Loading...
HomeMy WebLinkAbout9 Firewall Upgrade ACTION ITEM #to Upgrade Network FirewallsInfobondContacts with Fortinet and Consideration of Approving to Upgrade Network FirewallsInfobondContacts with Fortinet and Consideration of Approving July 18, 2018 9 Contracts to Upgrade Network Firewalls Calls for Firewall replacement in 2018•District Master IT Plan (2017)•firewall implemented in 2011Existing •firewall technology evolves quicklyNetwork •protection from attackMission critical services require •Firewalls are District’s first line of cyber defense•BACKGROUND / HISTORY Contracts to Upgrade Network Firewalls NEW INFORMATION encryption-Current Firewall incapable of performing de•encryption for security analysis-Traffic will now be encrypted; requires de•Google Chrome will require websites to use SSL security•, 2018 presents a defining change in the Web. th August 27•iskrIncreased security •Three examples•Significant risk to District without upgrades•Contracts to Upgrade Network FirewallsContracts to Upgrade Network Firewalls NEW INFORMATION and increase ability to find anomaliesProvide better insight, reporting•security visual design improvements-New firewall has cyber•segmentation from switches to firewallNeed to move •Need to identify bad traffic quicker•S•VPN technology is integrated in the Firewall•Recent scans show existing VPN technology a security risk•District required to secure network for credit card use•equirementsrPCI compliancy •Contracts to Upgrade Network FirewallsContracts to Upgrade Network Firewalls NEW INFORMATION$155,718Total16,600$ ServicesProfessional CMASInfobond12,816$ Firewall NetworkCMASFortinet126,302$FirewallCMASFortinetAmountDescriptionContractVendor procurements(Services) are CMAS InfobondQuotes from Fortinet (Hardware) & •District allows procured through CMAS (District Code 3.08.060)•Fortinet has the best cost/value ratio to the District•Staff has evaluated industry leading firewalls•Contracts to Upgrade Network FirewallsContracts to Upgrade Network Firewalls FISCAL IMPACT procurementUtility FY18 Electric the Board adopted funds exist in Sufficient •Contracts to Upgrade Network FirewallsContracts to Upgrade Network Firewalls RECOMMENDATION authorization for a total not to exceed contract amount of $18,260.professional services in an amount of $16,600 plus a 10% change order for Infobond2) Authorize the General Manager to execute a contract with amount of $153,030; and10% change order authorization for a total not to exceed contract firewall hardware, software licenses, in an amount of $139,118 plus a Authorize the General Manager to execute a contract with Fortinet for 1) Contracts to Upgrade Network FirewallsContracts to Upgrade Network Firewalls