HomeMy WebLinkAbout11 UAMPS Pooling Appendix Extension -Stampede FallonAction Item # 11
Extension of Pooling Appendix,
Stampede Hydro & City of Fallon
February 20, 2013
Background / History
• Stampede Generation Pooling Appendix Agreement
• Initially the Stampede Generation is shared with the City of
Fallon ("Fallon") by scheduling the every other month to
TDPUD
• TDPUD and Fallon entered into a UAMPS Pooling Appendix
on February 1, 2010
• Currently all the Stampede generation is delivered to
TDPUD
• In exchange for Fallon's portion of Stampede, TDPUD sells
Fallon a similar amount of MWh's from its UAMPS
resources
2
New Information
• Staff has negotiated with Fallon to extend the exchange of
energy from the Stampede generation to TDPUD
• TDPUD will replace this generation to Fallon from its UAMPS
resource mix
• TDPUD will sell Fallon 500 kW per hour at a rate of $32/MWh
minus the REC valuation and UAMPS transmission
• REC valuation is the average of bid and offer prices of the
WECC Green-E Wind (wregis)
• A true -up is performed once a year
• Term of this appendix begins Jan 1, 2014 through Dec 31,
2018
3
Fiscal Impact
• The net cost of the Stampede generation transfer is the
difference between the Stampede generation and the cost
of TDPUD's other resources at UAMPS
— These costs currently range between $20 and $40 per MWh and do
not include REC's or transmission
0
Recommendation
• Approve the UAMPS Pooling Appendix concerning the
transfer of energy from the Stampede generation from the
City of Fallon to Truckee Donner PUD
5