HomeMy WebLinkAboutAttch1-SCADA1Change Order
Contract Name: SCADA Reliability Improvement Project -Phase 1
Contract Change Order No: 1 Orig. Contract Amt. $
279,653.60 Days 135
Date: 12/8/11 Prev. Apprd Changes $
0.00 Days 0
Contractor: Curtis and Sons, Inc. This Change $
0.00 Days 84
Revised Contract Amt. $
279,653.50 Days 219
Remaining Authorized
28,000
Change Amt. $
Days NA
This Change Order covers changes to the subject Contract as described herein.
The Contractor shall construct,
furnish equipment and materials, and perform all work as necessary or required
to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District.
Increase in
(Decrease)
Contract Time
Description of Changes
Contract
Amount $
in Contract
Amount $
Extension
(days)
Delays in materials procurement
0.00
0.00
84 days
Deadlines for the Contract Milestones will be as follows:
Milestone 1 — Cable Installation by 3/31/12
Milestone 2 — Substantial Completion by 4/30/12
Milestone 3 — Final Completion by 5/11/12
Totals
Net change in contract amount (increase or decrease)
0.00
0.00
84 days
The amount of the Contract will be increased by the sum of $ 0.00 and the Contract Time be extended by
84 days. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item including any and all supervision costs and other miscellaneous costs
related to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on
account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other
necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete
the Change order items. This document will become a supplement of the contract and all provisions will apply
hereto. It is understood that the Change Order shall be effective when approved by the District.
/Contractor
tsignarure)
Approved: /District
nature)
Page 1
Date:
Date: