Loading...
HomeMy WebLinkAbout13 Red Mountain Tank Project Final PaymentAM TRUCKEE DONNERAGENDA Public Utility District MEETING DATE: June 1, 2022 TO: Board of Directors FROM: Neil Kaufman, Water System Engineer Chad Reed, Water Utility Director SUBJECT: Consideration of Accepting the Red Mountain Tank Construction Project as Complete and authorize Payment of Reimbursable Costs APPROVED BY Brian C. Wright, General Manager RECOMMENDATION: Accept the Red Mountain Tank Construction Project as complete and authorize payment of reimbursable costs in accordance with the Board approved Phase 3 Final Development and Reimbursement Agreement Between the Truckee Donner Public Utility District and Coldstream Properties, LLC for Construction of Certain Potable Water System Improvements BACKGROUND: At the August 5, 2020 meeting, the Board approved an amendment to the Coldstream Development and Reimbursement Agreement between the District and Coldstream Properties, LLC for the construction of certain potable water system improvements associated with Phase 3 of the Coldstream Development (PC-1). The water utility system improvements included the on -site water utility distribution system infrastructure within the development's Phase 3 parcels, as well as the design and construction of a potable water storage tank at the Red Mountain site, which is located on the south side of Donner Lake. A copy of the First Amendment to the agreement has been included with this report as Attachment 1 In June, 2020, the developer had issued a request for bids for the construction of the Red Mountain Tank. The scope of work included the construction of a welded steel potable water storage tank as well as site work such as grading, foundation construction and the associated underground piping. Following review of bids for compliance with District standards and specifications, contractor experience and familiarity with similar projects in Page 1 of 4 the region, and proposed construction schedules, the developer with approval from staff, identified Crosno Construction from Arroyo Grande, CA as the most favorable contractor for the project. The total bid price for the tank project was $869,820. The development agreement outlines specific provisions for reimbursements to the developer for construction of the storage tank. An initial change order allowance of ten percent ($86,982) was included in reimbursement agreement. Section 3.1 of the First Amendment to Phase 3 Final Development Agreement and Reimbursement Agreement Between Truckee Donner Public Utility District and Coldstream Properties, LLC for Construction of Certain Potable Water System Improvements requires that "any Change Order that would increase the original amount owed under the Construction Contract by more than 10% may be approved by the District's Board of Directors." Construction of the tank began in June 2020. It was planned to complete all of the grading, tank foundation and site piping work during 2020. Work would then pause for the winter of 2020-21, with construction of the actual tank and completion of the project planned for the summer of 2021. A summary of the approved change orders is provided below: 1. The contractor encountered some difficulties during the site grading portion of the project involving large boulders and saturated soils. A number of discussions occurred involving Crosno, the developer and the District along with the design engineer and geotechnical engineer for the project. It was eventually agreed that Crosno was due an additional $55,428.68. This total covered the issues associated with the boulders and soils, along with some modifications to the site piping and additional rebar for the retaining wall at the site. 2. In June 2021, a change order for $26,551 was approved by District staff. This change order covered the addition of three items not included in the original design: • A safety handrail along the top of the retaining wall • A safety platform for improved access to the exterior tank ladder • A stilling well for level sensing instrumentation inside the tank NOTE: The total change order approvals at this point in the project were in the amount of $81, 979.68, which is approximately 9.4 % of the original contract amount. 3. In July 2021 staff was informed that the exterior coating system specifications included in the original project bids were not the optimum specifications for above ground welded steel tanks located in regions with climates similar to Truckee. Following further evaluation, staff determined that authorizing the upgrade in coating systems to be in the best interest of preserving the longevity of the new tank. Page 2 of 4 On July 21, 2021 the Board approved an increase in the total project change order authorization from 10% ($86,982) to 12% (104,379) establishing a new construction project total not to exceed $974,199. On April 11, 2022 the District received a written request for final acceptance of the project and payment for all reimbursable costs to date. A copy of the request for final acceptance has been included with this staff report as Attachment 2. Included with the request for final acceptance is a summary of the total reimbursable costs upon project completion (Attachment 3), totaling $1,075,135.37. This total includes the final construction costs as completed by Crosno Construction, Inc., Project Design Engineering completed by Sauers Engineering Inc., and geotechnical and construction inspection services provided by NV5 Engineering Services. Goals and Objectives: This item is in support of the following goals and objectives: District Code1.05.020 Objectives: 3. Provide reliable and high quality water supply and distribution system to meet current and future needs. Strateaic Goals: 1. Manage for Financial Stability and Resiliency ANALYSIS: The Red Mountain Storage Tank construction has been completed to the District's satisfaction. Staff have worked with Coldstream Properties, LLC., Teichert Construction Crosno Construction, Sauers Engineering and NV5 Engineering Services to ensure final inspections, testing and punch list items have all been completed in accordance with the development agreement, construction contract and District specifications. Following review of all construction as-builts, field inspections and testing, staff is recommending final acceptance of the project. As set forth in the Development Agreement entered into on June 10, 2020, and amended on August 6, 2020, Coldstream is entitled to reimbursement of actual costs to design and construct the Red Mountain Tank facilities. The final total for reimbursable construction costs is $1,075,135.37. In accordance with the amended reimbursement agreement $500,000 of the total project costs will be reimbursed by facilities fees collected from within the Coldstream Development. At the time of publication of this staff report, the total applicable facilities fees collected to date are $198,089.48. Any project costs in excess of the $500,000 facilities fee reimbursements will be paid by the District to Coldstream Properties LLC. in a lump sum payment following final acceptance of the tank facilities construction. Including the final change order of $100,936.37 identified in this staff report (pending Board approval), the lump sum payment due to Coldstream Properties, LLC. Following final acceptance is $575,135.37. Page 3 of 4 FISCAL IMPACT: The Red Mountain Tank Construction project was not included in FY2022-23 Water Budget but is being funded by the Phase 3 Final Development and Reimbursement Agreement between the Truckee Donner Public Utility District and Coldstream Properties, LLC for Construction of Certain Potable Water System Improvements and available funds as follows: • $500,000 - Facilities collected from the Cold Stream Properties Development (PC-1) ($198,089.48 to 3/11/2022 collected and currently payable) • $575,135.37 - Donner Lake Assessment District Improvement Fund (fund balance $101,178.28 post this payment) Attachments: 1. First Amendment to Phase 3 Final Development Agreement and Reimbursement Agreement Between the Truckee Donner Public Utility District and Coldstream Properties, LLC for Construction of Certain Potable Water System Improvements 2. Request for Final Acceptance of the Red Mountain Tank Construction Project from Coldsteam Properties, LLC 3. Summary of Actual Construction Costs for the Red Mountain Tank construction project Page 4 of 4