HomeMy WebLinkAbout13 Closeout Fireboard Pump Agenda Item # 13
DistrictPublic Utility
ACTION
To: Board of Directors
From: Ed Taylor
Date: February 04, 2009
Subject: Approve the Closeout of the Fibreboard Pump Development Project
1. WHY THIS MATTER IS BEFORE THE BOARD
The Fibreboard Well Drilling Pump Development and Testing Project is complete. A
closeout change order and a resolution accepting the project require Board approval.
2. HISTORY
The Board previously awarded the Fibreboard Well Drilling Pump Development &
Testing program to Carson Pump, LLC in an amount not to exceed $66,202.50
(includes 5% original change order authorization).
3. NEW INFORMATION
Well development and testing began in November 2008 after the well drilling was
complete. As of December 2008 all portions of the pump development are complete.
Staff is now requesting Board authority to file a formal Notice of Completion.
A closeout change order is requested for this Contract. The changes to the contract
include:
• An increase of $14,000 for the use of a drilling mud dispersant compound and
seven extra hours of test pumping
• A decrease of $9,425 due to a reduction of 20 hours of development pumping
and 2.5 hours of step draw down pumping
These changes result in a net increase of $4,575 and a revised Contract total of
$67,625.
4. FISCAL IMPACT
A change order in the amount of $4,575.00 will bring the new contract total to
$67,625.00, which exceeds the total approved contract amount of $66,202.50
(includes 5% original change order authorization). Sufficient funds exist in facilities
fees to fund this change order.
5. RECOMMENDATION
a) Authorize Contract Change Order No. 1, in the amount of$4,575.00 to Carson
Pump LLC
b) Authorize the transfer of$4,575 from facilities fees to the Water General Fund
c) Adopt the attached draft resolution accepting the Fibreboard Well Drilling
Pump Development and Testing program as complete and authorize staff to file
the Notice of Completion
Ed Taylor Michael D. Holley
Water Utility Manager General Manager
Jan-29-2009 09:41am From-TRWKEE DONNER PUD +5206871199 T-018 P.001/001 F-838
TRUCKEE DONNER , Change Order
Contract Name: _Pump Development and Testima Program for the Fibreboard Well
Contract Change Order No: 1 Orig.Contract Amt.$ 63,050.00 Days NA
Date: January 28,2009 Prev.Apprd Changes$ 0.00 pays NA
Contractor: Carson Pump This Change$ 4.576-00 Days NA
Revised Contract Amt$ 67,825.00 Days NA
This Change Order covers changes to the subject Contract as described hereln. the Contractor shall construct,
furnish equipment and materials, and perform all work as necessary or required to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District.
Increase in (Decrease) Contract Time
CWwription of Changes Contract in Contract Extension
Amount W Amount M da
■ Conduct dual swab pump development,(-12 Hours) -$3,300.00 N/A
■ Furnish 30 gallons of Johnsons,NW-220 mud dispersant $3,450,00 NIA
chemical
■ Install tremme pipe to 1,0o0 $1,000.00 NIA
■ Mix and inject NW-220 at various levels $1,200.00 NIA
■ Line swab well for 5 hrs to work In chemical $1,200.00 NIA
• Furnish,install,and remove test pump(estimate pump $5,400.00 WA
setting at 360 ft)
■ Conduct pump development program(-20 Hours) -46,500.00 N/A
■ Conduct Step-Drawdown Pumping Test(-2.5) 4625.00 NIA
■ Conduct Constant-Discharge Pumping Test,(7 fours) $1,750.00 WA
Totals $.14,000.00 49,425.00 N/A
Net change in contract amount(increase or decrease) $4,515.00 NIA
The amount of the Contract will be increased by the sum of $4,579-00 and the Contract Time shall not be
extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item including any and all supervision costs and other miscellaneous costs
relating to the change In work, and as to the extension of time allowed, if any,.for completion of the entire work on
account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other
necessary work, inclusive of the directly or indirectly related to the approved time extension,required to complete
the Change order items. This document will become a supplement of the contract and all provisions will apply
hereto. It is understood that the Change Order Shall be effective when approved by the District_
Accepted: /Ccttitrector F3ata: /
(Signature)
Approved: /District Date:
(Signature)
Page 1
k
CKEE r DONNER
�- PLAAC Utility District
Resolution No. 2009 - XX
AUTHORIZING THE ACCEPTANCE OF
THE FIBREBOARD PRODUCTION WELL PUMP DEVELOPMENT &
TESTING PROGRAM AND DIRECTING FILING OF THE NOTICE
OF COMPLETION
WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to
undertake the Fibreboard Production Well Pump Development& Testing Program; and
WHEREAS, Carson Pump, LLC was selected by the District to perform the work; and
WHEREAS, Carson Pump, LLC has completed all of the Work included in the Project; and
WHEREAS, The District's Consultant, David Carlson of Aqua Hyd rogeolog ic Consulting, now certifies the
completion of the project; and
WHEREAS,the District's Water Utility Manager, Ed Taylor, has recommended that the work be accepted bythe
District;
NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows:
1. That the District hereby accepts the Fibreboard Production Well Pump Development&Testing Program
as complete.
2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a
copy of which is attached hereto.
3. That 35 days following the filing of the Notice of Completion, the monies retained from the contractor
payments be released to the contractor if no claims have been made to the District by material suppliers or
laborers.
PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the 0
day of February 2009 by the following roll call vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
J. Ron Hemig, President of the Board
ATTEST:
Michael D. Holley, Clerk of the Board
RECORDING REQUESTED BY:
Truckee Donner Public Utility District
WHEN RECORDED, RETURN TO:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
Barbara Cahill
Post Office Box 309
Truckee, CA 96160
THE UNDERSIGNED DECLARES
DOCUMENTARY TRANSFER TAX-NONE
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. That the name and address of the public entity for whom the improvement project was done, as owner
thereof, is the Truckee Donner Public Utility District, Post Office Box 309, Truckee, CA 96160.
2. Nature of interest or estate of owner: beneficial interest of a public utility easement for installation of water
facilities.
3. That on February 4th, 2009 the hereinafter described improvements were accepted as complete
pursuant to Resolution 2009-XX of the Truckee Donner Public Utility District, the awarding authority.
4. That the subject improvements of the Notice are generally described and identified as follows:
The pump development and testing program of a production well completed to a depth of
approximately 1,200 feet.
5. That the name and address of the contractor for such project was: Carson Pump, LLC, P.O. Box
20159, Carson City, NV 89721-0159.
1 certify under penalty of perjury under the laws of the State of
California that the foregoing is true and correct.
Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
Michael D. Holley, General Manager
MAIL TAX STATEMENTS TO:
SAME AS ABOVE
Legal References: CC-3093,CCP-2003 (oath), 2015.5 (unsworn statement)