HomeMy WebLinkAbout9 Attachment 3 Draft Agreement with the Town of TruckeeREIMBURSEMENT AGREEMENT
THIS REIMBURSEMENT AGREEMENT (the "Agreement") is entered into as of
, 2022 by and between Truckee Donner Public Utility District, a public
agency ("TDPUD"), Truckee Donner Land Trust (TDLT), a California corporation
("TDLT"), and the Town of Truckee, a municipal corporation of the State of California
(the "Town").
Section 1: Recitals
A. The Town is planning on constructing a Class 1 Trail along the south side of the
Truckee River at the end of South River Street ("Trail") and will include a
pedestrian bridge across the Truckee River to the west end of Riverside Drive
("Bridge"), trailhead parking lot, and an extension of South River Street with a
vehicle bridge. The Town will construct the Trail using local funds and private
funds from the Truckee Donner Land Trust (TDLT). State grant funds may also
be used, but have not been secured at the time of this contract.
B. TDPUD desires to install a water line across the Bridge and along portions of the
Trail alignment and areas in the vicinity of the Trail to provide a connection
between South River Street and Riverside Drive
C. The Truckee Donner Land Trust owns the property under the Trail and water line
and is funding 75% of the Bridge, 100% of the trailhead parking lot, South River
Street extension and trail connection to the Bridge. The water line will use the
Bridge to cross the Truckee River.
D. Town and TDPUD have determined that it will be more cost effective and
efficient for the Town to construct the TDPUD water line at the same time as the
Trail and then be reimbursed by TDPUD for the portion of the coordination and
construction cost that is the responsibility of TDPUD.
Section 2: Agreement
For good and valuable consideration, the receipt and adequacy of which is
acknowledged, the parties agree as follows:
A. TDPUD agrees to reimburse the Town for 100 percent of the actual construction
costs associated with the Truckee Donner PUD Water Line as shown in Exhibit
A and attached hereto. The costs include the waterline bid items plus a
percentage of the shared costs, such as mobilization, traffic control, erosion
control, protecting and inspecting the TTSA sewer line, dewatering, restoration,
and survey. The Truckee Donner PUD Water Line bid items include that portion
of the construction project that is associated with the installation of water
facilities. The estimated cost for each specific line items and TDPUD's and the
Town's resultant calculated contribution rates are shown in Exhibit B. Actual
costs and the fair share percentage will be based on the awarded bid.
B. The Town of Truckee has retained the consultant Lumos and Associates for
design of the Trail, permitting assistance, and production of the Plans,
Specifications, and Engineering (PS&E) package. TDPUD has also hired
Lumos and Associates to design the water line and provide specifications.
TflDlTvr vcagreestgig' the water lino plans and pFeyirl The plans and
specifications for the water line portion of the project shall be in the same format
as the Trail plans. Lumos and Associates will incorporate TDPUD plan sheets
and specifications into the PS&E package for bidding and permitting purposes.
The coordination effort is anticipated to consist of adding notes for referencing
TDPUD plans, table of contents coordination, word processing, and SWPPP
revisions specific to the water line portion. TDPUD agrees to reimburse the
Town for Lumos' fees that are attributed to the plans and specification
coordination effort described above, as identified by Lumos.
C. The Town of Truckee contracted with Nutt, Redfield, and Valentine (NRV) for
design of the Bridge prior to the inclusion of the water line. Per TDPUD's
request, NRV has incorporated the water line crossing of the Bridge in the
Bridge plans. TDPUD agrees to reimburse the Town for design costs related to
incorporating the water line in the Bridge plans. NRV will identify the water line
costs separately in their invoices.
D. The TDPUD agrees to reimburse the Town for other shared cost items
associated with the project implementation, including, but not limited to,
restoration monitoring, construction inspection, materials testing, pre -
construction bird and nesting animal surveys, Washoe Tribe site monitor, and
other construction related items that benefit both the Trail Project, Bridge, and
the TDPUD water line installation. These items are anticipated to be shared
based on the percentage of the non -shared construction costs that are related to
the waterline construction, as estimated in Exhibit B and identified as "TDPUD's
Fair Share for General Items".
E. The entire project is subject to State Prevailing Wage and other related State
requirements.
F. Town will obtain or cause to be obtained all governmental or other permits
required for the Project. Permits that would be required by both portions of the
project will be a shared cost, including but not limited to the Construction
General Permit, Timber Harvest Waiver, 401 permit, 404 permit, and Streambed
Alteration Agreement. Permits that are unique to one project or the other will not
be a shared cost. TDPUD shall reimburse the Town for 33 percent of shared
permit costs, dewatering, mitigation in lieu fees, and monitoring of restoration
areas.
G. Town agrees to solicit bids for construction of the Trail and water line facility.
The project will be bid in a manner that will allow the TDPUD water line facility
costs to be easily extracted from the total bid cost. TDPUD retains the right to
reject the Truckee Donner PUD Waterline bid items. The Town retains the right
to reject all bids.
H. After bids have been received and an apparent low bidder determined, Town
shall review the bids to determine TDPUD's fair share cost and notify TDPUD of
the bid amounts within 48 hours of receiving the bids.. The engineer's estimate
for TDPUD's share of the project construction is $357,594, or $411,233 including
a 15% contingency, included in Exhibit B. TDPUD shall notify Town in writing
within 35 days of the first regularly scheduled Board meeting following the bid
opening whether it wants to proceed with the construction of the waterline.
Unless the Town decides to reject all bids, the Town will award the project to the
lowest responsible bidder, a California licensed general contractor (the
"Contractor"), who is appropriately licensed for the work relating to the Project.
The Town will delete the waterline work from the contract via change order if the
TDPUD decides not to move forward.
TDPUD agrees to participate in and provide timely review of items related to the
water line infrastructure, including, but not limited to, submittal review, responses
to RFIs, meetings associated with the construction, inspections, change order
authorization. The party that is primarily involved in a specific change order shall
take the lead in communications with the contractor. However, project change
orders associated with the water line work shall be approved and signed by both
agencies prior to incorporation into the contract.
J. TDPUD shall have the right to inspect all water line work.
K. TDPUD agrees to make payments to the Town for its fair share of the costs.
The Town will invoice TDPUD after costs are incurred. TDPUD shall reimburse
the Town for final design coordination and bridge design fees outlined in Section
2B and 2C above within 30 days of receiving an invoice from the Town. The
invoice is anticipated to be sent within 2 weeks of the bid opening. TDPUD shall
reimburse the Town monthly once construction has commenced, based on work
completed. Within 60 days of filing the Notice of Completion, the Town and
TDPUD will reconcile the construction costs.
L. Prior to project acceptance from the contractor, Town will consult with TDPUD to
verify that the water line work is acceptable to TDPUD.
M. If a claim or dispute with the contractor arises that is clearly related to a non -
shared portion of the project, the responsible agency shall resolve the issue
without monetary implications to the other agency.
N. Town will obtain from the selected general contractor, general liability insurance,
automobile liability, and workers compensation insurance in the amount
approved by the Town's Risk Manger after consultation with its liability insurer.
Town, TDLT,and TDPUD shall be named as additional insureds on the policies
provided by the general contractor which shall be accompanied by certificates of
insurance and policy endorsements.
O. This agreement neither grants nor authorizes an easement for the water line.
This agreement is solely for describing monetary reimbursement of the design,
construction, and permitting of the water line. TDLT will consider executing the
easement agreement with TDPUD as a separate agreement. If determined to be
necessary by Town, Town and TDPUD shall enter into a separate license
agreement on terms acceptable to both parties for waterline access across the
bridge crossing.
Section 3: General Provisions
A. Assignment/Successors
This Agreement may not be assigned without prior written approval of all parties
which approval shall not be unreasonably withheld or delayed. The terms,
conditions, covenants and agreements set forth herein shall apply to and bind
the heirs, administrators, assigns and successors of the parties hereto.
B. Authority
Each party warrants that the person executing this Agreement on behalf of the
respective party is fully authorized by that party to do so.
C. Notices
All notices required to be given under this Agreement shall be in writing and sent
by (a) first class mail, postage prepaid, in which case notice shall be deemed
delivered three (3) business days after deposit in the United States Mail; (b) a
nationally recognized overnight courier, in which case notice shall be deemed
delivered one (1) business day after deposit with that courier, or (c) telecopy or
similar means, in which case notice shall be deemed delivered in one (1)
business day after the day it was transmitted by telecopier or similar means,
provided that transmission report is generated reflecting the accurate
transmission of the notices. The place for delivery of all notices given under this
Agreement shall be as follows:
TDPUD: General Manager
Truckee Donner Public Utility District
11570 Donner Pass Road
Truckee, CA 96161
Town: Town Manager
Town of Truckee
10183 Truckee Airport Road
Truckee, CA 96161
TDLT: Executive Director
Truckee, CA 96162
or to such other addresses that any party may respectively designate by written
notice to the others.
D. Entire Agreement
This Agreement and the attached Exhibits, which are herein incorporated into
this Agreement by this reference, supersede all previous oral or written
communication and contain the entire agreement of the parties to this
Agreement and shall not be modified in any manner except by an instrument in
writing executed by the parties or their respective successors in interest.
E. Termination
This agreement shall terminate after all invoices have been paid and 90 days
after recordation of a Notice of Completion for the project.
F. Construction
The section headings and captions of this Agreement are, and the arrangement
of this instrument is, for the sole convenience of the parties to this Agreement.
The section headings, captions and arrangement of this instrument do not in any
way affect, limit, amplify or modify the terms and provisions of this Agreement.
This Agreement shall not be construed as if it had been prepared by one of the
parties, but rather as if all parties have prepared it. The parties to this
Agreement and their counsel have read and reviewed this Agreement and agree
that any rule of construction to the effect that ambiguities are resolved against
the drafting party shall not apply to the interpretation of this Agreement.
G. Waiver
Waiver of any provision or of a breach or default under this Agreement shall not
constitute a continuing waiver or a waiver of a subsequent breach of the same or
any other provision of this Agreement.
H. Severability
In the event any provision of this Agreement is held invalid or unenforceable by
a court of competent jurisdiction, the remaining provisions shall not be affected.
Counterparts
This Agreement may be executed in any number of counterparts, each of which
shall be original, but all of which taken together shall constitute one instrument.
Representation
This Agreement is executed voluntarily by each of the parties hereto, all of
whom have been advised by independent counsel of their choice as to the
content and effect of this Agreement.
K. Governing Law
The Agreement shall be governed by and construed according to the laws of the
State of California.
L. Venue
Nevada County shall be the venue for any action or proceeding that may be
brought or arise out of, in connection with or by reason of this Agreement.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the date
first above written.
TDPUD:
Truckee Donner Public Utility District, a Public Agency
Brian Wright, General Manager
TOWN:
Town of Truckee, a Municipal Corporation of the State of California
as
Town Manager, Jennifer Callaway
TDLT:
Truckee Donner Land Trust, a California Corporation
By:
John Svahn, Executive Director