HomeMy WebLinkAbout12 Pioneer Trail Pipeline - Award'400 TRUCKEE DONNER AGENDA
Public Utility District
MEETING DATE: June 1, 2022
TO: Board of Directors
FROM: Neil Kaufman, Water System Engineer
Chad Reed, Water Utility Director
SUBJECT: Consideration of the Pioneer Trail Pipeline Construction Contract
�/
APPROVED BY
Brian C. Wright, General Manager
RECOMMENDATION:
Authorize the General Manager to execute a contract with C&D Contractors in an amount
of $4,497,043, plus a ten percent change order allowance for a total authorization not to
exceed $4,950,000 for the Pioneer Trail Pipeline Project
BACKGROUND:
The Tahoe Donner subdivision consists of approximately 5,600 single family homes,
about 400 multi -family residential units, a golf course, downhill ski area, cross-country ski
area and other amenities. This represents about 44% of the water system customers.
An additional 500 residential units are expected in the Tahoe Donner area at buildout
conditions. The entire subdivision is served by a single 14" welded steel pipeline with two
pump stations and two storage tanks that essentially serve as forebays. These facilities
were constructed in the early 1970s and are approaching the end of their useful life.
The District previously identified the need to construct a second pipeline into Tahoe
Donner. This project was planned for and discussed in the current Water System Master
Plan (Master Plan). The Master Plan identified the need for a 20" pipeline, but more
recent estimates of buildout water demand have determined that the pipeline can be
downsized to 16" diameter.
On the eastern end, the new pipeline will connect to an existing 24" pipe near Pioneer
Trail and Comstock Drive. The western end will connect to an existing 16" pipe at the
intersection of Northwoods Boulevard and Lamplighter Way. Additionally, in alignment
with the Strategic Plan, the District intends to install electrical and communications
Page 1 of 4
conduits in a joint trench with the water pipeline in preparation for future electric
distribution system redundancy and fiber communication network completion.
A new pump station will be needed to lift water into the Tahoe Donner area. The planned
location for the pump station is on District -owned property in close proximity to the TNT
Materials concrete batch plant. The project has been broken into two separate
construction contracts — one covering the pump station and the other covering the pipeline
and conduits.
The Board previously awarded three contracts with outside consulting firms associated
with this project:
• In November 2020, a contract was awarded Water Works Engineers (WWE) to
provide design assistance with the crossing of Trout Creek and performance of a
hydraulic transient analysis.
• In October 2021, a contract was awarded to Sauers Engineering to design the
pump station.
• In October 2021, a contract was awarded to Helix Environmental Consulting to
perform the environmental review of the project.
The CEQA Initial Study/Mitigated Negative Declaration (IS/MND) was made public on
March 12, 2022 and the public comment period closed on April 12, 2022. On May 4,
2022, the Board of Directors approved the project for the purposes of CEQA.
On April 18, 2022, the District began advertising for bids for the pipeline construction
contract. The bid opening was held at 2:00 PM on May 19, 2022. Two bids were received:
TOTAL AMOUNT OF BID
Bidder
Location
Amount
Responsive
C&D Contractors
Nevada City, CA
$4,497,043
Yes
Burdick Excavating
Carson City, NV
$5,296,845
Yes
As noted above, this is a joint project between the Water Department and the Electric
Department. The overall project scope includes:
• Approximately 8,150 feet of 16-inch water pipe
• Approximately 7,800 feet of 6-inch and 2-inch conduit
• Five fire hydrants
• Valves and pipe fittings
• Eleven primary power vaults and one switchpad
• Construction of a utility crossing of Trout Creek on the existing bridge
Page 2 of 4
A tentative construction timeline has been set. Due to the long lead time for acquiring 16-
inch water pipe, the great majority of the project construction will occur during the summer
of 2023. Work completed in the summer of 2022 will include the Trout Creek utility
crossing and the installation of a valve at the east end of the pipeline that will serve as
the interface between the pipeline and pump station construction contracts. On April 6,
2022, the Board approved the purchase of the water piping materials for this work. The
contractor will be responsible for obtaining all other materials for the project.
The District has received the 95% design submittal from Sauers Engineering for the pump
station project. It is expected that advertising for bids will begin in early June with a bid
opening planned for early July.
ANALYSIS/BODY:
Part of the mission statement of the District is to "provide reliable, high quality
water ... while meeting customer demand." The Pioneer Trail Pipeline project exemplifies
this by adding additional reliability and redundancy to the water system for the customers
in the Tahoe Donner community and removes the potential single point of failure.
Over the past year staff has seen several projects come in over the engineers estimate
including those incorporated into the water utility capital improvement plan. Often these
overages have been several times the anticipated cost due to increasing materials and
labor costs. This project is over the estimated budget however, staff is recommending to
move forward with this project due to the redundancy it provides in both potable water
deliveries and fire flow protection to more than 6,000 customers. Additionally, the second
pipeline significantly limits the risk of a catastrophic failure of the existing pipeline
constructed nearly 50 years ago.
Staff is recommending the additional electrical and communication conduit installations
OBJECTIVES & GOALS:
This item is in support of the following goals and objectives:
District Code1.05.020 Objectives:
3. Provide reliable and high quality water supply and distribution system to meet current
and future needs.
Strategic Goals:
1. Manage for Financial Stability and Resiliency
FISCAL IMPACT:
The bid price from C&D Contractors is $4,497,043. It is recommended that a ten percent
change order allowance be established for a total authorization of $4,950,000.
Page 3 of 4
Using the individual bid items from the bid schedule and C&D bid prices, the cost
allocation between the Water Department and Electric Department was calculated and is
given in the table below:
Amount
Percentage
Water Department
$ 3,613,391
80.4%
Electric Department
$ 883,652
19.6%
Change Order
$452,957
10%
Total
$4,950,000
110%
The Water Department budget includes $2,555,000 for the Pioneer Trail Pipeline in 2022.
With this bid, the water department's portion of cost including potential change orders is
$3,980,000. The increase in cost of $1,425,000 is projected to be absorbed over -time
within the 10-year capital improvement plan, due to the timing of projects over future
years.
The commitment to the Pioneer Trail Pipeline project also commits the District to the
Pioneer Trail Pump Station project, which has a budget of $2,865,000 ($350,000 in
Budget 2022 and $2,515,000 in Budget 2023). As noted above, the bid documents for
the pump station are still being finalized and the project has not yet been placed out to
bid. Both projects are budgeted and recommended to be funded by the water new debt
issuance.
The Electric Department portion of this project ($970,000 including potential change
orders) is not specifically budgeted in Electric's capital improvement plan or Budget 2022
& 2023. Sufficient funds for this expenditure are available in the Electric Department
capital reserve, which had a balance of $11.3 million as of December 31, 2021.
ATTACHMENT:
None
Page 4 of 4