HomeMy WebLinkAbout9 Attachment 2 Town of Truckee Council Meeting Staff Report0 0
2� ee9
`e
4eQ' 63 Inea`P
Date: April 26, 2022
Honorable Mayor and Council Members:
Author and title: Jessica Thompson, Senior Engineer
Title: Truckee River Legacy Trail Phase 4A C0702—Bid Update
Approved By: Jen Callaway, Town Manager
Recommended Action: Town Council receive an update from staff regarding the Truckee River
Legacy Trail Phase 4A construction contract bid.
Discussion: The Truckee River Legacy Trail Phase 4A project consists of construction of a 10-12 foot
wide Class 1 multi -use trail along the south side of the Truckee River between the west end of South
River Street and the western town limits. The project includes a pedestrian bridge across the Truckee
River, extension of South River Street with a vehicle bridge to a trailhead parking lot, and a spur to the
Cottonwood Restaurant with a second pedestrian bridge. The project includes restoration and a trail to
the river at the Donner Creek Confluence area on West River Street, restoration of existing wetlands
and a portion of a small creek within the project area, and a new Truckee Donner Public Utility District
(TDPUD) water line will also be incorporated into the project.
The Truckee River Legacy Trail Phase 4A Project was last presented to Council on January 25, 2022
for authorization to bid the project. The project construction bid was publicly advertised on February
23, 2022. Bids were received from three contractors on April 15, 2022 (Mercer -Fraser Company, Walsh
Construction Company, and Herback General Engineering). The low bidder was Mercer -Fraser, and all
three bids were within approximately 6% of each other. A summary of the bids received is provided
below and the bid tabulations are included as Attachment 1.
Table 1: Bid Summary
Contractor
Bid Amount
Herback General Engineering
$13,170,160.23
Walsh Construction Company
$12,489,209.25
Mercer -Fraser
$12,395,287.32*apparent low bid
The Engineer's estimate for the project was $8.2 million and the apparent low bid is $12,395,287, which
is $4.2 million (50 percent) above the Engineer's Estimate. The Construction Bid for the bridge over the
Truckee River was approximately 2.5 times the Engineer's Estimate for that bridge, and thus represents
the majority of the overall project bid which is in excess of the Engineer's Estimate.
The Town has funding agreements in place or in progress with both the Truckee Donner Land Trust
(TDLT) and Truckee Donner Public Utility District (TDPUD), summarized below.
Truckee Donner Land Trust (TDLT)
• TDLT and the Town will split the design and construction costs for the pedestrian bridge with
TDLT paying 75% and the Town paying 25% of the bridge costs.
• TDLT will fund 100% of the design of the trailhead infrastructure in the Truckee Springs parcel,
including the South River Street road extension, small vehicle bridge over existing drainage,
parking lot, trail connection to the pedestrian bridge, and the soft surface trail improvements. The
Town will fund the trail connection connecting the parking lot and the Legacy Trail.
Truckee Donner Public Utility District (TDPUD) Water Line
• TDPUD agrees to reimburse the Town for 100 percent of the actual construction costs associated
with the TDPUD waterline.
The TDLT agreement has a meet and confer requirement if the bridge bid is above $2.5 million to discuss
possible means of reducing the bridge cost, including without limitation revising the bridge design or not
building parts of the bridge, as well as the possibility of TDLT raising additional funds. Staff has initiated
this process, based on the project cost shares discussed in the Fiscal Impact Section below. TDLT staff
has told Town staff that they do not currently have funding available to move forward with their share of
the project funding based on the current bridge costs. Town staff will provide an update on further
discussions with TDLT and TDPUD at the April 26, 2022 Council meeting.
The proposed bridge is a unique design that was chosen through a process facilitated by TDLT.
However, there are less expensive bridge options available, such as the pre -fabricated bridges that are
currently on portions of the Truckee River Legacy Trail and Trout Creek trail. If funding for the current
bridge continues to be unavailable, below are some options that would allow for the Project to move
forward.
1. Award the contract and replace the bridge with a less -expensive bridge type through a contract
change order.
2. Reject all bids and rebid the project without the bridge in late summer or fall of 2022. Rebidding
the project does not guarantee lower prices. A revised bridge design could be pursued in the
future as a separate project or incorporated as part of the West River Street Park project.
3. If TDLT commits to fund raising their fair share in the future, the Town could amend the current
reimbursement agreements such that the Town would proceed without the full deposit from TDLT
and with the understanding that TDLT would reimburse the Town for their full fair share over time.
4. The Town could increase its funding contribution to the project above current levels.
Priority:
xBEnhanced Communication x Climate and Greenhouse Gas Reduction Housing
Infrastructure Investment Emergency and Wildfire Preparedness Core Service
Fiscal Impact: The total construction cost for the Project is estimated to be $14,360,511.05, which
includes a 10% contingency for the contract award plus estimated costs for permitting, construction
engineering, and construction support costs (consistent with the agreements with TDLT and TDPUD).
The breakdown of the various parts of the trail is provided in Table 2.
Table 2: Summary of Estimated Construction Costs
Section Description
Estimated Cost
A
General (Mobilization, Stormwater BMPs, Traffic Control, etc.)
$ 1,538,400.00
B
Legacy Trail A Line (Class 1 Trail from Parking Lot to West)
$ 1,466,532.00
C
Legacy Trail J Line (Class 1 Trail to Cottonwood)
$ 2,690,228.32
D
South River Street Extension, Trailhead Parking Lot and H Line to
Bridge
$ 904,307.00
E
Truckee Springs Pedestrian Bridge
$ 5,463,120.00
F
TDPUD Water Line (excludes portion on the bridge)
$ 252,750.00
G
Donner Creek Confluence Restoration
$ 79,950.00
Subtotal
$ 12,395,287.32
Construction Contract Contingency 10%
$ 1,239,629.73
Construction Engineering/ Materials Testing/Permits/Construction
Support
$ 725,694.00
Total
$ 14,360,511.05
Per the existing agreement, the costs for the construction of the bridge will be split 75%/25% between
the TDLT and the Town, respectively, with the exception of the waterline on the bridge, the cost for which
will be paid by TDPUD. The TDLT will fund 100% of the trailhead parking (row D above). The "General"
items Row A will be split between the Town, TDPUD, and TDLT based on the proportion of the cost of
each entities' non -general construction items to the total cost of non -general construction items. Staffs
estimate of the construction cost breakdown based on the low bid are provided in the table below.
Table 3: Shared Construction Costs
Entity
Construction Contract
Cost (excludes 10%
contract contingency)
% of Contract
TDLT
$ 5,600,092
45%
TOT
$ 6,354,344
51%
TDPUD
$ 440,852
3%
Total
$ 12,395,287
100
Construction also includes other costs such as environmental permitting, construction management,
inspection, pre -construction surveys, and for this project, a Washoe Tribal monitor, summarized below.
Some of these items are only estimates and may change:
Table 4: Additional Construction Costs
Soft Costs (some
items are
estimates)
Estimate
TDLT
TDPUD
TOWN
SWPPP Permit
$
1,512
$
504
$
504
$
504
404 Permit
$
4,000
$
1,333
$
1,333
$
1,333
401 Permit
$
3,802
$
1,267
$
1,267
$
1,267
1600 Permit
$
30,000
$
10,000
$
10,000
$
10,000
Interpretive Signs
$
30,000
$
15,000
$
15,000
NV5 (Material
Testing and
Inspections)
$
114,031
$
51,542
$
3,877
$
58,612
Pre -Construction Bio
$
21,500
$
9,718
$
731
$ 11,051
Washoe Monitor
$
20,000
$
14,490
$
680
4,830
Staff Time
$
80,000
$
36,160
$
2,720
$ 41,120
CME (Construction
Management)
$
420,849
$
190,224
$
14,309
$ 216,316
Total
$
725,694
$
330,748
$
35,422
$ 360,204
Based on the construction costs and soft costs, as well as the design costs, the following breakdown is
estimated between the funding partners based on current funding agreements. Some of the design
costs have already been invoiced and paid by the partners.
Table 4: Total Estimated Construction and Soft Costs
Agency
Construction
Amount
With 10% Contingency
and Soft Costs
TDLT
$ 5,600,091.77
$ 6,490,339.38
TOT
$ 6,354,343.65
$ 7,349,812.01
TDPUD
$ 440,851.89
$ 520,358.67
Total
$ 12,395,287.32
$14,360,510.05
Accounting for projected trail maintenance costs and other CIP's that include Measure R funding (trail
seal coat and Martis Creek Trail design initiation), it is anticipated that there is over $9 million in
Measure R funds available to expend on the Legacy Trail between now and the end of Fiscal Year
23/24.
Public Communication: Ongoing communication with the property owners, TDPUD, and TDLT.
Attachments:
1. Bid Tabulations
2. Bid Shared Costs