HomeMy WebLinkAboutORD 2014-02 - Board 0 TRUCKEE DONNER
Publ D strict
• Ordinance No. 2014 - 02
AMEND ELECTRIC FEE SCHEDULE
WHEREAS, on September 6, 2006, an ordinance was adopted to establish certain electrical costs
as flat fees rather than billing the actual cost; and
WHEREAS, on February 6, 2008, an ordinance was adopted to amend those fees; and
WHEREAS, on April 16, 2014, a workshop was held to recommend an increase to reflect the
average actual costs of relocating overhead power service and to provide temporary power; and to
recommend combining several fees for single phase connection with other fees.
NOW, THEREFORE, BE IT ENACTED by the Board of Directors of the Truckee Donner Public
Utility District as follows:
ELECTRIC FEES
Size and Type of Service Fee
Single Phase, 120/240 Service— 200 amp•
1) Permanent connection to structure $1,248
2) Temporary connection to customer-owned power pole and $1,534
subsequent transfer to structure
Single Phase, 120/240 Service—400 amp
1) Permanent connection to structure $2,364
2) Temporary connection to customer-owned power pole;
removal of same and installation of underground permanent $2,649
service to structure
Three phase, 208v, 240v or 480v service
1) Permanent connection to structure Actual Cost
2) Temporary single phase 120/240 service for construction Actual Cost
purposes to become three-phase permanent service to
structure
Overhead to Underground upgrade or relocate, up to 200 amp panel $1,248
Overhead Relocation $467
400 amp upgrade $1,854
Underground Relocation up to 200 amp $1,248
Underground Relocation 400 amp $2,364
Temporary overhead service $1,248
• Overhead to Underground upgrade or relocate, up to 200 amp panel, $1,534
with TPP (Temp to Permanent Installation)
1 Ordinance 2014-02
Section 3. If no protest is made pursuant to Public Utilities Code Section 16078, then this
• ordinance shall be effective on June 21, 2014, after adoption by the board of directors of the
District.
Section 4. The Clerk of the District shall immediately cause a copy of this ordinance to be
published in a newspaper of general circulation and posted in three places within the District.
Section 5. The provisions of other Ordinances shall remain if effect to the extent that they do not
conflict with this ordinance.
PASSED AND ADOPTED by the Board of Directors of the Truckee Donner Public Utility District at
a meeting duly called and held within the District on the twenty first day of May 2014 by the
following roll call vote:
AYES: Directors Aguera, Bender, Ellis, Hemig and Laliotis
NOES: None
ABSTAIN: None
ABSENT: None
• TRUCKEE ONNERR PUBLIC UTILITY DISTRICT
By ./ /
Tony Laliotis President of the Board
ATTEST:
Michael D. Holley, Clerk of the Board
•
•
2 Ordinance 2014-02