Resolution Accepting Final
Completion and Closeout
Change Order for SCADA
Reliability Improvement
Project -Phase 1
June 6, 2012
Background / History
• Project to improve communication reliability to remote
electric and water facilities
• Civil Construction contract awarded to Heavy Equipment in
May, 2011
• Fiber installation contract awarded to Curtis & Sons
Construciton, Inc. in October, 2011
— Contract price $279,653.50 + 10% ($28,000) change order
allowance
2
Background / History (Cont'd)
• Phase 1 Route
01
New Information
• Two change orders required
— Contract deadline extension required due to long lead times
— Field conditions differed from contract drawings
• Total cost for change orders was $1,151.73
• Well under Change Order Allowance
• Project is complete
0
Fiscal Impact
• Project funded as follows:
Electric $1407402.62 Capital Reserves and Projects
Water $140,402.62 Capital Projects
Total $280,805.24
• Sufficient funds exist in the FY12 budget
5
Recommendation
• Adopt a resolution accepting the SCADA Reliability
Improvement Project —Phase 1 as complete and authorize
the filing of the Notice of Completion