HomeMy WebLinkAbout20-2 Attch2-SCADA1Contract Name
Contract Change Order No
Date:
SCADA Reliabilitv I
K
5/23/12
Contractor: Curtis and Sons Construction, Inc.
Change Order
ment Proiect - 2011
Orig. Contract Amt. $
279,653.50
Days
135
Prev. Apprd Changes $
0.00
Days
84
This Change $
1,151.73
Days
0
Revised Contract Amt. $
280,805.23
Days
219
Remaining Authorized
Change Amt. $
26,848.27
Days
NA
This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct,
furnish equipment and materials, and perform all work as necessary or required to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District.
Increase in
(Decrease)
Contract Time
Contract
in Contract
Extension
Description of Changes
Amount $
Amount $
(days)
12ct Fiber Installed, Less than Bid Quantity
0.00
(407.40)
0
48ct Fiber Installed, Greater than Bid Quantity
420.64
0.00
0
96ct Fiber Installed, Greater than Bid Quantity
1,062.53
0.00
0
216ct Fiber Installed, Less than Bid Quantity
0.00
(217.84)
0
12ct Fiber (Aerial) Installed, Greater than Bid Quantity
393.80
0.00
0
Fusion Splices Completed, Less than Bid Quantity
0.00
(100.00)
Totals
1,876.97
(725.24)
0 days
Net change in contract amount (increase or decrease)
1,151.73
0 days
The amount of the Contract will be increased by the sum of $ 1,151.73 and the Contract Time be extended by 0
days. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item including any and all supervision costs and other miscellaneous costs
related to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on
account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other
necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete
the Change order items. This document will become a supplement of the contract and all provisions will apply
hereto. It is understood that the Change Order shall be effective when approved by the District.
Accepted:
Approved:
(Signature)
(Signature)
/Contractor Date:
/District Date:
Page 1