
Proposal from Inland Ecosystems
ALDER DRIVE
PUMP STATION SITE
f TRUCKEE DONNER Alder Drive Pump Station
Public Utility District Site Location
INLAND ECOSYSTEMS
- 1000 Bible Way,Suite 16
Reno,NV. 89502
INLAND Phone: (775)786-3223 Fax: (775)786-3229
ECOSYSTEMS Email: amerrni@inlandeemistems.com
Mr. Neil Kaufman October 11, 2006
Truckee Donner Public Utility District
11570 Donner Pass Road
Truckee, CA 96160
Subject: Proposal to Prepare a California Environmental Quality Act Initial
Study/Mitigated Negative Declaration for the Alder Drive Pump Station
Dear Mr. Kaufman:
Inland Ecosystems is pleased to submit this scope of work and cost estimate to assist the
Truckee Donner Public Utility District (District) with preparation and circulation of a
California Environmental Quality Act (CEQA) Initial Study and Proposed Mitigated Negative
Declaration for the Alder Drive Pump Station.
This proposal includes the environmental and cultural resource tasks associated with
construction of the well. Mark Chainey will conduct the Biological Resources surveys. Dr.
Susan Lindstrom will carry out the Cultural Resources surveys. I will coordinate all
components of the project and complete the CEQA document.
Our cost estimate for the survey work and preparation of the environmental document is a
"not to exceed" contract amount of $4,796. Table 1 provides a breakdown of all estimated
costs associated with this proposal. According to Susan Lindstrom's voice mail, she is away
until October 25 and is not able to check phone messages (she must be out of the country). I
know her billing rate is $125 an hour. For Inland's budget I estimated her time at 10 hours,
which should be sufficient for her research, field work, coordination and reporting. I also
gauged her level of effort from previous work associated with conducting the field work and
reporting at the District's Corp site with Kathy Neus.
Our goal is to ensure that the District is provided with an exceptionally high quality of
environmental and cultural documentation to ensure that the project is carried out with the
least amount of environmental disturbance.
Should you have any questions please contact me at (775) 786-3223. We look forward to
assisting the District with this important project.
Sincerely,
Glenn S. Merron, Ph.D.
t
WORK AUTHORIZATION ORDER
October 11, 2006
This Work Authorization Order confirms the agreement between the Truckee Donner
Public Utility District ("District") and Inland Ecosystems ("Contractor"), that Company is
engaging Contractor to provide certain services (the "Work," as further defined below). This
Work Authorization Order is being provided in accordance with the Scope of Services
described below.
(i) Description of the Work
TASK 1: Conduct special-status plant, bird, and mammal survey in the area potentially
affected by the proposed action. A target list of potential sensitive plant species will be
identified using data collected from the California Natural Diversity Database (CNDDB)
and the USFWS 7.5-minute quadrangle database. A habitat characterization of the project
site and adjacent area will be prepared.
TASK 2: Conduct a cultural resources Record Search through the North Central
Information Center of the California Historical Resources Information System including
an archaeological site assessment by a registered professional archeologist. The
California Native American Heritage Commission will be contacted for the presence of
any Sacred Lands. Consultation with other Native American groups will be completed.
TASK 3: Prepare California Environmental Quality Act (CEQA) Initial Study/Proposed
Mitigated Negative Declaration for the Alder Drive Pump Station.
(ii) Schedule, Completion Date (period for performance of the Work, including the
required completion date, if any, and an estimated progress schedule for the Work showing
dates for commencement and completion of each of the various subdivisions of Work):
TASK 1: Completion date—October 20, 2006
TASK 2: Completion date - November 10, 2006
TASK 3: Completion date—December 22, 2006
(iii) Compensation,Invoicing and Payment:
a. Fee. The fee for Work performed by Contractor pursuant to this Work Authorization
Order shall be on a"Time and Materials"basis, not-to-exceed $4,796.
b. Invoicing and Payment. Consultant shall submit to Company an invoice within
seven (7) days after the end of each month on which Work is performed by Contractor
hereunder. Payment is due within thirty(30) days of receipt of each invoice.
2
(iv) Other:
Tasks, costs and schedules described herein are subject to unforeseen changes in scope and
schedule.
ACCEPTED:
Truckee Donner Public Utility District Inland Ecosystems, Inc.
By: By:
Title: Title:
Date:
Date:
3
TABLE 1. Estimated Costs for Alder Drive Pump Station.
Estimate of hours by task TASK 2 TASK 3 TOTAL
TASK 1
Personnel: 2 2 24 28
G.Merron 10 10
S.Lindstrom 8
M.Chainey 8
10 12 48 46
TOTAL HOURS 46
RATE $2,464
112
G.Merron $88 $176 $176 $2, $1,250
$1,250
S.Lindstrom $125 $0 $552
M.Chainey $69 $552
TOTAL COST
$728 $1,426 $2,112 $4,266
OTHER DIRECT COSTS
TASK 1 TASK 2 TASK 3 TOTAL
$125
MILEAGE 0.35/mile $125 25 $25
$
COPIES $30
Phone $10 $10 $10 $350
Cultural Record Search $3 $530
TOTAL $135 $360 $35
TOTAL COSTS
$863 $1,786 $2,147 $4,796
TASK 1 Biological Resources Survey
TASK 2 Cultural Resources Survey
TASK 3 Prepare CEQA Initial Study/Proposed Mitigated Negative Declaration
r
i
S