Notice of Completion Sun Valley Pipeline Replacement
1. WHY THIS MATTER IS BEFORE THE BOARD
2. HISTORY
In August 2015, the Board awarded the construction contract for the Sun Valley Road
Pipeline Replacement project to Longo Incorporated of Tahoe City, California. The
project involved replacement of about 750 feet of pipeline along Sun Valley Road.
The original bid price was $225,634. At the time of award, the Board also established
a 10 percent change order allowance for a total for a total authorization not to exceed
$248,000.
3. NEW INFORMATION
Longo began work in September and completed the construction in early November.
District staff has performed a final walkthrough on the project. The work is complete
and should be accepted by the District.
There were no change order requests submitted by the contractor. The contract is
based on a unit price bid. Attachment 1 shows the differences between bid totals and
the amounts actually constructed. This analysis results in a $3,883 credit to the
District.
Attached is a draft resolution 2015-23 (Attachment 2) accepting the project and
directing that a Notice of Completion be filed.
4. FISCAL IMPACT
The original bid price was $225,634. Once an adjustment is made to reconcile the bid
quantities versus the actually constructed quantities, the final contract price is
$221,751. As discussed at the time of award, the anticipated funding source for the
project is the Water Department Capital Replacement Fund. Once that fund is
depleted the anticipated funding source for the project is the Water Department
Operating Reserve Fund.
5. RECOMMENDATION
Adopt Resolution 2015-23 accepting the Sun Valley Road Pipeline Replacement
project as complete and authorize the filing of the Notice of Completion.
Michael D. Holley
General Manager / Water Utility Manager
Analysis of Bid Quantities vs. Actual Quantities Constructed
Sun Valley Road Pipeline Replacement
Contractor: Longo Incorporated
Bid Item
Description
Bid Amounts
Actual Amounts
Quantity Units
Unit Price
I Subtotal
Quantity
Units
I Unit Price
Subtotal
1
Mobilization
1
LS
$
15,500.00
$
15,500.00
1
LS
$
15,500.00
$
15,500.00
2
8" Water Main
745
FT
$
96.00
$
71,520.00
754
FT
$
96.00
$
72,384.00
3
2" PE Water Service Lateral
300
FT
$
84.00
$
25,200.00
312
FT
$
84.00
$
26,208.00
4
Two 1" PE Water Service Laterals in Common Trench
12
FT
$
72.00
$
864.00
27
FT
$
72.00
$
1,944.00
5
Double Water Service (DS)
4
EA
$
3,500.00
$
14,000.00
4
EA
$
3,500.00
$
14,000.00
6
Double Water Service with One Lot Vacant (DSV)
4
EA
$
3,200.00
$
12,800.00
3
EA
$
3,200.00
$
9,600.00
7
Connect New 2" Lateral to Existing Meter Box at 11464 Sun Valley Road
1
LS
$
2,800.00
$
2,800.00
1
LS
$
2,800.00
$
2,800.00
8
Fire Hydrant Assemby
1
EA
$
8,700.00
$
8,700.00
1
EA
$
8,700.00
$
8,700.00
9
Air Release Valve Assembly
1
EA
$
4,300.00
$
4,300.00
1
EA
$
4,300.00
$
4,300.00
10
Connection to Existing 8" Pipe at Station 0+00
1
EA
$
5,750.00
$
5,750.00
1
EA
$
5,750.00
$
5,750.00
11
Connection to Existing 8" Pipe at Station 7+45.02
1
EA
$
5,750.00
$
5,750.00
1
EA
$
5,750.00
$
5,750.00
12
Rock Excavation
2
HRS
$
1,000.00
$
2,000.00
7
HRS
$
1,000.00
$
7,000.00
13
AC Pavement and Base (trench restoration)
5,800
SF
$
8.50
$
49,300.00
4,890
SF
$
8.50
$
41,565.00
14
Additional 1/2" Thickness of AC Pavement (trench restoration)
5,800
SF
$
0.75
$
4,350.00
4,600
SF
$
0.75
$
3,450.00
15
All Other Work Required by the Contract Documents
1
LS
$
2,800.00 1
$
2,800.00
1
LS
$
2,800.00 1
$
2,800.00
$ 225,634.00 $ 221,751.00
Credit to the District $ 3,883.00
Resolution No. 2015 - 23
AUTHORIZING THE ACCEPTANCE OF
THE DISTRICT PIPELINE REPLACEMENT - SUN VALLEY ROAD 2015
PROJECT
AND DIRECTING FILING OF THE NOTICE OF COMPLETION
WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to
undertake the Sun Valley Road Pipeline 2015 Project and
WHEREAS, Longo Incorporated was selected by the District to perform the work; and
WHEREAS, Longo Incorporated has completed all of the work included in the Project; and
WHEREAS, The District's Water System Engineer, Neil Kaufman, now certifies the completion of the project; and
WHEREAS, the District's Water Utility Manager/General Manager, Michael D. Holley, has recommended that the
work be accepted by the District;
NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows:
1. That the District hereby accepts the Sun Valley Road Pipeline 2015 Project as complete.
2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a copy
of which is attached hereto.
3. That 35 days following the filing of the Notice of Completion, the monies retained from the contractor
payments be released to the contractor if no claims have been made to the District by material suppliers,
laborers, or sub -contractors.
PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the
ninth day of December 2015 by the following roll call vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
Bob Ellis, President of the Board
ATTEST:
Michael D. Holley, Clerk of the Board
RECORDING REQUESTED BY:
Truckee Donner Public Utility District
WHEN RECORDED, RETURN TO:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
Shanna D. Kuhlemier, Deputy District Clerk
11570 Donner Pass Road
Truckee, CA 96161
THE UNDERSIGNED DECLARES
DOCUMENTARY TRANSFER TAX - NONE
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
That the name and address of the public entity for whom the improvement project was done, as owner
thereof, is the Truckee Donner Public Utility District, 11570 Donner Pass Road, Truckee, CA
96161.
2. Nature of interest or estate of owner: beneficial interest of a public utility easement for installation of
water facilities.
3. That on December 9, 2015 the hereinafter described improvements were accepted as complete
pursuant to Resolution 2015-23 of the Truckee Donner Public Utility District, the awarding authority.
4. That the subject improvements of the Notice are generally described and identified as follows: Sun
Valley Pipeline 2015 Project.
5. That the name and address of the contractor for such project was: Longo Incorporated, P.O. Box 6177,
Tahoe City, CA 96145
I certify under penalty of perjury under the laws of the State of
California that the foregoing is true and correct.
Dated: December 9, 2015 TRUCKEE DONNER PUBLIC UTILITY DISTRICT
Michael D. Holley, General Manager
MAIL TAX STATEMENTS TO:
SAME AS ABOVE
Legal References: CC-3093,CCP-2003 (oath), 2015.5 (unsworn statement)