Consent Item # 7 August 20, 2014 Rehabilitation projectSpring Street Pipeline Final Completion of the
Final Completion of the Spring Street 2 Streetscape projectProject to be completed prior to Town of Truckee’s •Replaced one service lateral–Sliplined about 430 feet of existing 10” pipe
with new 6” pipe–The Spring Street Pipeline Rehabilitation project:•Background / History Pipeline Rehabilitation Project
Final Completion of the Spring Street 3 Truckee with a bid price of $59,200In May 2014, contract was awarded to Aspen Developers of •Change order allowance of up to $6,000–Base contract
of up to $60,000 –construction contractIn April 2014, the Board authorized award of the •Background / History Pipeline Rehabilitation Project
New Information Pipeline Rehabilitation ProjectFinal Completion of the Spring Street 4$2,834 credit to the District–Reconciliation of bid vs. actual quantities–Cost of $4,500–DistrictInstallation
of an additional 26 feet of pipe at the request of the –Two change orders•July 1, 2014Construction began in late May and was completed on •
Fiscal Impact$60,866Total($2,834)Bid vs. Actual Quantities–CO Item No. 2 $4,500Additional Pipe –CO Item No. 1 $59,200Bid PriceOriginalAmountItem Pipeline Rehabilitation ProjectFinal
Completion of the Spring Street 5$60,866Original bid price was $59,200. Final contract amount is •
Recommendation Pipeline Rehabilitation ProjectFinal Completion of the Spring Street 6 Authorize filing of the Notice of Completion•project as completePipeline RehabilitationSpring Street
-Adopt a Resolution 2014•