HomeMy WebLinkAbout9, Consideration of Regulator Purchase
ACTION ITEM #9Substation Voltage RegulatorsContract for the Procurement of Consideration to Approve a Substation Voltage RegulatorsContract for the Procurement of Consideration to Approve
a September 05, 2018
Consideration to Approve a Contract for the repairThese units show signs of aging and require frequent maintenance and •Useful equipment life is up to 30 years•Existing voltage regulators
were installed in 1998•BACKGROUND / HISTORY Procurement of Substation Voltage RegulatorsConsideration to Approve a Contract for the Procurement of Substation Voltage Regulators
NEW INFORMATION Yes$110,968BeniciaAnixterResponsiveAmountLocationBidder Summary of bid information is shown below•Bids sent out August 2 and advertised in Sierra Sun August 10•Procurement
of Substation Voltage RegulatorsConsideration to Approve a Contract for the Procurement of Substation Voltage RegulatorsConsideration to Approve a Contract for the
FISCAL IMPACT Capital Budget for this procurementSufficient funds exist in Board Approved Electric Utility’s FY18 •Procurement of Substation Voltage RegulatorsConsideration to Approve
a Contract for the Procurement of Substation Voltage RegulatorsConsideration to Approve a Contract for the
RECOMMENDATION plus taxexceed contract amount of $122,065, $110,968, plus a 10% change order authorization for a total not to the Purchase of Substation Voltage Regulators, in an amount
of Authorize the General Manager to execute a contract with Anixter for •Procurement of Substation Voltage RegulatorsConsideration to Approve a Contract for the Procurement of Substation
Voltage RegulatorsConsideration to Approve a Contract for the