Loading...
HomeMy WebLinkAbout8 Notice of Completion 2015 Pipeline Projectenda Item # CONSENT To: Board of Directors From: Neil Kaufman Date: November 04, 2015 Subject: Final Completion of the District Pipeline Replacement 2015 Project 1. WHY THIS MATTER IS BEFORE THE BOARD The District Pipeline Replacement - 2015 project is complete. A resolution accepting the project as complete requires Board approval. 2. HISTORY In April 2015, the Board awarded the construction contract for the District Pipeline Replacement - 2015 project to AM-X Construction & Excavation (AMX) of Truckee, California. The project involved replacement of about 4,900 feet of pipeline in three segments along Northwoods Boulevard in Truckee. The project also included installation of about 7,850 feet of fiber optic inner duct. AMX began work in June and completed the construction at the end of October. The original bid price was $1,478,273.75. At the time of award, the Board also established a 10 percent change order allowance for a total for a total authorization not to exceed $1,626,000. 3. NEW INFORMATION During the course of the project, 15 change order requests were submitted and reviewed by staff. After review and discussion, the District and AMX agreed on a total of $25,238.22 for these issues. This amount did not exceed the $147,726.25 change order allowance established by the Board of Directors. The items generally fell under the following categories: • Additional work such as installation of fire hydrant extensions and AC dike • Repair of water leaks • Unmarked or mis-marked utilities There was one item that resulted in a credit to the District. The contract is based on a unit price bid. Attachment 1 shows the differences between bid totals and the amounts actually constructed. This analysis results in a $47,597.29 credit to the District. Page 1 of 5 In mid -October, District staff performed a final walkthrough on the project. The work performed is complete and should be accepted by the District. Attached is a draft resolution (Attachment 2) accepting the project and directing that a Notice of Completion be filed. !11111126W-11aIIT, 1:7_1;O1 The original bid price was $1,478,273.75. Once adjustments are made for the items described above, the final contract price is $1,455,914.68. As discussed at the time of award, the anticipated funding sources for the project were: Funding Source Amount Electric Department General Fund Water Department Capital Replacement Fund $161,723.75 $1,316,550.00 Total $1,478,273.75 After adjustments for change orders and the reconciliation of bid vs. actual quantities, the final funding for the project is: Funding Source Amount Electric Department General Fund Water Department Capital Replacement Fund $166,139.95 $1,289,774.73 Total $1,455,914.68 5. RECOMMENDATION Adopt resolution 2015-21 accepting the District Pipeline Replacement - 2015 project as complete and authorize the filing of the Notice of Completion. /� , & �' ��- -e _ - Michael D. Holley General Manager / Water Utility Manager Page 2 of 5 Analysis of Bid Quantities vs. Actual Quantities Constructed District Pipeline Replacement - 2015 Contractor: AM-X Construction & Excavation Bid Item Description Bid Amounts Actual Amounts Quantit Units Unit Price Subtotal I Quantity Units I Unit Price Subtotal 1 Mobilization 1 LS $ 30,000.00 $ 30,000.00 1 LS $ 30,000.00 $ 30,000.00 1A 8" Water Main - Station 0+00 to 19+38.55 1,939 FT $ 95.00 $ 184,205.00 1,949 FT $ 95.00 $ 185,155.00 113 8" Water Main - Stations 0+60 and 4+73 125 FT $ 120.00 $ 15,000.00 148 FT $ 120.00 $ 17,760.00 1C 2" PE Water Service Lateral 850 FT $ 65.00 $ 55,250.00 786 FT $ 65.00 $ 51,090.00 1 D Double Water Service (DS) 12 EA $ 2,435.00 $ 29,220.00 10 EA $ 2,435.00 $ 24,350.00 1E Single Water Service (SS) 3 EA $ 2,115.00 $ 6,345.00 3 EA $ 2,115.00 $ 6,345.00 1 F Double Water Service with One Lot Vacant (DSV) 4 EA $ 3,075.00 $ 12,300.00 4 EA $ 3.075.00 $ 12,300.00 1G Double Water Service with Both Lots Vacant (D2V) 1 EA $ 1,490.00 $ 1,490.00 1 EA $ 1,490.00 $ 1,490.00 1H Connect New 2" Lateral to Existing Meter Box 1 EA $ 1,205.00 $ 1,205.00 1 EA $ 1,205.00 $ 1,205.00 11 Connect New 2" Lateral to Existing Lateral 1 EA $ 1,300.00 $ 1,300.00 1 EA $ 1,300.00 $ 1,300.00 1J Fire Hydrant Assembly 4 EA $ 8,360.00 $ 33,440.00 4 EA $ 8,360.00 $ 33,440.00 1 K Connection to Existing 8" Pipe at Station 0+00 1 EA $ 2,615.00 $ 2,615.00 1 EA $ 2,615.00 $ 2,615.00 1L TeeNalve Assembly at Station 0+60 1 EA $ 5,685.00 $ 5,685.00 1 EA $ 5,685.00 $ 5,685.00 1 M Cross/Valve Assembly at Station 4+73 1 EA $ 11,780.00 $ 11,780.00 1 EA $ 11,780.00 $ 11,780.00 1N Connection to Existing 6" Pipe at Station 19+38.55 1 EA $ 2,710.00 $ 2,710.00 1 EA $ 2,710.00 $ 2,710.00 10 Rock Excavation 16 HRS $ 675.00 $ 10,800.00 6 HRS $ 675.00 $ 3,712.50 1 P AC Pavement and Base (trench restoration) 18,000 SF $ 5.00 $ 90,000.00 11,943 SF $ 5.00 $ 59,715.00 1 Q Additional'/i' Thickness of AC Pavement (trench restoration) 18,000 SF $ 0.75 $ 13,500.00 46,784 SF $ 0.75 $ 35,088.00 1R All Other Work Required by the Contract Documents 1 LS $ 29,000.00 $ 29,000.00 1 LS $ 29,000.00 $ 29,000.00 2A 8" Water Main 2,290 FT $ 97.00 $ 222,130.00 2,235 FT $ 97.00 $ 216,795.00 2B 2" PE Water Service Lateral 1,000 FT $ 65.00 $ 65,000.00 980 FT $ 65.00 $ 63,700.00 2C Double Water Service (DS) 21 EA $ 2,435.00 $ 51,135.00 18 EA $ 2,435.00 $ 43,830.00 2D Double Water Service with One Lot Vacant (DSV) 3 EA $ 2,525.00 $ 7,575.00 6 EA $ 2,525.00 $ 15,150.00 2E Connect New 2" Lateral to Existing Meter Box 1 EA $ 1,205.00 $ 1,205.00 1 EA $ 1,205.00 $ 1,205.00 2F Fire Hydrant Assembly 3 EA $ 8,455.00 $ 25,365.00 3 EA $ 8,455.00 $ 25,365.00 2G 1" Air Valve Assembly 1 EA $ 6,820.00 $ 6,820.00 1 EA $ 6,820.00 $ 6,820.00 2H Connection to Existing 8" Pipe at Station 0+00 1 EA $ 2,615.00 $ 2,615.00 1 EA $ 2,615.00 $ 2,615.00 21 TeeNalve/Fire Hydrant Assembly at Station 9+80 1 EA $ 9,930.00 $ 9,930.00 1 EA $ 9,930.00 $ 9,930.00 2J TeeNalve Assembly at Station 20+53 1 EA $ 9,465.00 $ 9,465.00 1 EA $ 9,465.00 $ 9,465.00 2K Connection to Existing 6" Pipe at Station 22+89.36 1 EA $ 3,155.00 $ 3,155.00 1 EA $ 3,155.00 $ 3,155.00 2L Rock Excavation 18 HRS $ 675.00 $ 12,150.00 23 HRS $ 675.00 $ 15,693.75 2M AC Pavement and Base (trench restoration) 25,000 SF $ 4.50 $ 112,500.00 15,549 SF $ 4.50 $ 69,969.38 2N Additional''M." Thickness of AC Pavement (trench restoration) 25,000 SF $ 0.65 $ 16,250.00 15,549 SF $ 0.65 $ 10,106.69 20 All Other Work Required by the Contract Documents 1 LS $ 32,935.00 $ 32,935.00 1 LS $ 32,935.00 $ 32,935.00 3A 8" Water Main 174 FT $ 120.00 $ 20,880.00 174 FT $ 120.00 $ 20,880.00 3B 12" Water Main 515 FT $ 125.00 $ 64,375.00 515 FT $ 125.00 $ 64,375.00 3C 2" PE Water Service Lateral 250 FT $ 70.00 $ 17,500.00 284 FT $ 70.00 $ 19,880.00 3D Double Water Service (DS) 5 EA $ 2,485.00 $ 12,425.00 4 EA $ 2,485.00 $ 9,940.00 3E Double Water Service at 16054 Northwoods Blvd 1 EA $ 3,315.00 $ 3,315.00 1 EA $ 3,315.00 $ 3,315.00 3F Fire Hydrant Assembly 1 EA $ 9,105.00 $ 9,105.00 1 EA $ 9,105.00 $ 9,105.00 3G Connection to Existing 8" Pipe at Station 0+00 1 EA $ 2,515.00 $ 2,515.00 1 EA $ 2,515.00 $ 2,515.00 3H TeeNalve Assembly at Station 1+74 1 EA $ 16,295.00 $ 16,295.00 1 EA $ 16.296.00 $ 16,295.00 31 Connection to Existing 8" Pipe at Station 6+88.21 1 EA $ 2,515.00 $ 2,515.00 1 EA $ 2,515.00 $ 2,515.00 3J Rock Excavation 6 HRS $ 675.00 $ 4,050.00 13 HRS $ 675.00 $ 8,606.25 3K AC Pavement and Base (trench restoration) 6,000 SF $ 5.25 $ 31,500.00 6,171 SF $ 5.25 $ 32,397.75 3L Additional'/2" Thickness of AC Pavement (trench restoration) 6,000 SF $ 0.80 $ 4,800.00 23,184 SF $ 0.80 $ 18,547.20 3M All Other Work Required by the Contract Documents 1 LS $ 13,200.00 $ 13,200.00 1 LS $ 13,200.00 $ 13,200.00 30 Single Water Service (SS) - Use Bid Price from 1 E 0 EA $ 2,115.00 $ - 2 EA $ 2,115.00 $ 4,230.00 4A Innerduct from Station 0+04 to Station 29+49, Offset Right 2,969 FT $ 7.75 $ 23,009.75 2,965 FT $ 7.75 $ 22,978.75 4B Innerductfrom Station 29+49 Offset Right to Station 53+61 2,436 FT $ 7.75 $ 18,879.00 2,423 FT $ 7.75 $ 18,778.25 4C 2" Conduit from Station 0+00 to Station 0+36 1 LS $ 5,900.00 $ 5,900.00 1 LS $ 5,900.00 $ 5,900.00 4D 6" Pipe at Station 6+16 1 LS $ 3,475.00 $ 3,475.00 1 LS $ 3,475.00 $ 3,475.00 4E 6" Pipe at Station 25+35 1 LS $ 3,475.00 $ 3,475.00 1 LS $ 3,475.00 $ 3,475.00 4F Communications Pull Box Assembly at Station 29+49 1 LS $ 5,520.00 $ 5,520.00 1 LS $ 5,520.00 $ 5,520.00 4G 6" Pipe at Station 39+24 1 LS $ 3,415.00 $ 3,415.00 1 LS $ 3,415.00 $ 3,415.00 4H 6" Pipe at Station 44+74 1 LS $ 3,415.00 $ 3,415.00 1 LS $ 3,415.00 $ 3,415.00 41 2" Conduit from Station 53+23 to Station 53+65.73 1 LS $ 5,850.00 $ 5,850.00 1 LS $ 5,850.00 $ 5,850.00 4J Rock Excavation 1 HRS $ 675.00 $ 675.00 0 HRS $ 675.00 $ - 4K AC Pavement and Base (trench restoration) 800 SF $ 16.55 $ 13,240.00 670 SF $ 16.55 $ 11,088.50 4L Additional'/z" Thickness of AC Pavement (trench restoration) 800 SF $ 2.35 $ 1,880.00 2,680 SF $ 2.35 $ 6,298.00 4M All Other Work Required by the Contract Documents 1 LS $ 12,800.00 $ 12,800.00 1 LS $ 12,800.00 $ 12,800.00 5A Inner Duct from Station 0+04 to Station 24+20 2,420 FT $ 7.75 $ 18,755.00 2,463 FT $ 7.75 $ 19,088.25 5B 2" Conduit from Station 0+00 to Station 0+52 1 LS $ 5,900.00 $ 5,900.00 1 LS $ 5,900.00 $ 5,900.00 5C 10" Pipe at Station 2+98 1 LS $ 3,475.00 $ 3,475.00 1 LS $ 3,475.00 $ 3,475.00 5D 10" Pipe at Station 18+80 1 LS $ 3,475.00 $ 3,475.00 1 LS $ 3,475.00 $ 3,475.00 5E 2" Conduit from Station 23+96 to Station 24+26.36 1 LS $ 6,775.00 $ 6.775.00 1 LS $ 6,775.00 $ 6,775.00 5F Rock Excavation 1 HRS $ 675.00 $ 675.00 0 HRS $ 675.00 $ - 5G AC Pavement and Base (trench restoration) 425 SF $ 23.05 $ 9,796.25 328 SF $ 23.05 $ 7,560.40 5H Additional''/2" Thickness of AC Pavement (trench restoration) 425 SF $ 3.15 $ 1,338.75 1,312 SF $ 3.15 $ 4,132.80 51 All Other Work Required by the Contract Documents 1 LS $ 1o,000.00 $ 10,000.00 1 LS $ 10,000.00 $ 10,000.00 Total Amount of Base Bid $ 1,478,273.75 $ 1,430,676.46 Credit to the District $ 47,597.29 Page 3 of 5 Resolution No. 2015 - 21 AUTHORIZING THE ACCEPTANCE OF THE DISTRICT PIPELINE REPLACEMENT - 2015 PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to undertake the District Pipeline Replacement - 2015 Project and WHEREAS, AMX-Construction Inc. was selected by the District to perform the work; and WHEREAS, AMX-Construction Inc. has completed all of the work included in the Project; and WHEREAS, The District's Water System Engineer, Neil Kaufman, now certifies the completion of the project; and WHEREAS, the District's Water Utility Manager/General Manager, Michael D. Holley, has recommended that the work be accepted by the District; NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows: 1. That the District hereby accepts the District Pipeline Replacement - 2015 Project as complete. 2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a copy of which is attached hereto. 3. That 35 days following the filing of the Notice of Completion, the monies retained from the contractor payments be released to the contractor if no claims have been made to the District by material suppliers, laborers, or sub -contractors. PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the fourth day of November 2015 by the following roll call vote: AYES: NOES: None ABSTAIN: None ABSENT: None TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Bob Ellis, President of the Board ATTEST: Michael D. Holley, Clerk of the Board Page 4 of 5 RECORDING REQUESTED BY: Truckee Donner Public Utility District WHEN RECORDED, RETURN TO: TRUCKEE DONNER PUBLIC UTILITY DISTRICT 11570 Donner Pass Road Truckee, CA 96161 THE UNDERSIGNED DECLARES DOCUMENTARY TRANSFER TAX - NONE NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. That the name and address of the public entity for whom the improvement project was done, as owner thereof, is the Truckee Donner Public Utility District, 11570 Donner Pass Road, Truckee, CA 96161. 2. Nature of interest or estate of owner: beneficial interest of a public utility easement for installation of water facilities. 3. That on November 4, 2015 the hereinafter described improvements were accepted as complete pursuant to Resolution 2015-21 of the Truckee Donner Public Utility District, the awarding authority. 4. That the subject improvements of the Notice are generally described and identified as follows: District Pipeline Replacement - 2015 Project. 5. That the name and address of the contractor for such project was: AMX-Construction Inc. P.O. Box 3605, Loomis, CA 96160. I certify under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Dated: November 4, 2015 TRUCKEE DONNER PUBLIC UTILITY DISTRICT M Michael D. Holley, General Manager MAIL TAX STATEMENTS TO: SAME AS ABOVE Legal References: CC-3093,CCP-2003 (oath), 2015.5 (unsworn statement) Page 5 of 5