HomeMy WebLinkAbout9 District High Efficiency Boiler ProjectAction Item # 9
Accepting the District High
Efficiency Boiler Replacement
Project as Complete
February 20, 2013
Background / History
• The original boilers were 25 years old
• August 1st contract awarded to Efficient Energy Concepts
• Total contract amount including change order allowance
was $104,309
• Work began mid -September
2
New Information
• Change orders
• Higher efficiency
• Time extension
• Project cost $91,624
• The project is now complete
3
Before After
Fiscal Impact
• Sufficient funds exist within FY12 budget to fund this project
• There is no fiscal impact associated with filing the Notice of
Completion
5
Recommendation
• Adopt the resolution accepting the District High Efficiency
Boiler Project as complete
• Authorize the filing of the Notice of Completion